M. Syal _2010
CHANGE ORDER
PROTOCOL
ELECTRI International
Prof. Matt Syal, Ph.D., LEED® AP
Construction Management
School of Planning, Design and Construction
Michigan State University
January 2013
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
PARTS OF THE PRESENTATION
1. Introduction
2. Justification
3. Goals and Objectives
4. Work Plan
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
Introduction
• Change orders are an essential part of every
construction project
• One of the main area of disagreement and,
even litigation, is their costing and pricing.
• All types of change orders can have these
disagreements but the unwritten change
orders with non-agreed upon price are
particularly prone to these
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
Total Cost
Direct Costs
Labor Material Equipment Profit
Home Office Costs Prep. Costs Overhead Consequential Costs Indirect Costs Field Supervisory Costs and Project Fees Labor Disruptions and Inefficiencies Project Delay and/or Acceleration Field Conditions and Others
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
Potential Consequential Cost Factors
I. Labor Related Disruptions and Inefficiencies
II. Project Delay and/or Acceleration
III. Field Condition and Others
Interferences and disruptions Acceleration Season and weather change Strikes Project delay costs: capacity
issues
Working in finished areas Stacking of trades Project delay costs: lost
opportunity costs
Suspension of work Morale and attitude Project delay costs: cash flow
interruption
Havoc in purchasing materials Reassignment of manpower Project delay costs: retainage
release
Increased contract administration Crew size inefficiency Altered anticipated sequences or
conditions
Increased job cost accounting Errors, omission and mistakes Canceled contracts Extra manpower requirements Fatigue Lost profit Congested drawings
Overtime Ripple effect Negotiation cost
Aggravation and stress Others Adverse impacts caused by others Others Coordination time
Logistics Others
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
Justification
• The single most area of dispute in the
change order process is the cost
• Majority of these disagreements are due to:
o
Lack of standardized process for overall costing
and pricing of change orders
o
what costs to include as the direct costs and
what to include as the overhead costs
o
what are the consequential/impact costs and
how to quantify them in the change order
pricing
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
Justification (cont.)
• Recently, the NECA chapter of Greater Toronto, jointly with other Canadian subcontractors associations, took the lead in developing a “Change Order Protocol” document.
• I understand that the Toronto documents is pretty
successful in streamlining the change order process for NECA and other subcontractor groups in Canada
• Many feel that a similar and expanded effort in the U.S. will be beneficial for the industry
• Giovanni Marcelli and I jointly presented a seminar at
recent NECA Convention on the overall change order topic and introduced the Canadian document to the participants. It led to a strong request by the participants to undertake this effort for the U.S.
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
Justification (cont.)
• Below is an email received from a NECA member
and it is representative of several similar inquiries.
Dear Dr. Syal and Mr. Marcelli:
I had the opportunity to attend the talk on change order protocol given by you at the recent NECA convention. Your presentation painted a hopeful road map for resolving many of the problems facing our industry
concerning change orders. I was wondering, after downloading and
reading the document "Change Order Protocol" if there were any plans for releasing a "U.S." version (vs. the "Canadian" version) of that document. I would very much like to use such a document as the basis for starting
discussions with our local architects, and the document would carry much more weight with them if the document referenced the corresponding AIA General Conditions, U.S. legislated labor burdens (FICA, Federal
Unemployment Insurance), etc. Please let me know there are any plans for moving forward with developing one. Thank You.
Chris J.
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
Change Order Protocol - Toronto
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
Goals
• The goal is to provide a standardized and
fair process for the costing and pricing of
change orders
• The document will be similar to the one by
NECA - Toronto but additional details
about the U.S. requirements of various
contractual documents (such as, AIA,
Consensus, and EJCDC) and various
labor burden costs, will be incorporated
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
Work Plan
• Analyze the NECA - Toronto document and its development challenges and lessons learned
• Analyze change order related requirements in various
contractual documents as well as various labor burden costs • Compile similar initiatives / data published by other major
subcontractor groups and invite them to participate*
* ASA and New Horizons Foundation (SMACNA) are considering collaboration
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
January 14, 2013 Matt,
We will participate and believe that deliverable would be benefit if broadened to include
mechanical and HVAC, especially if the objective is to establish an industry standard/protocol. We have a significant number of companies that are active in both areas.
Dennis
Dennis Bradshaw, Executive Director New Horizons Foundation
Sheet Metal and Air Conditioning Contractors’ National Association
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
Work Plan
• Analyze the NECA - Toronto document and its development challenges and lessons learned
• Analyze change order related requirements in various
contractual documents as well as various labor burden costs • Compile similar initiatives / data published by other major
subcontractor groups and invite them to participate*
* ASA and New Horizons Foundation (SMACNA) are considering collaboration
• Survey NECA members to compile various consequential costs and a process to quantify their impact
• Develop and finalize the change order protocol with the help of Industry Task Force
• Develop a MEI seminar presentation package**
** MEI has already stated interest in a seminar package based on this project
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
PROS and CONS
PROS
• A standard document compiled by an independent entity such as MSU, with participation from more than one
subcontractors group, will provide uniformity and credibility • Will give industry members a stronger basis to state their
case
• Will help to bring the impact of consequential costs to the forefront
• Can benefit from the work already done by NECA-Toronto
CONS
• Difficulty in bringing and finding common ground among various subcontractors groups
• Time and efforts needed for disseminating and gaining acceptance of the document
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
Output and Dissemination
• The outcome of this project will be:
o a protocol document o a Seminar Package
• The output will also be shared with various
industry groups affiliated with GC’s/CM’s, owners
and major subcontractors
• Presentations will be made at various industry
meetings and articles will be published in industry
magazines
• In addition, we will work with MEI’s and NECA’s
PR staff to publicize the protocol and the
seminars
M. Syal _2013
Prof. Matt Syal, Construction Management, MSU
THANK YOU.
Prof. Matt Syal
Michigan State University
[email protected]
www.msu.edu/~syalm
M. Syal _2013
M. Syal _2010
Comments at NECA Convention Seminar
Recommendations/comments on how to improve seminar: - Open-Ended Response
• Bring in other trades..
• More time for this subject matter.
• The mentioned paperwork to review the subject matter was not available for the class. • Too short time frame for information
• Excellent!
• Too short would like the seminar to be longer. • More time to present.
• Handouts should be available during presentations.
• This is not an area that could or should be standardized. Education of contractors on cost
behavior is the best outcome from this course/project but the presenters should steer away from trying to standardize the process.
• Very important topic -> very popular seminar->bigger room please. • Little dry mono tone
M. Syal _2010
Classification of Costs
20
Direct Costs Overhead Costs Labor Home office overhead
Material costs Off-site supervision
Site supervision Change order preparation, negotiation and associated travel
Handling, carrying and shipping costs
Restocking and/or cancellation costs Time delays
Performance and payment bond premiums Guaranty and warranty durations Temporary protection
Additional performance and payment bond premiums
Temporary heat, light and power Property taxes, business licenses, auto insurance
Safety equipment staging, scaffolding and lights
Items directly related to the changes Dues and subscriptions All applicable taxes Postage and courier
(non-job related) Material escalation
Labor escalation Advertising and telephone Clean-up and disposal Legal and accounting fees Estimating/Engineering Sales and marketing
As-built drawing and schedules President's salary and benefits CPM revisions and updating Sales force salaries and benefits Cost analysis Support Staff salaries and benefits Purchasing and Expediting Dispatcher's salary and benefits Timekeepers Support staff salaries and benefits Mobilize and demobilize Purchasing salaries and benefits
(estimating only) Contract Administration
Audit cost contingency Estimators salaries and benefits (except for change orders) Travel, room and board expenses
Permits and licenses fees
Small tools
Equipment and tool rental Job-related insurance, warranty and interest Job site office and storage rental Job site equipment, furniture and supplies Salaries and benefits for job site management and clerical staff