Work Breakdown
Structure
Project Scope Management
• Includes the processes required to ensure
that the project includes all the work
required, and only the work required, to
complete the project successfully
– Collect Requirements
– Define Scope
– Create Work Breakdown Structure (WBS)
– Verify Scope
Planning Processes
Work Breakdown
Structure with RAM
Estimate Duration
and Resources
Network Analysis
Schedule Development
Project Baseline
A deliverable-oriented
grouping of project elements
that organizes and defines
the total work scope of the
project. Each descending
level represents an
increasingly detailed
definition of the project work.
PMBOK® Guide Definition
The tool for breaking down a
project into its component parts
(work package).
It is the foundation of project
planning and one of the most
important techniques used in
project management.
Project X
Software
Development
Prepare
Func.Specs.
Approve
Requirements
Prepare
Test plan
Prepare
Test data
Conduct
Testing
Code
Programs
Customer
Requirements
Acceptance
Testing
Testing
Training
WBS in Graphical Form
1.2.2.1 Dig trenches 1.2.2.2 Install pipe & hardware 1.2.2.3 Cover sprinkler system 1.2.3.1 Remove debris 1.2.3.2 Prepare soil 1.2.3.3 Plant lawn seed 1.3.2.1 Mark fence line & post 1.3.2.2 Install post 1.3.2.3 Install fencing & gates 1.3.2.4 Paint fence 1.3.1 Acquire fence material 1.3.2 Construct fence 1.2.1 Acquire lawn material 1.2.2 Install sprinkler system 1.2.3 Plant grass 1.2.4 Plant shrubs 1.1 Design home landscape 1.2 Put in lawn 1.3 Build fence 1.0 Home Landscape project
WBS in Graphical Form
1.
Software Development
1.1 Customer Requirements
1.1.1
Approve Requirements
1.1.2
Prepare Functional Specifications
1.2 Code Programs
1.3 Testing
1.3.1
Prepare Test Plan
1.3.2
Prepare Test Data
1.3.3
Conduct Testing
1.4 Training
1.5 Acceptance Testing
1.0 Home Landscaping Project
1.1 Design home landscape
1.2 Put in lawn
1.2.1 Acquire lawn material
1.2.2 Install sprinkler system
1.2.2.1 Dig trenches
1.2.2.2 Install pipe and hardware
1.2.2.3 Cover sprinkler system
1.2.3 Plant grass
1.2.3.1 Remove debris
1.2.3.2 Prepare soil
1.2.3.3 Plant lawn seed
1.2.4 Plant shrubs
1.3 Build fence
1.3.1 Acquire fence material
1.3.2 Construct fence
1.3.2.1 Mark fence line and post
1.3.2.2 Install post
1.3.2.3 Install fencing and gates
1.3.2.4 Paint fence
Provides a detailed
illustration of the
project scope
Create accurate cost
and schedule
estimates
Monitor progress
easily
Basis for building
project teams
WBS must be broken
down starting at the
top
Work packages must
add up to the summary
task (100% Rule)
Each summary task
and work package
must be named an
activity that produces a
product (use SMART
Technique)
specific
measurable
agreed upon
realistic
time-bound
Criteria for a Successful WBS
S
M
A
R
T
Planning Processes
Work Breakdown
Structure with RAM
Estimate Duration
and Resources
Network Analysis
Schedule Development
Project Baseline
Factors Affecting Resource Estimating
Work Methodology
Statutory Requirements
Specifications
Project Duration
Estimating Work Process
Alignment Scope of Work Prepare Estimate Document Estimate Review Estimate Adjust Estimate? Project Execution Project Completion Establish Standards Database Revise Estimate(Based on External Review) Yes
Reality Check (Based on Internal Review)
Lessons Learned for Continuous Improvement
Estimate Feed-back for Continuous Improvement