• No results found

Project Management Plan for

N/A
N/A
Protected

Academic year: 2021

Share "Project Management Plan for"

Copied!
16
0
0

Loading.... (view fulltext now)

Full text

(1)

[Project Name] 

[Project ID] 

                 

Prepared by:   Date:  

  [Name], Project Manager 

   

Approved by:   Date:  

  [Name], Project Sponsor 

   

Approved by:   Date:  

  [Name], Executive Manager 

   

(2)

Table of Contents

Project Summary ... 4 

1  Scope Management ... 5 

1.1  Scope Statement ... 5 

1.2  Work Breakdown Structure (WBS) ... 5 

1.3  Manage Requirements ... 6 

1.4  Manage Change ... 6 

2  Schedule Management ... 7 

2.1  Develop Schedule ... 7 

2.2  Control Schedule ... 7 

3  Cost Management ... 7 

3.1  Estimate Costs ... 7 

3.2  Determine or Refine Budget Baseline ... 8 

3.3  Control Costs ... 9 

4  Quality Management ... 9 

4.1  Plan Quality ... 9 

4.2  Assure Quality ... 9 

4.3  Control Quality ... 10 

4.4  Improve Processes ... 11 

4.5  Lessons learned ... 11 

5  Human Resources ... 11 

5.1  Roles and Responsibilities ... 11 

5.2  Manage Staffing ... 12 

6  Communications Management ... 12 

6.1  Report Progress ... 12 

6.2  Define Communications ... 12 

6.3  Manage Stakeholder Expectations ... 13 

7  Risk Management ... 13 

7.1  Identify, Analyze, and Plan for Risks ... 13 

7.2  Monitor and Control Risks ... 14 

8  Procurement Management ... 14 

(3)

8.2  Conduct and Administer Procurements... 14 

8.3  Close Contracts ... 14 

9  Transition to Operations ... 15 

9.1  Manage Project Records ... 15 

9.2  Develop Post‐Project Agreements ... 15 

9.3  Measure Post‐Project Benefits ... 15 

9.4  Asset Commissioning and Decommissioning ... 15   

 

(4)

PROJECT MANAGEMENT PLAN

The Project Management Plan defines how the project is executed, monitored and controlled, and  closed, and sets the project baselines from the planning process. The plan’s content will vary depending  on the type of project and the complexity of the project.  

This plan is developed during project planning and approved prior to project execution. The project  manager will update the plan as needed and track these changes.  

[Project Manager Instructions: Keep the text at the beginning of each section for the sponsors and  stakeholders. Next, describe the process you will use to reach these objectives. Then, give any specific  information that relates to your project for each section. 

Comments contained in brackets, [], are guidance that must be reviewed and customized for the given  project. Delete the highlights after section completion.  

To update the Table of Contents (TOC), right click on the TOC, click the Update Table tab that appears,  choose Update entire table, and then click OK.] 

Project Summary

[Provide a high‐level narrative summary of the project. Note that many of the details will be described  under Scope Management.] 

   

(5)

1 Scope Management

This section describes how the project scope will be defined, documented, verified, managed, and  controlled by the project management team. Managing the project scope is primarily concerned with  defining and controlling what is and is not included in the project.  

1.1 Scope Statement

The project scope statement describes the project’s deliverables and the work required to create those  deliverables. It provides a common understanding of the scope among stakeholders.  

Product scope description. Characteristics of the product, service, or result described in the project  charter and requirements documentation. 

[Description here.] 

Product acceptance criteria. Process and criteria for accepting completed products, services, or results. 

[Description here.] 

Project deliverables. Outputs of the project and associated documentation.  

[Description here.] 

Project exclusions. Items that are out of the scope for the project.  

[Description here.] 

Project constraint. Factors that limit options and that may affect the performance of the project.  

[Examples of constraints are a predefined budget; dates or milestones issued by the customer or  organization; endangered species; contractual obligations.]   

Project assumptions. Factors that are considered certain and that may affect the performance of the  project if they prove to be false.  

[Description here.] 

1.2 Work Breakdown Structure (WBS)

The WBS organizes and defines the total scope of the project and is a deliverable‐oriented hierarchy of  the work to accomplish the project objectives. Significant work packages will have a Statement of Work,  which is the contract between the project manager and work package manager or vendor. 

[Example: Following are the work packages and deliverables for the project.] 

Work Package  Deliverable 

Person  Responsible 

Schedule  Milestone 

Work Order  Estimated Cost 

         

(6)

         

         

 

[Example: Work packages and deliverables are documented on the project website (insert hyperlink).] 

1.3 Manage Requirements

This section documents how requirements will be analyzed, documented, and managed throughout the  project.  

Components may include:  

1. How requirements will be planned, tracked and reported 

2. Configuration management activities—how changes to the requirements will be managed  3. Requirements prioritization process 

4. Product metrics 

5. Traceability matrix—to link and track requirements through the project lifecycle   

[Construction example: The architects will develop and maintain building program documents that will  be reviewed and signed by the project sponsor. Etc…] 

[IT example: Requirements for the project are maintained in the requirements document (insert  hyperlink).] 

1.4 Manage Change

Integrated change control includes reviewing all change requests, approving changes, and managing  changes to the deliverables and project documents.  

Project change requests are used to initiate and document changes that affect the project baselines—

scope, schedule, or budget. Changes to the project baselines will follow LCRA policies and guidelines and  must be approved by the project sponsor and PMO manager. 

The project manager will assess the impact of the change and develop recommendations for  implementing the change. Only formally documented, requested, and approved changes will be  implemented.  

[Example: The work package manager has the authority to approve most minor project  revisions. The work package manager is responsible for documenting and communicating the  change to the project manager.] 

Contract change requests are used to make changes to a contract or purchase order with an outside  vendor or provider. These changes must be documented and processed in accordance with LCRA’s  procurement policies.  

(7)

[Example: Field change orders up to $5,000 may be processed by the project manager. All other  changes must be processed through Supply Management.] 

2 Schedule Management

This section establishes criteria and the activities for developing and controlling the project schedule.  

2.1 Develop Schedule

The project manager will maintain the schedule in PMIS. It will include costs, resources, and contingency  requirements according to LCRA project management guidelines. The project schedule baseline will be  set at the end of the planning process and before starting project execution. 

[Use this chart to identify key project‐level milestones. Note that the milestones identified in the Scope  WBS section generally apply more to each work package than to the entire project. For smaller projects,  this information may be redundant with the WBS.] 

[Example: Following are the key schedule milestones for this project.] 

Milestone  Target Date 

Project schedule baseline set  xx/yy/zzzz 

Substantial Completion (In Service)  xx/yy/zzzz 

Formal Acceptance  xx/yy/zzzz 

Project Close  xx/yy/zzzz 

   

 

2.2 Control Schedule

The project manager will update the schedule in PMIS at least monthly. Changes to the project schedule  baseline will follow the change process described in section 1.4.  

[Describe any conditions under which outside vendors would develop and/or update the schedule and  how the schedules will be integrated with the PMIS schedule.] 

3 Cost Management

This section establishes criteria and the activities for estimating, budgeting, and controlling project  costs. Project cost management is primarily concerned with the cost of the resources needed to 

complete project activities. Project cost management should also consider the effect of project decisions  on the cost of using, maintaining, and supporting the product, service, or result of the project.  

3.1 Estimate Costs

Project cost estimates are developed using one of three estimating levels: preliminary, budgetary or  final. Contingency percentage (or amount) is also determined and disclosed. 

(8)

[Example for CIP: This project was recommended to the Board for approval at the budgetary estimating  level during the capital planning process. The contingency percentage disclosed in the capital plan was  10%. At the end of planning, the baseline cost estimate is (will be) at the definitive level of estimating  accuracy, and the contingency percentage is 9%.] 

[Construction Example:] 

Item  Funding 

Source 

Work Order  FYxx  FYxx  Total 

Internal Labor       

Design       

Construction       

Other       

Contingency       

G&A        

TOTAL       

 

[Technology Example:] 

Item  Funding 

Source 

Work Order  FYxx  FYxx  Total 

Internal Labor       

Outside Services       

Hardware        

Software       

Other       

Contingency       

G&A        

TOTAL       

 

[Example: The project budget is documented on the project website (insert hyperlink).] 

[Also describe any ongoing costs or potential O&M cost savings that the project will affect.] 

3.2 Determine or Refine Budget Baseline

The project cost baseline will be set at the end of the planning process and before starting project  execution. Cost performance, including contingency, will be measured against the project baseline.  

[Describe any additional information about the project baseline.] 

(9)

3.3 Control Costs

The project manager will update the cost projections for the project at least monthly. The PMO Manager  and appropriate management will review these projections as part of the overall project portfolio.  

Changes to the project cost baseline will follow the change process described in section 1.4. Changes to  the lifetime budget can only be made in accordance with LCRA financial policies and guidelines. 

[Describe any additional cost control processes that will be used for this project.] 

4 Quality Management

This section describes how the project will implement project quality. Quality is defined as the degree to  which a set of inherent characteristics fulfills requirements.  

The plan should include efforts at the front end of a project to ensure that the earlier decisions, for  example on concepts, designs, and tests, are correct. These efforts should be performed through an  independent peer review and not include individuals that worked on the material being reviewed. The  benefits of this review can include reduction of cost and schedule overruns caused by rework.  

Quality baseline 

4.1 Plan Quality

This section identifies the relevant quality requirements and/or standards for the project and product  and documents how the project will demonstrate compliance.  

[Describe the quality strategy for the project and any quality standards that apply. Consider safety,  environmental, regulatory, and legal requirements, as well as quality implications of LCRA policies. 

Specify whether a quality baseline will be set and how it would be changed.]  

 [Construction example. The project will adhere to International Building Codes and to LCRA and OSHA  safety standards. In addition, the project will use LEED Green Building Guidelines.]  

[Technology example: Project schedule and budget will be measured using standard PMIS reports. The  project will follow ITIL guidelines for software testing.] 

4.2 Assure Quality

This section describes the process of auditing the quality requirements and the results from quality  control measurements to ensure appropriate quality standards and operational definitions are used. All  required project deliverables will be reviewed by the project sponsor and the PMO manager. 

[Describe how quality will be tested and measured against the quality standards, including quality  milestones.]  

 [Technology example: The technical team will use standard PeopleSoft/Maximo practices for design,  development, testing, and deployment. Test environments will reflect the current production 

(10)

environments. The team will develop test plans and logs for unit, system, and integration testing. 

Customer signoff of testing results will ensure that the system meets user requirements.] 

[Construction example: The following metrics will be used on the project:    

 Completion and documentation of all quality review processes 

 Compliance for building systems with all commissioning requirements  

 100% compliance with building code requirements for Certificate of Occupancy 

 100% compliance with accessibility standards.  

 Written acceptance by the project sponsor 

 Completion of all punch list items 

 USGBC LEED Silver Rating (33 points) for sustainable design] 

4.3 Control Quality

This section describes how quality results will be monitored and recorded to assess performance and  recommend necessary changes. 

 

[Technology example: At the end of development, the project team will review the deliverables with a  focus group. Revisions and changes will be made based on this feedback. Other members of the project  team will then develop a test plan that they will utilize to conduct system testing after changes have  been made based on focus group feedback. Sign‐off on the test plan will be the acceptance of what has  been developed and will be the approval for the project team to deploy the system or product.] 

[Construction example: The project manager will use the following checkpoints to monitor project  quality, and will provide detailed feedback to the PMO Manager, project sponsor and project 

stakeholders concerning the audit and review results as defined in the communication plan. The project  manager tracks all non‐compliance issues to closure, including escalation as needed.  

1. Design reviews. Progress design documents to be reviewed by the project team at the following  phases: programming, schematic design 50% & 100%; design development 50%, 75% & 100%; 

and construction document 50% & 100%. 

2. Submittals. Construction materials and shop drawings will be reviewed for compliance and  approved by the general contractor, A/E and Cx Agent.  

3. Mock‐ups. Certain items, such as architectural concrete, will have mock‐ups cast on site. 

Approved mock‐ups will be used as a comparison to actual work.  

4. General inspections. The Construction Coordinator will be dedicated full time on this project for  construction inspection and coordination. The A/E team will make periodic site visits to observe  compliance. 

5. Code compliance. City of Austin will perform plan reviews and required inspections of the  building and utilities prior to issuing a Certificate of Occupancy. A third‐party agency will be  engaged for review of compliance with accessibility standards. 

6. Testing. Testing will be in accordance with the contract documents, including soil density, piers,  concrete, rebar and steel. 

7. Commissioning (cx). A third party authority will be engaged for building commissioning. The  commissioning authority is responsible for cx design reviews, planning, oversight, and 

(11)

8. Final Inspections. Parties included in the key final inspections will include the A/E Team, project  manager, Construction Coordinator, Facilities Manager, GOC Site Manager, Preventative  Maintenance Team, and appropriate project team members. Additional participants may  include the project sponsor and certain user representatives. 

9. One year warranty inspection. This inspection will be scheduled with the Contractor, Architect  and Facilities staff 11 months after substantial completion.] 

4.4 Improve Processes

This section details the steps for analyzing processes to identify activities that enhance their values. 

Areas to consider include process boundaries, process configuration, process metrics, and targets for  improved performance. 

 

[If applicable, describe process improvements planned.] 

4.5 Lessons learned

The learning gained from performing the project should be identified, documented, and reviewed  throughout the project.  

 

[Example: As part of project planning, the project manager will review the lessons learned from similar  past projects. The team will review these lessons to assist with project risk management. At the end of  the project, the project manager will arrange a formal lessons learned session. The results will be  documented using the Lessons Learned function on the project website.] 

5 Human Resources

This section provides guidance on how project human resources should be defined, staffed, managed,  controlled, and eventually released from the project. 

5.1 Roles and Responsibilities

Following are the team members who are assigned responsibilities for project activities. 

 

Role  Name  Major Responsibilities 

Project sponsor    Make decisions on key business issues 

Project manager    Plan, deliver and control project activities 

Project analyst    Assist with reporting, schedule and budget 

Construction coordinator    Coordinate project field activities 

Supply management    RFP process; materials procurement 

Safety     

Environmental     

Real Estate Services     

Legal     

Communication Services     

Information Technology     

Contractor     

 

(12)

5.2 Manage Staffing

This section describes how human resource requirements will be met.  

[Identify staffing elements of your plan: staff acquisition, skills needed, staff training needs, recognition  and rewards, compliance and safety, and staff release at the end of the project.] 

6 Communications Management

This section describes the communications requirements and expectations of the project. These may  include what information is to be communicated, in what format, when, to and from whom, use of  technology, escalation process, and communication constraints.  

The project website [link here] will be used for all documentation per LCRA project management  guidelines. [Describe any processes for tracking tasks, use of group calendars, working with project  documents, etc.] 

6.1 Report Progress

The project manager will report project progress to the project sponsor and stakeholders at least  monthly. The project manager will update project progress in PMIS, which will generate standard  project progress reports by the 15th of each month. The project manager will update spending  projections and status monthly in the portfolio report, which will be reviewed by management.  

6.2 Define Communications

The following matrix describes the communication requirements for this project.  

What (content)  Audience  When/how often  How (medium)  Provider (who)  Project Progress  project team, 

project sponsor,  stakeholders,  management 

monthly by the 5th  working day of the  month 

PMIS project  progress report,  Portfolio report 

project manager   

project analyst  Project Status  project manager  weekly  project status 

meeting 

project team  Project 

Deliverables  Review 

PMO management  end of each  process group 

project review  meeting 

project manager 

Project Risks and  Issues 

project team  as needed  risk register and  issues log 

project manager,  project team  Board and FOG 

reporting 

Board of Directors,  FOG 

Monthly,  Quarterly 

PMIS or Excel  reports 

project manager,  PMO manager  Project Changes  project sponsor 

stakeholders,  management 

as need  Project Change 

Request 

project manager 

Public Input or  Notifications 

Public  as needed  Public meeting  Management 

(13)

may be affected  e‐mail  Services  Training Materials  system operators, 

end‐users 

as needed  updated training  manuals, 

tutorials,  job aids 

project manager,   trainer 

 

6.3 Manage Stakeholder Expectations

This section describes the process of communicating and working with stakeholders to meet their needs  and to address issues as they occur.  

[Use this section to describe decision‐making process, issue management (tracking, resolution, and  escalation of issues), communication constraints, and glossary of common terminology.] 

7 Risk Management

This section defines how risk management will be structured and performed on the project. Risk is an  uncertain event or condition that, if it occurs, has an effect on at least one project objective, including  scope, schedule, cost, and quality.  

The project team will use the risk register on the project website [link here] to store project risks,  including their definition, category, probability of occurrence, and potential impact.  

7.1 Identify, Analyze, and Plan for Risks

Risk identification determines which risks may affect the project and documents their characteristics. 

Risk analysis prioritizes risks for further analysis or action by assessing and combining their probability of  occurrence and impact, and analyzing the effect on project objectives. Risk response planning develops  options and actions to enhance opportunities and to reduce threats to project objectives. 

[Describe how you will identify, analyze, and plan for the risks throughout the project. State how you  will identify risk response (avoid, transfer, mitigate, or accept). Include the organizations tolerance for  risk on this project.]  

[Example: The project manager will work with the project team to identify any possible risks that may  arise, their probability of occurrence, and the potential impact to scope, schedule, budget, or quality.]  

[Describe a few of the key risks on the project. Example: Construction on this project will occur during  working hours; therefore, timely communication will be critical to ensure employees’ safety.] 

Risk  Potential Impact  Risk Trigger  Strategy 

Construction  during work hours 

accident or injury  construction   Notify employees of  construction and safety  practices 

       

(14)

7.2 Monitor and Control Risks

This section describes how risks will be monitored and controlled. This includes tracking identified risks,  monitoring residual risks, identifying new risks, executing risk response plans and evaluating their  effectiveness throughout the project.  

[Example: The project manager will maintain the risk register on the project website. Risks that the team  has identified as high risk [define this] will be monitored weekly by the project manager. All risks will be  reviewed monthly at a project team meeting and with project sponsors. At the end of the project, risks  will be reviewed and entered as lessons learned as appropriate.] 

8 Procurement Management

This section describes how the procurement processes will be managed from developing procurement  documents through contract closure. [Describe how you will engage Supply Management, including  roles and responsibilities on the project.] 

8.1 Plan Procurements

This section documents project purchasing decisions, specifies the approach, and identifies potential  sellers. It identifies the project needs that can best be, or must be, met by outside resources versus  those that can be accomplished by the project team.  

[Describe the approach to procurement on this project: whether you will use outside or internal  resources, and how you will engage Supply Management. Describe how materials will be procured. 

Describe the type(s) of contracts you plan to use. Describe whether you will use existing contracts or go  through an RFP process.] 

[Example: An outside vendor will be used on the project to develop and implement the software  solution. Internal resources will test the software and migrate it through the various environments.] 

8.2 Conduct and Administer Procurements

Conducting procurement includes obtaining seller responses, selecting a seller, and awarding a contract. 

Administering procurements includes managing procurement relationships, monitoring contract  performance, and making changes and corrections as needed. [Describe how you will conduct and  administer procurements, including project manager and Supply Management roles and 

responsibilities.] 

8.3 Close Contracts

Closing contracts involves verification that all work was completed and that the deliverables were  acceptable. [Describe how you will verify completion of work and deliverables. Describe whether/how  you will close the contract or statement of work. Describe how vendor performance will be 

documented.] 

(15)

9 Transition to Operations

This section describes how the assets being developed by the project will be turned over to operations  staff. 

9.1 Manage Project Records

This section defines how project files will be organized and maintained.  

[Describe the process for managing project documents and disposing of them at project close.]  

[Example: The project manager will file all project‐related documentation on the project website. At  project close, the project manager will follow LCRA records management guidelines to identify 

documents as permanent retention (stored in EDMS), project documentation (on project website for 12  years), or purpose served (delete).]  

9.2 Develop Post‐Project Agreements

This section describes any agreements that must be put in place prior to system operation.  

[Describe any service level agreements with vendors or staff that need to be developed and by whom. 

Describe how you will document operating procedures and train support staff in the new procedures. 

Document capacity planning assumptions or describe how future capacity requirements will be  assessed.] 

9.3 Measure Post‐Project Benefits

This section describes how the expected benefits from the project will be measured once the project is  complete. 

[Determine how the expected benefits from the project will be measured and who will track the  realization of the cost‐benefit analysis. Only include items here if they can be measured.] 

[Example: The site manager will verify the benefits defined in the business case and provide a report  annually to management.] 

 

Expected benefit  How measured  Expected savings  Responsibility  Reduce electricity usage by $$  Review electric bill  $500/year  operations 

supervisor 

Reduce number of outages by x%  Outage statistics    operations 

supervisor 

9.4 Asset Commissioning and Decommissioning

This section defines how assets created by the project will be put into service and into the financial  system, and how assets removed by the project will be removed from service and from the financial  system.  

[Describe the process for putting the asset in service and deadlines for unitization. If assets are being  removed from service, describe how they will be disposed of and removed from the financial system.] 

(16)

[Construction example: Staff will move into the building once the Certificate of Occupancy has been  approved. Commissioning of the building will occur prior to the COA; however, some punch‐list items  may be completed up to 90 days after building occupancy. The project analyst will complete the 

preliminary unitization within 90 days of building occupancy, and will finalize the asset unitization within  one year.  

Prior to building construction, a storage building on the site will be demolished. Asbestos will be  removed, Habitat for Humanity will salvage fixtures, and the contractor will demolish and remove the  remaining materials and restore the site to grade. The project analyst will contact Asset Management  that the storage building is no longer in service.] 

[Technology example: The technical team will deploy the system using the standard PeopleSoft/Maximo  practices once the customer has signed off on the test results. The project analyst will complete the  unitization within 90 days of system deployment. Four servers being replaced by this project will be  repurposed for use on the xyz system.] 

References

Related documents

Given both the absence of research in existing professional counseling literature specific to the use of ASAM dimension assessment as an effective outcome evaluation with

The central contribution of this work is an adaptive foraging method in which the swarm makes colony-level decisions based on distributed informa- tion, choosing the algorithm

The present paper shows that classical methods of Multi Criteria Decision Making analysis can be used, at the end of a divergent Problem Solving process, to asses several

Public Service Board (the Board) order that created Efficiency Vermont made clear that, although Efficiency Vermont would be responsible for statewide efficiency programs,

By extending the concepts established in a number of studies (e.g. [8,31,33,57] ), we show the system boundaries and spatial impacts of fi ve di ff erent types of footprints;

That paper shows that by measuring shocks to this technology as the sole source of permanent shocks to the relative price of investment goods, investment- specific technology

If it had been passed into law at the same time as being the subject of a national action plan for awareness raising and implementation, the NPD would likely have secured

This worsening financial situation in the period 2007 – 2010 led to more demanding requirements from investors to improve operational cash-oriented performance (measured