Method Statement for
PLATE BEARING TESTS
Chulalongkorn University
Saraburi Campus
Contractor: EMC Public company limited
NOVEMBER 2009
BY
Infratech ASTM CO., LTD.
TABLE OF CONTENTS
Chapter Title
Page
Table of Contents... 1
List of Appendix...Error! Bookmark not defined.
List of Figures...Error! Bookmark not defined.
1.0 PROJECT
INFORMATION ... 3
2.0
PLATE LOAD TEST INFORMATIN ... 3
3.0
TEST APPARATUS ... 3
4.0
TEST PROCEDURE ... 3
5.0
RESULTS
OF
TEST ... 4
Appendix
Infratech ASTM CO., LTD.
List of Appendix
Appendix A Data Recording Form
Appendix B Sample of Graph of Load-Time-Settlement
Appendix C Sample of Test Data
Appendix D Calibration of Hydraulic Jack
Infratech ASTM CO., LTD.
1.0 PROJECT
INFORMATION
x
Project Name :
Chulalongkorn University Saraburi Campus
x
Contractor :
EMC Public Company Limited
x
Location : Saraburi,Thailand
2.0
PLATE LOAD TEST INFORMATION
x
Number of Tests : 11
x
Plate Size :
Dia . 12”x 25 mm
x
Design Load : 20 Tons/sq.m.
x
Proposed Test :
50 Tons/sq.m. (2.5 * design load)
x
Testing Standard :
AASHO T235-74 (1986) / ASTM D1195
3.0 TESTING
APPARATUS
The test apparatus consists of the following:
1. A 10-ton hydraulic jack was used as loading device.
2. A dia.12”x 25 mm thick steel plate was used to distribute the load from the jack to the plate
and to the ground.
3. Three dial gauges with accuracy of 0.01 mm were used to measure the deflections during
loading and unloading.
4 .Back hoe axial was used as reaction load during loading
.
4.0 TEST
PROCEDURE
The test ground was loaded as per AASHO T 235-74 (1986) as per the loading and unloading
steps. These steps were for all the tests conducted.
Loading: 0- 25% - 50% - 75% - 100% - 125% - 150% - 175% - 200% - 225% - 250% of the
design load.
Unloading: 150% - 100% - 50% and 0% of the design load
Infratech ASTM CO., LTD.
Each loading and unloading stage was maintained for 15 minutes with readings made at 1, 2, 4,
8 and 15 minutes after the application or removal of load. During the test, records including plots of load
vs. time and load vs. settlement were maintained progressively.
5.0 RESULTS OF TEST
Results of test will be presented in graph form show relationship among load-time-settlement
and prediction of subgrade modulus.
Appendix-A
Data recording form
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……….... Area : ……… Pit 1
Certification No. :
Date : …
26/10/2010Soil Description
: Silty SandPlate Size
: Dia.12" x 25 mm.Area / Line No.
: ……….Def. Rate (mm/min) 10.30
Result :
Accepted
Rejected
Re-CompactTest by :
Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
COMPANY SIGNATURE NAME DATE
(ITP-C-116/LRS) Rev.0 E:\05-PlateBearing-EMC\[PlateLoadTestEMC.xls]Basic Info
14 1.09 15.0 14 0.73 10.0 13 0.73 10.0 12 0.73 10.0 10 0.73 10.0 13 0.36 5.0 12 0.36 5.0 10 0.36 5.0 8 0.36 5.0 0 (bars) 31 (bars) 50.00 50.00 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 10.0 10.0 15.0 10.0 10.0 10.0 10.0 0.36 0.00 0.0 5.0 5.0 0.36 0.36 5.0 5.0 5.0 5.0 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 0.73 0.73 0.73 0.73 0.73 0.73 0.36 0.36 0.36 2 1 2 4 8 14 15 4 8 15 15 0 1 10 13 12 0 0 1 2 4 0 DATE TIME (tons) TIME 26-Oct-10 REMARKS 51 (bars) ELAPSED
ASTM Testing Co.,ltd. Kenber
72 (bars)
Rangsan Gamsantia Poosit S.
SUBMITTED BY RECEIVED BY
t/m^2 G1 G2 G3 (mm)
LOAD APPLIED Avg. Set.
50.00 50.00 Owner : CU Main Conractor:EMC Contractor :
Footing
Appendix-A
Data recording form
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……….... Area : ……… Pit 1
Certification No. :
Date : …
26/10/2010Soil Description
: Silty SandPlate Size
: Dia.12" x 25 mm.Area / Line No.
: ……….Def. Rate (mm/min) 10.30
Result :
Accepted
Rejected
Re-CompactTest by :
Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
COMPANY SIGNATURE NAME DATE
(ITP-C-116/LRS) Rev.0 E:\05-PlateBearing-EMC\[PlateLoadTestEMC.xls]Basic Info
14 1.09 15.0 14 0.73 10.0 13 0.73 10.0 12 0.73 10.0 10 0.73 10.0 13 0.36 5.0 12 0.36 5.0 10 0.36 5.0 8 0.36 5.0 0 (bars) 31 (bars) 50.00 50.00 15.0 15.0 15.0 15.0 15.0 15.0 15.0 15.0 10.0 10.0 15.0 10.0 10.0 10.0 10.0 0.36 0.00 0.0 5.0 5.0 0.36 0.36 5.0 5.0 5.0 5.0 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 0.73 0.73 0.73 0.73 0.73 0.73 0.36 0.36 0.36 2 1 2 4 8 14 15 4 8 15 15 0 1 10 13 12 0 0 1 2 4 0 DATE TIME (tons) TIME 26-Oct-10 REMARKS 51 (bars) ELAPSED
ASTM Testing Co.,ltd. Kenber
72 (bars)
Rangsan Gamsantia Poosit S.
SUBMITTED BY RECEIVED BY
t/m^2 G1 G2 G3 (mm)
LOAD APPLIED Avg. Set.
50.00 50.00 Owner : CU Main Conractor:EMC Contractor :
Footing
Appendix-B
Sample of Graph for
Load-Time-Settlement
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……. Area : ………
Certification No. :
Date : ………..……
Soil Description
: Silty ClayPlate Size
: Dia. 304 mm. x 25 mm.Area / Line No.
: ………..k = Subgrade modulus( t/sq.m./mm.) =9.3
E = Soil Modulus(Mpa.) = k x Dx(1-u^2)/100 = 0.91xKx450/100 ,in which u = Poison ratio,D=Plate Diameter
(Ref. Foundation analysis and design By Joseph E. Bowles 4th Edition page407 Eq.9.6a)
For Silt,Sand&Dry clay, E = 26 MPA
For wet clay, E = 22
MPAResult :
Accepted
Rejected
Re-Compact
Test by :
Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
COMPANY SIGNATURE NAME DATE
(ITP-C-116/LRS) Rev.0 E:\99-07-PlateBearingTest\[PlateBearingTestReport.xls]Report (1)
SUBMITTED BY RECEIVED BY
Infratech ASTM Co.,ltd.
Rangsan Gamsantia
Owner : CU
Main Contractor: EMC Contractor :
LOAD-SETTLEMENT CURVE
-7.0 -6.0 -5.0 -4.0 -3.0 -2.0 -1.0 0.0 0 10 20PRESSURE, (t/m30 40 50 60 2 ) SETTLEMENT, (mm) Actual loading Unloading Linear loadingTIME - LOAD CURVE
0 10 20 30 40 50 60 0.0 1.0 2.0 3.0 4.0 TIME, (hrs) PRESSURE, (t/m 2 )
TIME-SETTLEMENT CURVE
-7.0 -6.0 -5.0 -4.0 -3.0 -2.0 -1.0 0.0 0.0 1.0 2.0 3.0 4.0 TIME, (hrs) SETTLEMENT, (mm)Footing
P234 1 Line No. 4/J-K
Appendix-C
Sample of Test Data
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……….... Area : ………
Certification No. :
Date : …
26/10/2010Soil Description
:Plate Size
: Dia. 304 mm. x 25 mm.Area / Line No.
: P 234 1 [Line 4/J-K]Def. Rate (mm/min) 15:05 15:05 15:06 15:07 15:09 15:13 15:20 15:20 15:21 15:22 15:24 15:28 15:35 15:35 15:36 15:37 15:39 15:43 15:50 15:50 15:51 15:52 15:54 15:58 16:05 16:05 16:06 16:07 16:09 16:13 16:20
Result :
Accepted
Rejected
Re-CompactTest by :
Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
COMPANY SIGNATURE NAME DATE
(ITP-C-116/LRS) Rev.0 E:\99-07-PlateBearingTest\[PlateBearingTestReport.xls]Report (1)
15 1.46 20.0 43.72 2.89 40.48 42.11 2.90 43.74 2.86 8 1.46 20.0 40.49 42.12 1.46 20.0 40.52 42.15 2 1.46 20.0 40.61 42.21 43.77 2.80 20.0 40.63 42.22 43.78 0 1.46 20.0 40.73 42.30 43.82 2.72 92 (bar) 44.02 2.39 15.0 15 1.09 15.0 44.02 2.39 8 1.09 15.0 41.23 42.58 15.0 1.09 15.0 41.33 41.27 1.09 43.04 41.71 41.80 42.65 42.63 42.58 42.60 42.58 45.00 42.82 5.0 42.81 0.0 5.0 5.0 43.53 43.52 42.80 43.53 42.82 42.80 45.00 43.52 43.52 43.52 43.13 43.07 43.05 43.04 Rangsan Gamsantia SUBMITTED BY RECEIVED BY
Infratech ASTM Co.,ltd.
113 (bar) 41.76 41.75 41.73 41.72 72 (bar) G3 (mm) G2
LOAD APPLIED Avg. Set.
(t/m^2) G1 2 4 1 Jack Pressure 51 (bar) 26-Oct-10 0 1 DATE TIME (tons) TIME ELAPSED 0.00 0.36 0 1.82 1.09 1.09 1 1.46 4 15 15 0 1 1 2 4 8 15 0 2 4 0 2 4 8 1.82 1.82 1.82 10.0 10.0 1.82 1.82 0.73 15.0 0.73 0.73 0.73 0.36 0.36 0.73 0.36 0.36 0.73 5.0 5.0 25.0 10.0 10.0 10.0 10.0 25.0 25.0 25.0 25.0 25.0 39.90 39.88 41.23 42.80 42.06 41.99 41.87 41.86 42.10 43.11 39.87 41.86 39.97 39.93 41.30 41.24 39.91 43.44 45.00 44.64 44.63 44.63 44.64 44.63 44.04 44.34 43.43 44.34 44.35 43.49 44.07 44.06 43.46 43.46 43.47 3.28 2.36 44.02 2.39 43.71 44.04 44.39 44.36 1.34 1.35 1.35 1.34 3.29 1.81 1.86 1.91 1.92 2.79 1.35 3.25 0 (bar) 31 (bar) 0.00 44.63 1.35 3.30 3.32 3.33 1.91 2.32 2.34 8 0.36 5.0 1.92 Owner : CU
Main Contractor: EMC Contractor :
Footing
Footing
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……….... Area : ………
Certification No. :
Date : …
26/10/2010Soil Description
:Plate Size
: Dia. 304 mm. x 25 mm.Area / Line No.
: P 234 1 [Line 4/J-K]Def. Rate (mm/min) 16:20 16:21 16:22 16:24 16:28 16:35 16:35 16:36 16:37 16:39 16:43 16:50 16:50 16:51 16:52 16:54 16:58 17:05 17:05 17:06 17:07 17:09 17:13 17:20 17:20 17:21 17:22 17:24 17:28 17:35
Result :
Accepted
Rejected
Re-CompactTest by :
Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
COMPANY SIGNATURE NAME DATE
(ITP-C-116/LRS) Rev.0 E:\99-07-PlateBearingTest\[PlateBearingTestReport.xls]Report (1)
3.28 45.0 37.17 39.69 41.41 5.58 37.14 39.64 41.37 5.62 8 3.28 45.0 37.23 39.76 41.50 5.50 4 3.28 45.0 3.28 45.0 37.32 39.85 41.59 5.41 37.40 39.92 41.65 5.34 1 3.28 45.0 40.04 41.75 5.22 195 (bar) 2.92 40.0 3.28 45.0 5.06 15 2.92 40.0 5.09 40.25 37.70 40.14 41.88 37.73 40.18 41.92 2 2.92 40.0 8 40.31 1 2.92 40.0 4 2.92 40.0 5.77 4.79 175 (bar) 4.90 216 (bar) 4.85 4.97 6.17 40.79 40.91 5.90 5.97 42.12 40.41 42.18 37.96 40.36 2.92 40.0 38.48 38.44 2.55 35.0 2.55 2.55 2.55 Avg. Set. 6.06 42.95 3.95 3.75 133 (bar) 4.61 8 2.19 30.0 42.44 42.71 42.56 42.53 2.19 3.98 4.40 40.73 42.39 42.35 41.21 41.08 41.00 42.08 42.01 39.04 43.12 43.06 43.00 43.18 39.07 36.59 38.26 36.97 36.85 36.78 38.03 37.83 37.90 37.55 38.70 36.54 35.0 35.0 35.0 38.35 38.30 50.0 36.71 50.0 50.0 50.0 50.0 2.19 2.55 2.55 30.0 30.0 2.19 2.19 30.0 2.19 30.0 35.0 35.0 30.0 3.65 3.65 3.65 3.65 3.65 3.65 50.0 15 15 0 1 4 8 0 0 2 15 0 2 1 2 4 8 15 2 4 0 DATE TIME (tons) TIME LOAD APPLIED (t/m^2) 1 Jack Pressure 154 (bar) ELAPSED 41.32 G3 (mm) G2
Infratech ASTM Co.,ltd.
6.23 41.19 Rangsan Gamsantia SUBMITTED BY RECEIVED BY 40.91 40.75 4.43 4.52 4.57 41.40 41.14 4.23 3.83 3.89 3.67 42.92 41.11 39.30 G1 39.30 39.21 39.14 39.40 41.25 39.04 39.21 39.10 40.73 40.64 40.60 40.57 39.50 39.38 Owner : CU
Main Contractor: EMC Contractor :
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……….... Area : ………
Certification No. :
Date : …
26/10/2010Soil Description
:Plate Size
: Dia. 304 mm. x 25 mm.Area / Line No.
: P 234 1 [Line 4/J-K]Def. Rate (mm/min) 17:35 17:36 17:37 17:39 17:43 17:50 17:50 17:51 17:52 17:54 17:58 18:05 18:05 18:06 18:07 18:09 18:13 18:20 18:20 18:21 18:22 18:24 18:28 18:35 18:35 18:36 18:37 18:39 18:43 18:50
Result :
Accepted
Rejected
Re-CompactTest by :
Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
COMPANY SIGNATURE NAME DATE
(ITP-C-116/LRS) Rev.0 E:\99-07-PlateBearingTest\[PlateBearingTestReport.xls]Report (1) 39.76 39.56 39.60 39.62 39.66 39.71 39.03 39.03 39.03 39.03 39.04 G1 36.54 36.54 36.54 36.54 39.04 39.04 G3 (mm) 0 (bar) G2 39.04 39.04
Infratech ASTM Co.,ltd. Rangsan Gamsantia SUBMITTED BY RECEIVED BY 5.50 Jack Pressure 151 (bar) ELAPSED 39.04 DATE TIME (tons) TIME LOAD APPLIED (t/m^2) 1 2 4 0 4 8 15 15 0 1 2 4 0.00 0 1 2 4 8 15 1.46 1.46 1.46 15 0 1 2 4 8 2.19 1.46 1.46 30.0 0.0 40.0 40.0 30.0 20.0 20.0 20.0 20.0 10.0 2.92 2.92 30.0 30.0 30.0 30.0 2.19 2.19 0.00 0.00 2.19 2.19 2.19 0.00 0.00 0.73 0.00 2.92 40.0 40.0 2.92 2.92 40.0 0.0 0.0 0.0 0.0 0.0 36.90 36.85 36.87 36.54 36.80 36.81 36.54 36.54 36.54 36.54 36.83 36.54 36.54 36.54 36.54 39.03 39.03 5.66 40.73 40.74 36.54 36.54 39.03 40.71 36.54 39.04 40.72 40.72 40.72 40.72 6.24 6.24 6.24 41.83 40.71 40.71 41.55 41.60 40.73 6.23 6.23 6.23 6.23 197 (bar) 8 2.92 40.0 5.60 6.23 40.71 40.71 40.71 5.64 41.64 41.70 6.24 39.04 6.23 40.72 Avg. Set. 6.24 40.71 6.24 6.23 5.55 6.23 6.18 41.76 6.24 5.70 6.23 104 (bar) 6.23 6.23 20.0 36.54 39.04 40.73 40.73 39.04 40.73 1.46 20.0 36.54 39.04 0 0.73 10.0 36.56 39.08 40.80 6.19 58 (bar) 1 0.73 10.0 36.56 39.08 40.80 6.19 2 0.73 10.0 36.56 39.08 39.09 40.81 36.56 39.09 40.80 6.19 36.56 6.18 8 0.73 10.0 40.81 6.18 15 0.73 10.0 36.56 39.09 40.81 Owner : CU
Main Contractor: EMC Contractor :
Appendix-D
Jack Calibration
Project :
Chulalongkorn Saraburi Campus
Contractor EMC PCL Plate Size 0.3048 m.(Dia.) Plate area 0.0730 Sq.m.
Jack Reading and Plate load Table
PLATE Jack Load Jack Pressure Applied Load (Y) Calculate(X) (tons/sq.m.) (kg) bar 0 0 0 LOADING 5 365 31 Y = AX+B X=(Y-B)/A 10 730 51 A= 17.7758 15 1094 72 20 1459 92 UNLODING 25 1824 113 A= 15.6833 30 2189 133 B= -176.3889 35 2554 154 40 2919 175 45 3283 195 50 3648 216 40 2919 197 30 2189 151 20 1459 104 10 730 58 0 0 0