• No results found

Downstream upgrade challenges and solutions

N/A
N/A
Protected

Academic year: 2021

Share "Downstream upgrade challenges and solutions"

Copied!
14
0
0

Loading.... (view fulltext now)

Full text

(1)

Downstream upgrade –

challenges and

solutions

(2)

1 Including all owned daughter companies

Having a huge performance gap compared to world-class level,

Russian refineries started an unprecedented modernization

program in 2008

1

Context

Most of Russian Refineries are 30+

years old and require massive

upgrade in order to meet market

requirements of

Motor fuel quality standards

High-octane gasoline and

kerosene demand

Operational efficiency and

processing depth

SOURCE: RosStat, companies data, Kortes report, McKinsey analysis

Company

1

Number of units

to be built or

revamped

Budget 2010- 2020

USD billions

Other

Total

75

25

7

22

24

10

26

30

20

3

11

9

8

10

195

91

(3)

19 18 17 16 15 14 13 12 11 10 09 08 2007 20 Stage of gain in operating performance Stage of product quality improvement

Stage of major projects – building up volumes and processing depth

Major projects – growing depth

Upgrading, renovation and gain in performance

Growing scale of investments and increasing project complexity

bring companies to a high risk zone

2 Volume of investments in oil refining

Total investment volume – about USD 60 – 70 bln Total investment volume –

USD 25 bln

(4)

Even global oil majors have significant challenges to deliver on

time and within budget

3 SOURCE: Media data; market intelligence

-20

-10

0

10

20

30

40

50

60

70

Cost deviation

Percent deviation

Schedule deviation

Time deviation

+24 mos.

+18 mos.

+12 mos.

+6 mos.

0

-6 mos.

Medium

de-viation case

High

devia-tion case

Medium

de-viation case

High

devia-tion case

“As

plann-ed” case

“As

plann-ed” case

PETROLEUM EXAMPLE

(5)

Russian context puts additional risks on execution of large

CAPEX projects

4

Project

management

Design

Procurement

Construction

Challenges

Limited capabilities of managing major capital projects and absence of developed

owner organization

No integrated responsibility of Contractor for project results in the applied

contractual models (EPCM)

Non-developed project management processes and tool-set

Low accuracy of budget estimates

Limited experience in working with sophisticated technologies and shortage of

Russian design institutes’ capacities

Difficulties of getting local Authorities approval by foreign ЕРС companies

Owner’s unreadiness to transfer full responsibility for procurement to a contractor

Unfamiliarity with the Russian equipment suppliers market and difficulty in working

with Russian suppliers, especially for foreign ЕРС companies

Specifics of Russian logistics of equipment delivery

Rare success of foreign ЕРС companies managing Russian construction

companies

(6)

Most companies establish Central Units Responsible for Major

Projects

5

Goals of a Central Unit

Implement advanced project execution models using

the synergy of expertise of Russian and international

engineering and construction contractors

Ensure execution of major projects portfolio in

accordance to Q/C/D targets

Develop competence of owner organization for

managing major projects

Implement international standards of major project

management

Need to build

owner ability to

manage Large

Scale CAPEX

projects

(7)

Omsk Oil Refinery

Hydrocracker

Delayed coking unit

CDU/VDU unit

The ambitious goal of the Central CAPEX Unit in GPN is

execution of 6 large projects in parallel, on time and within

budget

6

17

15

13

14

16

2018

2012

Year

Moscow Oil Refinery

Hydrocracker

Flexicocker

Combined Complex

Distillation unit

5

6

2

3

1

4

Completion date

Effect from

1 month

schedule

reduction

for each

project

is USD 10 –

20 mln

(8)

Project Offices are directly reporting to Large Scale Projects

Directorate (LSPD)

7

Head of Project

offices

Head of Large Scale

Projects Directorate

Planning and

control

Engineering

Construction

Contracting and

Document

control

Procurement

Engineering

Planning and

control

Procurement

Organizational

development

Construction

6

(9)

Just recruiting personnel is insufficient:

Capability building effort is critical for team effectiveness

Orientation program

PM Basics

Functional trainings Stage-specific trainings

Functional modules

Target group: functional specialists

Objective:

Implement specific functional processes and tools

Define relationships between functional specialists and PO

Provider: PMC PM Basics

Target group: management of LSPD and PO

Objective: Implement fundamental processes and tools

Provider: Experts (e.g. McKinsey) Orientation program

Target group:

New comers and heads of interlinked units

Objective: Agree on key principles of the project management system

Provider: Experts (e.g. McKinsey)

Stage-specific modules

Target group: functional specialists

Objective:

Implement processes of a specific project stage

Develop interaction mechanisms

Transfer of stage specific competencies

Provider: PMC
(10)

РМС contractors were selected as the main expert support to

Project offices and a source of knowledge for capability building

9

Areas of work

Function

Interaction with FEED and EPC contractors

Document quality control process

Progress monitoring (reports, meetings, records)

Change order management

Interaction between different PO’s (in case of interrelated technical solutions)

Planning and control of project schedule

Identification and control of project costs

Risk management

Resource management (mobilization/demobilization/evaluation)

Taking decision on the selection of equipment and materials (total cost of

ownership analysis, demand analysis, LCC)

Selection of contractors (EPC, etc.)

Contract management

Document management

Creation of LSPD knowledge database

PMC provides experts for particular areas of expertise in the absence of qualified

employees in the PO structure

Organization and

coordination of

works

Project

Management

knowledge base

Extensive technical

expertise

(11)

Implementation of international standards for large projects

management is one of the key tasks of the Central CAPEX Unit

10

Pre-study

Base project

FEED

ЕРС/EPCM

Operation

Purchase of

equipment

Feasibility study

Selecting construction

contractor

Strategy

Purchase of the LLI

equipment

Selecting EPC

contractor

Development of the

FEED/PD

Detailed design

Construction

Project implementation

model

Basic engineering

Selecting licensor

Selecting PMC

Selecting FEED/ PD

designer

Commissioning

Reporting on the status of projects

Codification of knowledge

Post-investment

monitoring and

evaluation

Procedure of going though all stages of the project

McKinsey – hired to support

Central Unit in this area

(12)

Applied contractual models (EPCM) do not provide

end-to-end responsibility of EPCs for project results

11 Responsibility Full Partial None Context Partial responsibility

Technical solutions

Timing: analysis of suppliers proposals

Budget D es ign P rocu rement C on str uc ti on Partial responsibility

Technical solutions

Timing: preparation of construction plan

Budget Full responsibility

Technical solutions

Timing

Budget

World practice – model with integrated responsibility Full responsibility

Technical solutions

Timing

Budget At the moment, EPCM scheme

has been approved as the standard contract model

Reasons behind the decision:

Lack of experience of Russian Owners in the implementation of major projects under the EPC model on the turn-key basis

No guarantees that the interests of the Owner during the procurement process will be carried out by the

contractor (P)

Insufficient experience of EPC companies with domestic manufacturers

Complexity of managing Russian construction contractors by western EPC companies

Limitation on use of foreign construction contractors

Responsibility of EPC contractor in the EPCM contract model Existing contractual model has to be upgraded in order to reflect end-to-end responsibility of contractor

(13)

Changing the model to “more EPC-like” has a potential

to reduce time and improve return on investments

12 Actions

New EPC model is syndicated with stakeholders

Upgraded EPC model aimed at reducing time while also taking into account measures to overcome the limitations

Owner concentrates resources on preparation of effective contractor relationships and control of critical commercial and technical issues

Responsibility Full Partial None Extended responsibility

Technical solutions

Timing

Budget (under the corporate Procurement) D es ign P rocu rement C on str uc ti on Extended responsibility

Technical solutions

Timing

Budget (under the LSPD control) Full responsibility

Technical solutions

Timing

Budget

Model 2 – EPC For projects/objects with defined scope of work

Full responsibility

Technical solutions

Timing

Budget Model 1 – EPCM

For projects/objects with

undefined scope of work Next steps

To assess the market of contractors in order to determine a possibility of

competitive

contractor selection for the proposed contract models to individual utilities, infrastructure and off-sites objects

To submit to the executive board a proposal for contract models for each type of objects with a pricing scheme for each type of work
(14)

Companies which can provide high quality services for large

projects are well known and their choice list is rather limited

13

NOT EXHAUSTIVE

Key selection criteria

Licensors

Operational efficiency

CAPEX

Technology expertise

Time of Basic design

Warranty terms

Russian

Design

Institutes

Experience in implementing similar projects in Russia

Good track of record of work with GPN

Successful experience in managing Russian state review procedures

FEED/EPC

Successful experience in implementing similar technology projects

globally and in Russia

Commercial terms

Proposed approach of project execution (technical and organizational)

Network and expertise of the subcontractors

PMC

Expertise of the team

Commercial terms

Positive experience of implementing similar projects globally and PMC

experience in Russia

References

Related documents

2008, 2009, 2011 IN+ Center for Innovation, Technology and Policy Research and Instituto Superior Técnico – Technical University of Lisbon, Portugal. 2008 Copenhagen

Despite being asked to visualise the future of a post-Brexit Britain, the great major- ity of participants returned artworks which focused on the ‘here and now’: Brexit as a

 Standard Enquiry Form (Dynamic)  Enquiry Form Program (Dynamic)  Product Pages with 50 Photographs  Customer provided Logo..  Image

There is a relationship in medication error rates between documenting medications given by using an electronic nursing note compared to using BCMA technology for patients ordered to

Laurence parishioners, these food drives generated 6,000 pounds of food to refill the Social Concerns Ministry pantry for Village families and people in crisis; 8,000 pounds of

The 30 th YMCA Advanced Studies Program organized by the Asia and Pacific Alliance of YMCAs will be held from 5 th to 30 th November 2012 at YMCA Wu Kwai Sha Youth Village in

Modelo de diseño Modelo de diseño Payment amount Sale date time Pays-for UP Domain Model.. Stakeholder's view of the noteworthy concepts in

We present a secure file sharing application that does satisfy the above requirements. Each user downloads her workstation’s configuration file and its public key to her mobile