• No results found

Program Life Cycle Cost Driver Model (LCCDM) Daniel W. Miles, General Physics, June 2008

N/A
N/A
Protected

Academic year: 2021

Share "Program Life Cycle Cost Driver Model (LCCDM) Daniel W. Miles, General Physics, June 2008"

Copied!
10
0
0

Loading.... (view fulltext now)

Full text

(1)

Program Life Cycle Cost Driver Model (LCCDM)

Daniel W. Miles, General Physics, June 2008

Introduction

Several years ago during the creation of the Periscope Total Ownership Cost (TOC) Program, it became very apparent that existing government processes and methods to assess TOC were not “user-friendly”. Documentation requirements were excessively detailed and difficult to use and, due to time constraints, most efforts were initially expended in interpreting these documentation requirements. Under these circumstances, it was very difficult to effectively provide a better understanding of the underlying program infrastructure costs and associated cost drivers that factor into the TOC process.

The development by General Physics Corporation (GP) of the P5 Cost Driver Model (CDM) subsequently provided a much needed TOC management tool to organize program cost data in a more efficient manner. The model distinguishes all program TOC factors as belonging to one of five possible basic cost driver categories — People, Paper, Parts, Performance, and Places. This classification approach provides for an easily understood graphical presentation of the five cost driver areas relative to TOC and enables a method to formulate and track the impact of specific cost drivers throughout program life-cycle activities for facilitating the development of cost reduction initiatives. With this insight, GP was able to interpret cost driver information that reduced program infrastructure and R&D costs and converted the savings into revenue flow for the program. The chart format in Figure 1 illustrates a typical generic example of profiling each of the five basic cost driver categories grouped together as a percentage of the total program expenditure. Several subcategories combine together to form each of these five main categories and will be broken down in more detail below.

Figure 1 – Generic Cost Driver Pie-Chart Profile

20%

20%

20% 20%

20%

People Paper Parts Performance Places

(2)

Phase Transitioning

Implementation of the Cost Driver Model on a cradle-to-grave government program usually involves segregating all identified costs into three logical life-cycle phases and constructing separate cost driver profiles typified by the following three chart figures. The first profile contains all Research, Development, Test, and Evaluation (RDT&E) costs which occur prior to the Acquisition (purchase) phase. This profile is typically dominated by non-recurring engineering design costs grouped within the Performance driver which directly affect the achievement of some operational requirement or performance specification. Figure 2 illustrates this point and also shows the relative representation of the impact to the total amount from the remaining cost drivers at this initial stage of sustainment.

Figure 2 – RDT&E Profile

The second profile contains all Acquisition costs required to purchase and install the system. Figure 3 illustrates percentages of costs from the model at this stage of the life-cycle sustainment. This profile now reflects the transition from a performance dominated phase to one exhibiting an increase in recurring costs such as Parts, system materials (fabricate or manufacture), and that of People required to build, install, and verify (test) system operation.

Figure 3 – Acquisition Profile

27%

9%

11% 51%

2%

People Paper Parts Performance Places

40%

19% 20%

17% 4%

People Paper Parts Performance Places

(3)

The third profile contains all Operation and Support costs necessary to maintain the system throughout its in-service life-span. Figure 4 illustrates the percentages of the cost drivers at this final stage of sustainment. The profile has now transitioned to one dominated by Parts costs. The maintenance actions of upgrades, technology refreshes, and repairs will exist until the entire system is replaced.

Figure 4 – Operation and Support Profile

In summary, all government programs follow an established sequence of transitional phases. Modeling of commercial programs appear to follow the same process, however different external forces affect the transition. Based on GP’s years of use with the Cost Driver Model, the following conclusions have been drawn:

• For any organization/project, People costs assume a range of 20% – 25% (with the exception of the Acquisition profile) for success. If the cost is below 18%, the organization/project slows down and becomes inefficient. If the costs are over 30%, the organization is either wasting or paying too much for resources.

• For any project, Paper costs are significantly less for commercial systems than that of government systems, by as much as a factor of 10.

• For any project, Parts costs increase through all profiles. In non-hardware projects, i.e. services, the Parts costs still reflect the dominant cost in the Operation & Support profile.

• For any project, Performance costs decrease through all profiles. Projects with a continuous improvement process, appear to maintain a constant level of performance, but are simply implementing new RDT&E profiles for each improvement. Eventually, in any performance improvement project/organization, the core requirement of the continuous improvement process will eventually be superseded by technology advancements.

• For any organization/project, Places costs are dependent on the profile requirements, but should not be more than 5% in any profile.

24%

10% 60%

6% 0%

People Paper Parts Performance Places

(4)

Applying Cost Driver Modeling for Life Cycle Sustainment

The life-cycle of a project starts in the RDT&E phase, followed by the Acquisition phase, and ends with the Operation and Support (O&S) phase. Following each phase, the Cost Driver Model allows for a feedback loop to any of the previous phases. This important feature enables smart management of variable program costs resulting in the ability to predict optimal allocation of resources for maximizing downstream savings. Table 1 provides a rough estimate of phase costs as a percentage of TOC as well as the amount to possibly save with intelligent cost budgeting.

Table 1 – Approximate Savings to TOC According to Program Phases

PHASE PERCENTAGE (%)

OF TOC

PERCENTAGE (%) OF POTENTIAL SAVINGS

RDT&E 10 20

Acquisition 20 10

Operation and Support 70 40

Cost Driver Subcategory Breakdown

For each cost driver category there are associated cost functions. Table 2 illustrates an example of a government program where the cost functions for each of the five basic categories are explained. A similar table for commercial organizations/projects has been developed by GP.

Table 2 – Breakdown of Cost Driver Subcategories

Cost Drivers Cost Functions Explanation of Cost Functions

Management The number of people in a department drives the expense of managing. Installation

The major source of cost to the installation is that of the people required to

accomplish the task. Technical Support

Re-active response requirement, usually off-site, to assure that system level problems are addressed.

PEOPLE

Liaison

Pro-active response requirement on-site to assure that system level problems are

(5)

Cost Drivers Cost Functions Explanation of Cost Functions

Hardware System level components or a purchase requirement.

Spares Spares to system level components or a purchase requirement.

Software Required to support the system level components.

PARTS

Repair/Overhaul The action required to bring components to an RFI condition.

Facilities Areas where workers reside.

Laboratories Areas where development is conducted or equipment is maintained.

PLACES

Warehouses/Inventory Storage Areas

Areas where parts are maintained.

Engineering

Activities required to design a fix to a problem report/resolve a

deficiency/provide a system enhancement. SUBSAFE Activities/materials required to meet

SUBSAFE requirements.

PERFORMANCE

Quality

Assurance test activities required to demonstrate and verify system level performance.

Acquisitions Activities required to procure system level materials.

ILS Activities required to support logistics requirements for system level materials. CM Activities required to support configuration

management of system level materials.

PAPER

User Feedback

Activities required to

identify/maintain/report system level problem reports.

(6)

276 226

143 186

264 302

98 51 51

96 136

241 300

200

100 150

50 0

50 100 150 200 250 300 350

Accumulated Cost

($ Millions) 171

250 206

BREAK-EVEN BLOCK DRIVER BLOCK

PERFORMANCE BLOCK

COST BLOCK and LINKS PROCESS

Support &

Operation System

Baseline

Costs Support &

Operation System

New

OOM =

(7)

Objectives of the Life Cycle Cost Driver Model

The primary goal of the LCCDM process is to reduce costs in all phases of a program. To meet this goal, the model provides a metrics-based decision-making process created from meaningful data. The model also allows for smart assessments in the RDT&E and Acquisition phases that will minimize O&S costs. The modeling process evaluates the impact of technical cost drivers on performance, cost, and schedule. It supplements Earned Value Management (EVM) and risk factor identification by assessing cost driver elements through a Links process. It also supports achievement of the goals to reduce/meet the true break-even point by evaluating the technical progress towards achieving that goal.

Analytical Features of the Life Cycle Cost Driver Model

Figure 5 provides a visual generic presentation of the LCCDM illustrating all features of the process. The five blocks and links process are described below.

Performance Block

The performance block identifies the relative performance between a current baseline system and a proposed new system. The block provides a means to identify all requirements and compare them to existing or other proposed alternatives. The block allows the developer to determine if all requirements are met.

Performance Requirements New

SONAR System

Reference Document

Baseline Cost-Risk Value

(100%)

New System Cost-Risk Value

(100%)

MF Passive Common Spec 100 110

MF Active Common Spec 100 100

Transmit Group Common Spec 100 80

Self Noise Common Spec 100 95

Color Key

Green – System meets or exceeds existing system performance

Red – System does not meet existing system performance and needs to be fixed

Blue – System does not meet the existing system performance, however the required change is not cost effective requiring extensive system changes or a complete redesign

(8)

Driver Block

The driver block identifies the cost drivers of the proposed new system including risk mitigation costs and accelerators. An accelerator is an implementation of a project initiative that initially increases the cost within a phase but results in significant savings for follow-on phases thereby reducing program TOC. Utilizing the LCCDM Links functionality, the driver block aligns the proposed system elements between all three life-cycle sustainment phases. Reference sources of the data are required to support the analysis.

Cost Driver Cost Identifier Link Element Sub-Element

Integrated Product

Team (IPT) Risk Mitigation 10 Risk IPT

Sensors: Hydrophones Projectors

Driver: Minimal 31 Reliability Robustness

Connector/mold

configuration Driver: Moderate 401 Reliability Survivability

Cost Block

The cost block provides the media to assign projected, anticipated, and actual costs of the existing system with that of the proposed system. The costs are summarized to determine the total cost of any phase. The example provided is for Operation & Support (O&S) Costs.

Cost Driver Baseline

Cost

New System

Cost Sub Drivers

People 24%

Management

Financial Data Center Projects

Program

Personnel Installation

Implementation ALTS Certifications Planning

Installation Manager

Technical Assistance System Testing

System Integration Liaison

(9)

Performance 6%

Parts 60% Paper 10% Places < 1%

Links Process

The Links functionality generates cost driver/risk mitigation relationships for all identified elements in the model. The Links process also identifies relationships between the three phases of life-cycle costing, derives anticipated Link cost-multipliers, and implements accelerators that may result in cost increases/decreases based on decisions made during prior phases. The multiplier indicates the magnitude of such a potential reduction in cost savings. As indicated in Table 1, each phase has a different savings potential that could be achieved by implementing an accelerator initiative.

Output Ownership Metric (OOM) Block

The OOM block provides an assessment of how the changes made in the RDT&E and Acquisition phases are expected to affect O&S phase costs. A value greater than 1.0 indicates that the proposed new system will increase O&S costs above the current baseline system.

Break-Even/Learning Curve Analysis Block

The break-even/learning curve analysis block provides an accounting/earned value status as to the achievement in the Acquisition phase to recover the anticipated RDT&E project costs of a proposed new system. The graph in Figure 6 illustrates an example of break-even projection analysis for the GP cost driver model using realistic feedback that continuously fine-tunes cost driver relationships and updates model input data. This result is compared with a baseline projection (blue line) assuming a simple linear fixed-cost per system. An alternate analysis (red line) is also superimposed on the graph to show its projected breakeven point against the constant-sloped baseline. Although the alternate approach appears somewhat realistic by incorporating variable cost factors that reflect learning curve assumptions, it can actually lead to large errors in total cost expectations as the number of acquired systems increases. That is because of false (overly optimistic in

Support &

Operation System

Baseline

Costs Support &

Operation System

New = Metric Ownership

(10)

this case) input assumptions for values and relationships that multiply over time and generate significant offsets to the true break-even point.

Figure 6 – Break-Even/Learning Curve Projection Analysis for a Proposed RDT&E Project vs. a Current Baseline Acquisition System

276 226

143

186

264

302

98 51 51

96

136

241

300

200

100

150

50 0

0 50 100 150 200 250 300 350

Number of Acquired Systems Accumulated

Cost ($ Millions)

Cost Driver Model 51* 98 143 186 226 264 302

Alternate Analysis 51* 96 136 171 206 241 276

Baseline System 0 50 100 150 200 250 300

1 2 3 4 5 6

171

250

206

0

Total Acquisition Phase Cost Data ($M) as a function of Systems Acquired

Systems Acquired 0 1 2 3 4 5 6

Figure

Table 2 – Breakdown of Cost Driver Subcategories
Figure 6 – Break-Even/Learning Curve Projection Analysis for a Proposed  RDT&amp;E Project vs

References

Related documents

Secondly, encourage your sitters to talk about what they &#34;feel&#34; as they work through the method and the reading. Not only can this become quite eerie, b u t it can

Here we argue that they also offer a natural framework to understand stationary distributions of generic driven non-equilibrium systems that are composed of a driving- and a

single market are indivisible and separate negotiations between individual Member States and Britain on matters pertaining to the withdrawal of the United Kingdom from the

Effect of verapamil on atrial tachycardia resulting from A V nodal reentry'- The top trace in each section is an atrial electrogram recorded 2 mm from the atrial border of the AV

For achieving the goals of conservation of fisheries resources in general and secure the future of exploited fisheries, there is need for reducing fishing effort, application

Put differently, since scarcity of attention limits the love-of-variety gains in an IS-regime with partitioning of firms by their export status, trade liberalization may reduce

In the case of the multigroup multicast, in order to realize the simultaneous delivery of the different multicast programs for the corresponding groups of users in the same time

Te seismic design of bolted FRP panel-type (BFRPP) water- storage tanks subjected to seismic loads includes two aspects: the “loading side,”  which is the determination of seismic