Project Activities and Tasks

Project Activities and Tasks

Module 4

Module Objectives

Module Objectives

After completing the Project Activities and Task Section, i i ill b bl

participants will be able to:

y learn the difference between an activity and a task. y define Work Breakdown Structure (WBS).

y describe the difference between summary and detailed

(c)2010 Competitive Advantage

activities.

y describe the different formatting approaches for a WBS.

5-2

(2)

Activities versus Tasks

Activities versus Tasks

An activity is generally a higher level of work or an element of the project. In some organizations, the term “activity” is used to describe a particular function such as design activity, purchasing activity, etc. If this is true of your organization, it may be more appropriate and less confusing to use the term “tasks”.

Tasks and subtasks describe what needs to be accomplished in the project. This is the actual work to be done by the

(c)2010 Competitive Advantage

people supporting the project. Time, cost, and resources can be assigned at the task level.

5-3A

3

Tasks (or Activities)

Tasks (or Activities)

y

Represent action or work and should begin

with a VERB

with a VERB

y

Assign resources - accountability and

responsibility

y

Determine duration and work

y

Identify cost

y

Identify cost

y

Track progress

(3)

Formatting Information

Formatting Information

After the Statement of Work has been completed, the next step is to identify all the elements (activities), tasks, and subtasks associated with the project.

The initial identification of tasks is a draft of what the project team thinks needs to be accomplished. When more structure is added to the Project Plan, the team may identify additional tasks, change tasks, or delete

(c)2010 Competitive Advantage

tasks altogether.

5-4A

5

Work Breakdown Structure

Work Breakdown Structure

(WBS)

(WBS)

Graphically depicts the elements and tasks to be l d i hi j h d i d j completed within a project to meet the desired project goals and objectives.

The Work Breakdown Structure (WBS):

y shows the different levels of a project.

(c)2010 Competitive Advantage

y does not take into consideration order of tasks or time. y can be presented in several different formats.

5-4B

(4)

(WBS)

(WBS)

Phase Element Segment Deliverable

Level I Level II T k Project (c)2010 Competitive Advantage Level III Tasks Subtasks Subtasks 5-5 7

Work Breakdown Structure

Work Breakdown Structure

Approaches

Approaches

y Top Down Approach

y Bottom Up Approach y Outlining Format

(5)

Top Down Format

Top Down Format

In the top down format, it is assumed that the project team knows the major elements. The team identifies the tasks and knows the major elements. The team identifies the tasks and subtasks associated with each element. For example, building a garage would include:

Build a  Garage

Administration Preliminary Cement Garage Electricity ManagementProject 

9 (c)2010 Competitive Advantage

Bottom Up Format

Bottom Up Format

The bottom up format is useful when the project team is able to determine the tasks and subtasks that need to be completed. Once this step is completed, then several common elements can be defined and the tasks grouped by elements.

10 (c)2010 Competitive Advantage

(6)

Build a  Garage

Administration Preliminary Cement Garage Electricity ManagementProject  ♦ Get permit ♦ Develop

layout ♦ Prepare & level  area ♦ Route electrical ♦ Install the switches ♦ Track costs ♦ Obtain signed contract ♦ Develop blueprint of garage ♦ Dig footings for the garage ♦ Rough in the walls ♦ Get inspection (electrical) ♦ Monitor hours worked ♦ Contact material suppliers

♦ Post permit ♦ Lay forms in ground ♦ Complete with texture sheathing ♦ Install the electricity & outlets ♦ Prepare weekly cash flow report ♦ Develop quote and estimate ♦ Get inspection (cement) ♦ Hang the garage door ♦ Connect electricity to the door ♦ Prepare schedule tracking report

♦ Contact ♦ Pour the ♦ Hang the ♦ Prepare

♦ Contact inspector ♦ Pour the cement ♦ Hang the 36” door ♦ Prepare resource tracking report ♦ Set trusses ♦ Get final inspection ♦ Sheath the roof & shingle ♦ Prepare invoice ♦ Get inspection ♦ Paint the garage 11 (c)2010 Competitive Advantage

Outline Format

Outline Format

This format is most common in many project

management software packages. This method is

often used in management consulting and

engineering projects. The number scheme is

usually determined by your organization.

I. Project Title

A. Element I

A 1

Complete task 1

A.1

Complete task 1

A.2

Complete task 2

(7)

Graphic

Graphic -- WBS

WBS -- Levels

Levels

WBS

Level 1

Chunk of

Work Deliverable Phase Element

Level 2 SUMMARY ACTIVITIES Level 3 Detailed Activities 13 (c)2010 Competitive Advantage

Outlining Format

Outlining Format -- Example

Example

ID Task Name

1 1 Preliminary

2 1.1 Develop Layout

3 1.2 Develop Blueprint of Garage

3 e e op uep o Ga age

4 1.3 Post the Permit

5 2 Administration

6 2.1 Develop Quote and Estimate

7 2.2 Get Permit

8 2.3 Obtain Signed Contract

9 2.4 Contact Material Supplier

10 2.5 Contact Inspector

11 3 Cement

12 3.1 Prepare & Level Area

13 3.2 Dig Footings for Garage

14 3.3 Lay Forms in Ground3 3 ay o s G ou d

15 3.4 Get Inspection (Cement)

16 3.5 Pour the Cement

17 4 Garage

18 4.1 Route Electrical Conduit

19 4.2 Rough in Walls

20 4.3 Complete with Texture Sheathing

21 4.4 Set Trusses

22 4.5 Sheath Roof & Shingle

14 (c)2010 Competitive Advantage

(8)

Sample WBS in MS Project

Sample WBS in MS Project

(c)2010 Competitive Advantage 15

Project Exercise: Work

Project Exercise: Work

Breakdown Structure

Breakdown Structure

Instructions:

y brainstorm a list of tasks and subtasks

y although your projects may be very detailed, do not go

below Level III; develop at a macro level

y use the Top Down or Bottom Up Approach to develop

your WBS

y use the next page to develop your draft

t f fi l WBS t fli h t

y transfer your final WBS to flipchart paper

(9)

Project Exercise: WBS Form

Project Exercise: WBS Form

(c)2010 Competitive Advantage

5-13

17

Module

Module Review

Review

This section covered the following topics:

y activities

y tasks and subtasks y elements

y Work Breakdown Structure (WBS) y Top Down WBS y Bottom Up WBS (c)2010 Competitive Advantage y Outline WBS 5-14 18

References

Related documents

C: Control; S: Silymarin; D: Diabetic; FBS: Fasting blood sugar; ALT: Alanine transaminase; AST: Aspartate transaminase; ALP: Alkaline phosphatase; HOMA-IR: Insulin resistance index;

Este livro contém três partes. As duas primeiras, a história da srta. Keller e trechos de suas cartas, formam um relato tão completo de sua vida quanto posso oferecê-lo. Keller não

This study investigates the impact of international outsourcing to low– and high income countries on total factor productivity growth based on manufacturing industry data for

Every building shall be maintained free of rodents, vermin and insects at all times and methods used for exterminating rodents, vermin or insects shall conform

In the case of the Inbound Travel Plan if you are 60 years of age of over at the time the Certificate of Insurance is to be issued, cover under Section 1 Medical Expenses, Section

The ABET criteria define the necessary elements of the curriculum: ‘The curriculum must require students to apply principles of engineering, basic science, and

Financial Management Workshops led by the BSU Platform on Human Health (BSUHH) were held during January - March 2012 for all four African partner universities targeted at