Chapter 8

Activity-Based Costing: A Tool to Aid Decision-Making

True/False 1. T Easy When combining activities in an activity­based costing system,  activities should be grouped together at the same level. For  example, batch­level activities should not be combined with  unit­level activities. 2. T Easy Unit­level activities arise as a result of the total volume of  production and are performed each time a unit is produced. 3. T Easy Unit­level production activities are performed each time a unit is made. 4. T Easy Organization­sustaining activities are carried out regardless  of how many units are made, how many batches are run, or how  many different products are made. 5. F Easy Activity­based costing uses a number of activity cost pools,  each of which is allocated to products on the basis of direct  labor­hours. 6. F Medium The first­stage allocation in activity­based costing is the  process by which overhead costs are assigned to products before they are assigned to customers. 7. T Easy Activity rates in activity­based costing are computed by  dividing costs from the first­stage allocations by the activity measure for each activity cost pool. 8. T Medium In the second­stage allocation in activity­based costing,  activity rates are used to apply costs to products, customers,  and other cost objects. 9. T Medium In traditional costing systems, all manufacturing costs are  assigned to products­­even manufacturing costs that are not  caused by the products. 10. T Hard When there are batch­level or product­level costs, in  comparison to a traditional cost system, an activity­based  costing system ordinarily will shift costs from high­volume to  low­volume products.

(2)

11. F Medium An activity­based costing system is generally easier to set up  and run than a traditional cost system. 12. F Medium Activity­based costing is a costing method that is designed to  provide managers with cost information for strategic and other  decisions that potentially affect only variable costs. 13. F Medium In activity­based costing, as in traditional costing systems,  nonmanufacturing costs are not assigned to products. 14. F Medium In activity­based costing, a plant­wide overhead rate is used  to apply overhead to products. 15 F Medium Changing a cost accounting system is likely to meet with little resistance in an organization since it is a technical matter of little interest to individuals outside of the accounting  department. Multiple Choice 16. D Medium Which of the following levels of costs should not be allocated  to products for decision­making purposes? a. Unit­level activities. b. Batch­level activities. c. Product­level activities. d. Organization­sustaining activities 17. C Easy Testing a prototype of a new product is an example of a: a. Unit­level activity. b. Batch­level activity. c. Product­level activity. d. Organization­sustaining activity. 18. B Medium Setting up equipment is an example of a: a. Unit­level activity. b. Batch­level activity. c. Product­level activity. d. Organization­sustaining activity. 19. B Hard The clerical activity associated with processing purchase  orders to produce an order for a standard product is an example of a: a. Unit­level activity. b. Batch­level activity. c. Product­level activity. d. Organization­sustaining activity.

(3)

20. D Medium Worker recreational facilities is an example of a cost that  would ordinarily be considered to be: a. Unit­level. b. Batch­level. c. Product­level. d. Organization­sustaining. 21. B Medium Arranging for a shipment of a number of different products to a customer is an example of an activity at which of the following levels? a. Unit­level activity. b. Batch­level activity. c. Customer­level activity. d. Organization­sustaining activity. 22. D Medium Human resource management is an example of an activity at which of the following levels? a. Unit­level activity. b. Product­level activity. c. Batch­level activity. d. Organization­sustaining activity. 23. D Medium Which of the following would be classified as a product­level  activity? a. Machine setup for a batch of a standard product. b. Cafeteria facilities available to and used by all employees. c. Human resource management. d. Advertising a product. 24. C Hard Departmental overhead rates may not correctly assign overhead  costs due to: a. the use of direct labor hours in allocating overhead costs  to products rather than machine time or quantity of  materials used. b. the high correlation between direct labor­hours and the  incurrence of overhead costs.  c. over­reliance on volume as a basis for allocating overhead  costs where products differ regarding the number of units  produced, lot size, or complexity of production. d. difficulties associated with identifying cost pools for the  first stage of the allocation process. 25. B Medium Overhead allocation based on volume alone: a. is a key aspect of the activity­based costing model. b. will systematically overcost high­volume products and  undercost low­volume products. c. will systematically overcost low­volume products and  undercost high­volume products. d. must be used for external financial reporting.

(4)

26. C Medium Paul Company has two products: A and B. The company uses  activity­based costing. The estimated total cost and expected  activity for each of the company's three activity cost pools  are as follows:   Activity       Estimated      Expected Activity        Cost Pool      Cost      Product A    Product B    Total  Activity 1       P22,000        400      100        500  Activity 2       P16,240        380      200        580  Activity 3       P14,600        500      250        750 The activity rate under the activity­based costing system for  Activity 3 is closest to: a. P70.45. b. P28.87. c. P19.47. d. P58.40. 27. B Medium Selena Company has two products: A and B. The company uses  activity­based costing. The estimated total cost and expected  activity for each of the company's three activity cost pools  are as follows:   Activity       Estimated      Expected Activity         Cost Pool      Cost      Product A    Product B    Total  Activity 1       P17,600        800      300       1,100  Activity 2       P12,000        500      200         700  Activity 3       P26,000        800      400       1,200 The activity rate under the activity­based costing system for  Activity 3 is closest to: a. P46.33. b. P21.67. c. P65.00. d. P18.53.

(5)

28. D Hard Matt Company uses activity­based costing. The company has two  products: A and B. The annual production and sales of Product A  is 8,000 units and of Product B is 6,000 units. There are three  activity cost pools, with estimated total cost and expected  activity as follows:   Activity       Estimated      Expected Activity        Cost Pool      Cost      Product A    Product B     Total  Activity 1       P20,000        100      400      500  Activity 2       P37,000        800      200        1,000  Activity 3       P91,200        800        3,000        3,800 The cost per unit of Product A under activity­based costing is  closest to: a. P2.40. b. P3.90. c. P10.59. d. P6.60. 29. Bridget Company uses activity­based costing. The company has two  products: A and B. The annual production and sales of Product A  is 2,000 units and of Product B is 3,000 units. There are three  activity cost pools, with estimated total cost and expected  activity as follows:   Activity       Estimated      Expected Activity          Cost Pool      Cost      Product A    Product B     Total  Activity 1        P9,000        400      350      750  Activity 2       P12,000        100      400      500  Activity 3       P48,000        400        1,200        1,600 The cost per unit of Product A under activity­based costing is  closest to: a. P6.00. b. P9.60. c. P8.63. d. P13.80. Reference: 8­1 Note to the Instructor: Questions 30 to 32, 33 to 35, and 36 to 38 are  different versions of the same questions. Dideda Company uses an activity­based costing system with three activity  cost pools. The company has provided the following data concerning its costs and its activity based costing system:

(6)

Costs:   Manufacturing overhead ...  P360,000   Selling and admin. expenses ...  P240,000     Total ...  P600,000 Distribution of resource consumption:         Activity Cost Pools             Order     Customer        Size      Support   Other    Total   Manufacturing overhead ...  25%         65%      10%     100%   Selling and admin. expenses ....  60%         20%      20%     100%     The "Other" activity cost pool consists of the costs of idle capacity  and organization­sustaining costs.     You have been asked to complete the first­stage allocation of costs to  the activity cost pools. 30. D Easy Refer To: 8­1 How much cost, in total, would be allocated in the first­stage  allocation to the Order Size activity cost pool? a. P150,000 b. P360,000 c. P255,000 d. P234,000 31. B Easy Refer To: 8­1 How much cost, in total, would be allocated in the first­stage  allocation to the Customer Support activity cost pool? a. P255,000 b. P282,000 c. P120,000 d. P390,000 32. C Medium Refer To: 8­1 How much cost, in total, should NOT be allocated to orders and  products in the second stage of the allocation process if the  activity­based costing system is used for internal decision­ making? a. P60,000. b. P0. c. P84,000. d. P120,000. Reference: 8­2 NOTE TO THE INSTRUCTOR: Questions 30 to 32, 33 to 35, and 36 to 38 are  different versions of the same questions. Diehl Company uses an activity­based costing system with three activity cost pools. The company has provided the following data concerning its costs and  its activity based costing system:

(7)

Costs:   Manufacturing overhead ...  P480,000   Selling and admin. expenses ...  P100,000     Total ...  P580,000 Distribution of resource consumption:         Activity Cost Pools              Order      Customer        Size       Support   Other   Total   Manufacturing overhead ...    5%        85%      10%      100%   Selling and admin. expenses ...   60%        20%      20%      100%     The "Other" activity cost pool consists of the costs of idle capacity  and organization­sustaining costs.     You have been asked to complete the first­stage allocation of costs to  the activity cost pools. 33. D Easy Refer To: 8­2 How much cost, in total, would be allocated in the first­stage  allocation to the Order Size activity cost pool? a. P348,000 b. P188,500 c. P29,000 d. P84,000 34. D Easy Refer To: 8­2 How much cost, in total, would be allocated in the first­stage  allocation to the Customer Support activity cost pool? a. P304,500 b. P493,000 c. P116,000 d. P428,000 35. A Medium Refer To: 8­2 How much cost, in total, should NOT be allocated to orders and  products in the second stage of the allocation process if the  activity­based costing system is used for internal decision­ making? a. P68,000. b. P0. c. P116,000. d. P58,000. Reference: 8­3 NOTE TO THE INSTRUCTOR: Questions 30 to 32, 33 to 35, and 36 to 38 are  different versions of the same questions. Dierich Company uses an activity­based costing system with three activity  cost pools. The company has provided the following data concerning its costs and its activity based costing system:

(8)

Costs:   Manufacturing overhead ...  P600,000   Selling and admin. expenses ...  P220,000     Total ...  P820,000 Distribution of resource consumption:       Activity Cost Pools              Order     Customer       Size      Support   Other    Total   Manufacturing overhead ...  15%        75%      10%      100%   Selling and admin. expenses ...  60%        20%      20%      100%     The "Other" activity cost pool consists of the costs of idle capacity  and organization­sustaining costs.     You have been asked to complete the first­stage allocation of costs to  the activity cost pools. 36. A Easy Refer To: 8­3 How much cost, in total, would be allocated in the first­stage  allocation to the Order Size activity cost pool? a. P222,000 b. P307,500 c. P123,000 d. P492,000 37. D Easy Refer To: 8­3 How much cost, in total, would be allocated in the first­stage  allocation to the Customer Support activity cost pool? a. P389,500 b. P615,000 c. P164,000 d. P494,000 38. B Medium Refer To: 8­3 How much cost, in total, should NOT be allocated to orders and  products in the second stage of the allocation process if the  activity­based costing system is used for internal decision­ making? a. P82,000. b. P104,000. c. P0. d. P164,000. Reference: 8­4 Davis Company uses an activity­based costing system in which there are three activity cost pools. The company has provided the following data  concerning its costs and its activity­based costing system: Costs:   Manufacturing overhead ... P400,000   Selling and admin. Expenses ... P200,000     Total ... P600,000

(9)

Distribution of resource consumption:          Activity Cost Pools                Order  Customer        Size   Support   Other  Total   Manufacturing overhead ... 35%     55%      10%    100%   Selling and admin. Expense ... 50%     30%      20%    100%     The "other" activity cost pool consists of the costs of idle capacity  and organization­sustaining costs.     You have been asked to complete the first­stage allocation of the costs  to the activity cost pools. 39. B Easy Refer To: 8­4 How much cost, in total, would be allocated in the first­stage  allocation to the Order Size activity cost pool? a. P210,000. b. P240,000. c. P300,000. d. P255,000. 40. D Easy Refer To: 8­4 How much cost, in total, would be allocated in the first­stage  allocation to the Customer Support activity cost pool? a. P255,000. b. P180,000. c. P330,000. d. P280,000. 41. C Medium Refer To: 8­4 How much cost, in total should NOT be allocated to orders and  products in the second stage of the allocation process if the  activity­based costing system is used for internal decision­ making? a. P0. b. P60,000. c. P80,000. d. P120,000. Reference: 8­5 NOTE TO THE INSTRUCTOR: Questions 42 to 44, 45 to 47, and 48 to 50 are  different versions of the same questions. Escau Company is a wholesale distributor that uses activity­based costing  for all of its overhead costs. The company has provided the following data  concerning its annual overhead costs and its activity based costing system: Overhead costs:   Wages and salaries ..  P380,000   Other expenses ...  P100,000     Total ...  P480,000

(10)

Distribution of resource consumption:          Activity Cost Pools             Filling    Customer       Orders     Support   Other    Total   Wages and salaries ..  30%         60%      10%      100%   Other expenses ...  35%         45%      20%      100%     The "Other" activity cost pool consists of the costs of idle capacity  and organization­sustaining costs.     The activity measures for the activity cost pools for the year are as  follows:       Activity Cost Pool         Activity               Filling orders ...    3,000 orders       Customer support...       20 customers 42. C Medium Refer To: 8­5 What would be the total overhead cost per order according to  the activity based costing system? In other words, what would  be the overall activity rate for the filling orders activity  cost pool? (Round to the nearest whole cent.) a. P56.00 b. P48.00 c. P49.67 d. P52.00 43. A Medium Refer To: 8­5 What would be the total overhead cost per customer according to the activity based costing system? In other words, what would  be the overall activity rate for the customer support activity  cost pool? (Round to the nearest whole peso.) a. P13,650 b. P12,600 c. P14,400 d. P10,800 44. B Hard Refer To: 8­5 To the nearest whole peso, how much wages and salaries cost  would be allocated to a customer who made 8 orders in a year? a. P14,784. b. P11,704. c. P7,392. d. P9,548. Reference: 8­6 NOTE TO THE INSTRUCTOR: Questions 42 to 44, 45 to 47, and 48 to 50 are  different versions of the same questions. Escalona Company is a wholesale distributor that uses activity­based costing for all of its overhead costs. The company has provided the following data  concerning its annual overhead costs and its activity based costing system:

(11)

Overhead costs:   Wages and salaries ..  P580,000   Other expenses ...  P200,000     Total ...  P780,000 Distribution of resource consumption:         Activity Cost Pools              Filling    Customer       Orders     Support   Other    Total   Wages and salaries ..  40%      50%     10%      100%   Other expenses ...  35%      45%     20%      100%     The "Other" activity cost pool consists of the costs of idle capacity  and organization­sustaining costs.     The amount of activity for the year is as follows:       Activity Cost Pool         Activity           Filling orders ...   1,000 orders       Customer support ....      30 customers 45. B Medium Refer To: 8­6 What would be the total overhead cost per order according to  the activity based costing system? In other words, what would  be the overall activity rate for the filling orders activity  cost pool? (Round to the nearest whole cent.) a. P273.00 b. P302.00 c. P312.00 d. P292.50 46. D Medium Refer To: 8­6 What would be the total overhead cost per customer according to the activity based costing system? In other words, what would  be the overall activity rate for the customer support activity  cost pool? (Round to the nearest whole peso.) a. P11,700 b. P13,000 c. P12,350 d. P12,667 47. C Hard Refer To: 8­6 To the nearest whole peso, how much wages and salaries cost  would be allocated to a customer who made 4 orders in a year? a. P8,859. b. P7,124. c. P10,595. d. P14,248.

(12)

Reference: 8­7 NOTE TO THE INSTRUCTOR: Questions 42 to 44, 45 to 47, and 48 to 50 are  different versions of the same questions. Escoto Company is a wholesale distributor that uses activity­based costing  for all of its overhead costs. The company has provided the following data  concerning its annual overhead costs and its activity based costing system: Overhead costs:   Wages and salaries ..  P540,000   Other expenses ...  P200,000     Total ...  P740,000 Distribution of resource consumption:         Activity Cost Pools              Filling    Customer       Orders     Support   Other    Total   Wages and salaries ..  10%      80%     10%      100%   Other expenses ...  20%      60%     20%      100%     The "Other" activity cost pool consists of the costs of idle capacity  and organization­sustaining costs.     The amount of activity for the year is as follows:       Activity Cost Pool         Activity            Filling orders ...   4,000 orders       Customer support ....      40 customers 48. C Medium Refer To: 8­7 What would be the total overhead cost per order according to  the activity based costing system? In other words, what would  be the overall activity rate for the filling orders activity  cost pool? (Round to the nearest whole cent.) a. P27.75 b. P37.00 c. P23.50 d. P18.50 49. D Medium Refer To: 8­7 What would be the total overhead cost per customer according to the activity based costing system? In other words, what would  be the overall activity rate for the customer support activity  cost pool? (Round to the nearest whole peso.) a. P12,950 b. P11,100 c. P14,800 d. P13,800 50. D Hard Refer To: 8­7 To the nearest whole peso, how much wages and salaries cost  would be allocated to a customer who made 8 orders in a year? a. P7,474. b. P14,948. c. P9,191. d. P10,908.

(13)

Reference: 8­8 NOTE TO THE INSTRUCTOR: Questions 51 to 54 and 55 to 58 are different  versions of the same questions. Acton Company has two products: A and B.  The annual production and sales of Product A is 800 units and of Product B is 500 units. The company has  traditionally used direct labor­hours as the basis for applying all  manufacturing overhead to products. Product A requires 0.3 direct labor  hours per unit and Product B requires 0.2 direct labor hours per unit. The  total estimated overhead for next period is P92,023.   The company is considering switching to an activity­based costing system  for the purpose of computing unit product costs for external reports. The  new activity­based costing system would have three overhead activity cost  pools­­Activity 1, Activity 2, and General Factory­­with estimated overhead  costs and expected activity as follows:        Estimated   Activity       Overhead      Expected Activity             Cost Pool        Costs      Product A    Product B      Total  Activity 1       P14,487        500      600         1,100  Activity 2       P64,800      2,500      500         3,000  General Factory  P12,736        240      100       340    Total      P92,023 (Note: The General Factory activity cost pool's costs are allocated on the  basis of direct labor hours.) 51. D Medium Refer To: 8­8 The predetermined overhead rate under the traditional costing  system is closest to: a. P37.46. b. P21.60. c. P13.17. d. P270.66. 52. A Medium Refer To: 8­8 The overhead cost per unit of Product B under the traditional  costing system is closest to: a. P54.13. b. P7.49. c. P4.32. d. P2.63. 53. B Medium Refer To: 8­8 The predetermined overhead rate (i.e., activity rate) for  Activity 1 under the activity­based costing system is closest  to: a. P28.97. b. P13.17. c. P83.66. d. P24.15.

(14)

54. A Hard Refer To: 8­8 The overhead cost per unit of Product A under the activity­ based costing system is closest to: a. P86.97. b. P70.79. c. P81.20. d. P11.24. Reference: 8­9 NOTE TO THE INSTRUCTOR: Questions 51 to 54 and 55 to 58 are different  versions of the same questions. Addy Company has two products: A and B. The annual production and sales of  Product A is 1,700 units and of Product B is 1,100 units. The company has  traditionally used direct labor­hours as the basis for applying all  manufacturing overhead to products. Product A requires 0.3 direct labor  hours per unit and Product B requires 0.6 direct labor hours per unit. The  total estimated overhead for next period is P98,785.   The company is considering switching to an activity­based costing system  for the purpose of computing unit product costs for external reports. The  new activity­based costing system would have three overhead activity cost  pools­­Activity 1, Activity 2, and General Factory­­with estimated overhead  costs and expected activity as follows:        Estimated   Activity       Overhead      Expected Activity               Cost Pool        Costs      Product A    Product B      Total  Activity 1       P30,528      1,000      600         1,600  Activity 2       P17,385      1,700      200         1,900  General Factory  P50,872        510      660         1,170    Total      P98,785 (Note: The General Factory activity cost pool's costs are allocated on the  basis of direct labor hours.) 55. C Medium Refer To: 8­9 The predetermined overhead rate under the traditional costing  system is closest to: a. P9.15. b. P43.48. c. P84.43. d. P19.08. 56. A Medium Refer To: 8­9 The overhead cost per unit of Product B under the traditional  costing system is closest to: a. P50.66. b. P5.49. c. P26.09. d. P11.45.

(15)

57. A Medium Refer To: 8­9 The predetermined overhead rate (i.e., activity rate) for  Activity 2 under the activity­based costing system is closest  to: a. P9.15. b. P51.99. c. P86.93. d. P10.23. 58. D Hard Refer To: 8­9 The overhead cost per unit of Product B under the activity­ based costing system is closest to: a. P50.66. b. P26.09. c. P35.28. d. P38.16. Reference: 8­10 NOTE TO THE INSTRUCTOR: Questions 59 to 60 and 61 to 62 are different  versions of the same questions. Abel Company uses activity­based costing. The company has two products: A  and B. The annual production and sales of Product A is 200 units and of  Product B is 400 units. There are three activity cost pools, with estimated  costs and expected activity as follows:   Activity       Estimated      Expected Activity          Cost Pool      Cost     Product A    Product B       Total  Activity 1       P16,660        600      100       700  Activity 2       P18,450      1,100      700         1,800  Activity 3       P 9,731         60      160       220 59. D Medium Refer To: 8­10 a. P24.91. b. P26.36. c. P16.77. d. P10.25. 60. A Medium Refer To: 8­10 The cost per unit of Product B is closest to: a. P41.58. b. P81.53. c. P74.73. d. P17.69. Reference: 8­11 NOTE TO THE INSTRUCTOR: Questions 59 to 60 and 61 to 62 are different  versions of the same questions. Accola Company uses activity­based costing. The company has two products: A  and B. The annual production and sales of Product A is 1,100 units and of  Product B is 700 units. There are three activity cost pools, with estimated  costs and expected activity as follows:

(16)

  Activity       Estimated      Expected Activity          Cost Pool      Cost      Product A    Product B       Total  Activity 1       P18,271        600      500      1,100  Activity 2       P35,891      1,600      300      1,900  Activity 3       P48,796        440      420      860 61. D Medium Refer To: 8­11 The activity rate for Activity 3 is closest to: a. P119.72. b. P116.18. c. P26.67. d. P56.74. 62. A Hard Refer To: 8­11 The cost per unit of Product A is closest to: a. P59.23. b. P57.20. c. P47.89. d. P22.70. Reference: 8­12 Arthur Company has two products: S and D. The company uses activity­based  costing and has prepared the following analysis showing the estimated total  cost and expected activity for each of its three activity cost pools: Activity      Estimated      Expected Activity            Cost Pool       Cost       Product S    Product D    Total Activity 1    P20,000         100      400        500 Activity 2    P14,600         500      250        750 Activity 3    P90,000         300        2,700      3,000 The annual production and sales of Product S is 4,547 units. The annual  production and sales of Product D is 7,913. 63. B Medium Refer To: 8­12 The activity rate under the activity­based costing system for  Activity 3 is closest to: a. P33.33. b. P30.00. c. P29.32. d. P41.53. 64. A Hard Refer To: 8­12 The cost per unit of Product S under activity­based costing is  closest to: a. P5.00. b. P1.98. c. P10.00. d. P1.83. Reference: 8­13 Monson Company has two products: G and P. The company uses activity­based  costing and has prepared the following analysis showing the estimated total  cost and expected activity for each of its three activity cost pools:

(17)

Activity      Estimated      Expected Activity            Cost Pool       Cost       Product G    Product P   Total Activity 1    P30,000         200      400        600 Activity 2    P24,000         600      900      1,500 Activity 3    P80,000         400        3,600      4,000 The annual production and sales of Product G is 10,640 units. The annual  production and sales of Product P is 26,600. 65. D Medium Refer To: 8­13 The activity rate under the activity­based costing system for  Activity 2 is closest to: a. P89.33. b. P21.97. c. P26.67. d. P16.00. 66. A Hard Refer To: 8­13 The cost per unit of Product P under activity­based costing is  closest to: a. P4.00. b. P30.16. c. P10.00. d. P6.88. Reference: 8­14 NOTE TO THE INSTRUCTOR: Questions 67 to 68, 69 to 70, and 71 to 72 are  different versions of the same questions. Forse Florist specializes in large floral bouquets for hotels and other  commercial spaces. The company has provided the following data concerning  its annual overhead costs and its activity based costing system: Overhead costs:   Wages and salaries ..   P80,000   Other expenses ...   P40,000     Total ...  P120,000 Distribution of resource consumption:         Activity Cost Pools              Making       Bouquets   Delivery    Other      Total   Wages and salaries ..   60%        30%        10%        100%   Other expenses ...   45%        25%        30%        100%     The "Other" activity cost pool consists of the costs of idle capacity  and organization­sustaining costs.     The amount of activity for the year is as follows:       Activity Cost Pool         Activity                 Making bouquets ...   60,000 bouquets       Delivery ...    5,000 deliveries

(18)

67. D Medium Refer To: 8­14 What would be the total overhead cost per bouquet according to  the activity based costing system? In other words, what would  be the overall activity rate for the making bouquets activity  cost pool? (Round to the nearest whole cent.) a. P0.90 b. P1.05 c. P1.20 d. P1.10 68. D Medium Refer To: 8­14 What would be the total overhead cost per delivery according to the activity based costing system? In other words, what would  be the overall activity rate for the deliveries activity cost  pool? (Round to the nearest whole cent.) a. P6.00 b. P6.60 c. P7.20 d. P6.80 Reference: 8­15 NOTE TO THE INSTRUCTOR: Questions 67 to 68, 69 to 70, and 71 to 72 are  different versions of the same questions. Foster Florist specializes in large floral bouquets for hotels and other  commercial spaces. The company has provided the following data concerning  its annual overhead costs and its activity based costing system: Overhead costs:   Wages and salaries ..      P70,000   Other expenses ...      P50,000     Total ...     P120,000 Distribution of resource consumption:         Activity Cost Pools                 Making       Bouquets   Delivery    Other     Total   Wages and salaries ..      70%        20%       10%       100%   Other expenses ...      45%        25%       30%       100%     The "Other" activity cost pool consists of the costs of idle capacity  and organization­sustaining costs.     The amount of activity for the year is as follows:       Activity Cost Pool         Activity              Making bouquets ...   40,000 bouquets       Delivery ...    1,000 deliveries

(19)

69. A Medium Refer To: 8­15 What would be the total overhead cost per bouquet according to  the activity based costing system? In other words, what would  be the overall activity rate for the making bouquets activity  cost pool? (Round to the nearest whole cent.) a. P1.79 b. P1.73 c. P2.10 d. P1.35 70. B Medium Refer To: 8­15 What would be the total overhead cost per delivery according to the activity based costing system? In other words, what would  be the overall activity rate for the deliveries activity cost  pool? (Round to the nearest whole cent.) a. P27.00 b. P26.50 c. P30.00 d. P24.00 Reference: 8­16 NOTE TO THE INSTRUCTOR: Questions 67 to 68, 69 to 70, and 71 to 72 are  different versions of the same questions. Foss Florist specializes in large floral bouquets for hotels and other  commercial spaces. The company has provided the following data concerning  its annual overhead costs and its activity based costing system: Overhead costs:   Wages and salaries ..      P70,000   Other expenses ...      P40,000     Total ...     P110,000 Distribution of resource consumption:          Activity Cost Pools               Making       Bouquets   Delivery    Other      Total   Wages and salaries ..      55%        35%       10%        100%   Other expenses ...      45%        25%       30%        100%     The "Other" activity cost pool consists of the costs of idle capacity  and organization­sustaining costs.     The amount of activity for the year is as follows:       Activity Cost Pool         Activity              Making bouquets ...   20,000 bouquets       Delivery ...    7,000 deliveries

(20)

71. A Medium Refer To: 8­16 What would be the total overhead cost per bouquet according to  the activity based costing system? In other words, what would  be the overall activity rate for the making bouquets activity  cost pool? (Round to the nearest whole cent.) a. P2.83 b. P2.75 c. P3.03 d. P2.48 72. D Medium Refer To: 8­16 What would be the total overhead cost per delivery according to the activity based costing system? In other words, what would  be the overall activity rate for the deliveries activity cost  pool? (Round to the nearest whole cent.) a. P3.93 b. P5.50 c. P4.71 d. P4.93 Reference: 8­17 NOTE TO THE INSTRUCTOR: Questions 73 to 75, 76 to 78, and 79 to 81 are  different versions of the same questions. Grogam Catering uses activity­based costing for its overhead costs. The  company has provided the following data concerning the activity rates in its activity­based costing system:        Activity Cost Pools       Preparing   Arranging       Meals     Functions   Wages ...  P1.15      P110.00   Supplies ...  P0.35      P380.00   Other expenses ...  P0.25       P70.00     The number of meals served is the measure of activity for the Preparing  Meals activity cost pool. The number of functions catered is used as the  activity measure for the Arranging Functions activity cost pool.     Management would like to know whether the company made any money on a  recent function at which 100 meals were served. The company catered the  function for a fixed price of P21.00 per meal. The cost of the raw  ingredients for the meals was P8.25 per meal. This cost is in addition to  the costs of wages, supplies, and other expenses detailed above.     For the purposes of preparing action analyses, management has assigned  ease of adjustment codes to the costs as follows: wages are classified as a  Yellow cost; supplies and raw ingredients as a Green cost; and other  expenses as a Red cost.

(21)

73. A Medium Refer To: 8­17 According to the activity­based costing system, what was the  total cost (including the costs of raw ingredients) of the  function mentioned above? (Round to the nearest whole peso.) a. P1,560 b. P1,760 c. P1,060 d. P910 74. D Hard Refer To: 8­17 Suppose an action analysis report is prepared for the function  mentioned above. What would be the "red margin" in the action  analysis report?  (Round to the nearest whole peso.) a. P690 b. P440 c. P390 d. P540 75. A Hard Refer To: 8­17 Suppose an action analysis report is prepared for the function  mentioned above. What would be the "yellow margin" in the  action analysis report?  (Round to the nearest whole peso.) a. P635 b. P815 c. P710 d. P760 Reference: 8­18 NOTE TO THE INSTRUCTOR: Questions 73 to 75, 76 to 78, and 79 to 81 are  different versions of the same questions. Groce Catering uses activity­based costing for its overhead costs. The  company has provided the following data concerning the activity rates in its activity­based costing system:        Activity Cost Pools       Preparing   Arranging       Meals     Functions   Wages ...  P0.70      P145.00   Supplies ...  P0.45      P230.00   Other expenses ...  P0.40      P100.00     The number of meals served is the measure of activity for the Preparing  Meals activity cost pool. The number of functions catered is used as the  activity measure for the Arranging Functions activity cost pool.     Management would like to know whether the company made any money on a  recent function at which 150 meals were served. The company catered the  function for a fixed price of P14.00 per meal. The cost of the raw  ingredients for the meals was P8.75 per meal. This cost is in addition to  the costs of wages, supplies, and other expenses detailed above.     For the purposes of preparing action analyses, management has assigned  ease of adjustment codes to the costs as follows: wages are classified as a  Yellow cost; supplies and raw ingredients as a Green cost; and other  expenses as a Red cost.

(22)

76. B Medium Refer To: 8­18 (including the costs of raw ingredients) of the function  mentioned above? (Round to the nearest whole peso.) a. P1,520 b. P2,020 c. P1,370 d. P2,220 77. A Hard Refer To: 8­18 Suppose an action analysis report is prepared for the function  mentioned above. What would be the "red margin" in the action  analysis report?  (Round to the nearest whole peso.) a. P80 b. (P20) c. (P70) d. P230 78. A Hard Refer To: 8­18 Suppose an action analysis report is prepared for the function  mentioned above. What would be the "yellow margin" in the  action analysis report?  (Round to the nearest whole peso.) a. P240 b. P365 c. P315 d. P420 Reference: 8­19 NOTE TO THE INSTRUCTOR: Questions 73 to 75, 76 to 78, and 79 to 81 are  different versions of the same questions. Grodt Catering uses activity­based costing for its overhead costs. The  company has provided the following data concerning the activity rates in its activity­based costing system:        Activity Cost Pools       Preparing   Arranging       Meals     Functions   Wages ...  P0.85      P110.00   Supplies ...  P0.50      P310.00   Other expenses ...  P0.30      P120.00     The number of meals served is the measure of activity for the Preparing  Meals activity cost pool. The number of functions catered is used as the  activity measure for the Arranging Functions activity cost pool.     Management would like to know whether the company made any money on a  recent function at which 60 meals were served. The company catered the  function for a fixed price of P19.00 per meal. The cost of the raw  ingredients for the meals was P8.60 per meal. This cost is in addition to  the costs of wages, supplies, and other expenses detailed above.     For the purposes of preparing action analyses, management has assigned  ease of adjustment codes to the costs as follows: wages are classified as a  Yellow cost; supplies and raw ingredients as a Green cost; and other  expenses as a Red cost.

(23)

79. B Medium Refer To: 8­19 According to the activity­based costing system, what was the  total cost (including the costs of raw ingredients) of the  function mentioned above? (Round to the nearest whole peso.) a. P655 b. P1,155 c. P505 d. P1,355 80. D Hard Refer To: 8­19 Suppose an action analysis report is prepared for the function  mentioned above. What would be the "red margin" in the action  analysis report?  (Round to the nearest whole peso.) a. P135 b. (P165) c. (P115) d. (P15) 81. D Hard Refer To: 8­19 Suppose an action analysis report is prepared for the function  mentioned above. What would be the "yellow margin" in the  action analysis report?  (Round to the nearest whole peso.) a. P248 b. P198 c. P303 d. P123

(24)

Essay 82. Hard Ingersol Draperies makes custom draperies for homes and  businesses. The company uses an activity­based costing system  for its overhead costs. The company has provided the following  data concerning its annual overhead costs and its activity cost pools. Overhead costs:   Production overhead ..  P120,000   Office expense ...  P120,000     Total ...  P240,000 Distribution of resource consumption:        Activity Cost Pools            Making      Job       Drapes    Support    Other     Total   Production overhead ..   35%         45%      20%       100%   Office expense ...    5%         65%      30%       100%     The "Other" activity cost pool consists of the costs of  idle capacity and organization­sustaining costs.     The amount of activity for the year is as follows:       Activity Cost Pool      Annual Activity       Making drapes ...   2,000 yards       Job support ...      160 jobs       Other ...    Not applicable Required: a. Prepare the first­stage allocation of overhead costs to the  activity cost pools by filling in the table below:        Making        Job        Drapes      Support    Other    Total    Production overhead ..    Office expense ...      Total ... b. Compute the activity rates (i.e., cost per unit of activity) for the Making Drapes and Job Support activity cost pools by filling in the table below:        Making        Job        Drapes      Support    Production overhead ..    Office expense ...      Total ...

(25)

c. Prepare an action analysis report in good form of a job that involves making 71 yards of drapes and has direct materials  and direct labor cost of P2,510. The sales revenue from this job is P4,400. For purposes of this action analysis report, direct  materials and direct labor should be classified as a Green  cost; production overhead as a Red cost; and office expense  as a Yellow cost. Answer: a. First­stage allocation        Making      Job        Drapes    Support    Other      Total    Production overhead .. P42,000    P54,000   P24,000   P120,000    Office expense ...  P6,000    P78,000   P36,000   P120,000      Total ... P48,000   P132,000   P60,000   P240,000    Activity ...  2,000      160        yards      jobs b. Activity rates (costs divided by activity)    Production overhead ..   P21.00     P337.50    Office expense ...    P3.00     P487.50      Total ...   P24.00     P825.00 c.    Overhead cost of the job.        Making      Job        Drapes      Support       Total     Activity ...      71       1     Production overhead .  P1,491.00     P337.50     P1,828.50     Office expense ...    P213.00     P487.50       P700.50       Total ...  P1,704.00     P825.00     P2,529.00     Revenue ...     P4,400.00     Green costs:        Direct materials and labor ...     P2,510.00     Green margin ...     P1,890.00     Yellow costs:        Office expense ...       P700.50     Yellow margin ...     P1,190.50     Red costs:        Production overhead ...     P1,828.50     Red margin ...      (P638.00)

(26)

83. Medium Hasty Hardwood Floors installs oak and other hardwood floors in homes and businesses. The company uses an activity­based  costing system for its overhead costs. The company has provided the following data concerning its annual overhead costs and its activity based costing system: Overhead costs:   Production overhead ..  P190,000   Office expense ...  P140,000     Total ...  P330,000 Distribution of resource consumption:          Activity Cost Pools               Installing      Job       Floors      Support    Other     Total   Production overhead ..  40%         40%       20%       100%   Office expense ...  10%         60%       30%       100%     The "Other" activity cost pool consists of the costs of  idle capacity and organization­sustaining costs.     The amount of activity for the year is as follows:       Activity Cost Pool      Annual Activity       Installing floors ...   200 squares       Job support ...      160 jobs       Other ...    Not applicable A "square" is a measure of area that is roughly equivalent to  1,000 square feet. Required: a. Prepare the first­stage allocation of overhead costs to the  activity cost pools by filling in the table below:        Installing      Job        Floors      Support    Other     Total   Production overhead ..   Office expense ...     Total ... b. Compute the activity rates (i.e., cost per unit of activity) for the Installing Floors and Job Support activity cost  pools by filling in the table below:       Installing      Job       Floors      Support   Production overhead ..   Office expense ...     Total ...

(27)

Answer: a. First­stage allocation        Installing     Job        Floors     Support     Other      Total    Production overhead  P76,000     P76,000    P38,000   P190,000    Office expense ... P14,000     P84,000    P42,000   P140,000      Total ... P90,000    P160,000    P80,000   P330,000    Activity ...   200        160       squares      jobs b. Activity rates (costs divided by activity)    Production overhead ..    P380         P475    Office expense ...     P70         P525      Total ...    P450       P1,000 c. Overhead cost of the job.        Installing      Job        Floors       Support     Total    Activity ...     3.4       1    Production overhead ..  P1,292         P475      P1,767    Office expense ...    P238         P525        P763      Total ...  P1,530       P1,000      P2,530 84. Medium Goel Company, a wholesale distributor, uses activity­based  costing for its overhead costs. The company has provided the  following data concerning its annual overhead costs and its  activity based costing system: Overhead costs:   Wages and salaries ..  P460,000   Nonwage expenses ....  P120,000     Total ...  P580,000 Distribution of resource consumption:          Activity Cost Pools              Filling    Product       Orders     Support    Other     Total   Wages and salaries ..  15%         75%       10%       100%   Nonwage expenses ....  10%         70%       20%       100%     The "Other" activity cost pool consists of the costs of  idle capacity and organization­sustaining costs.     The amount of activity for the year is as follows:       Activity Cost Pool      Annual Activity       Filling orders ...   4,000 orders       Product support ...      30 products       Other ...    Not applicable

(28)

Required: Compute the activity rates (i.e., cost per unit of activity)  for the Filling Orders and Product Support activity cost pools  by filling in the table below:       Filling   Product       Orders    Support   Wages and salaries ..   Nonwage expenses ....     Total ... Answer: First­stage allocation       Filling   Product       Orders    Support     Other      Total   Wages and salaries .  P69,000   P345,000   P46,000   P460,000   Nonwage expenses ...  P12,000    P84,000   P24,000   P120,000     Total ...  P81,000   P429,000   P70,000   P580,000   Activity ...    4,000         30        orders     products Activity rates (costs divided by activity)   Wages and salaries..   P17.25    P11,500   Nonwage expenses....    P3.00     P2,800     Total...   P20.25    P14,300 85. Medium Fife & Jones PLC, a consulting firm, uses an activity­based  costing in which there are three activity cost pools. The  company has provided the following data concerning its costs  and its activity based costing system: Costs:   Wages and salaries ...      P540,000   Travel expenses ...      P100,000   Other expenses ...      P140,000     Total ...      P780,000 Distribution of resource consumption:          Activity Cost Pools               Working On    Business       Engagements   Development    Other   Total   Wages and salaries      50%      20%      30%     100%   Travel expenses ...     60%      30%      10%     100%   Other expenses ....     35%      25%      40%     100%

(29)

Required: a. How much cost, in total, would be allocated to the Working  On Engagements activity cost pool? b. How much cost, in total, would be allocated to the Business  Development activity cost pool? c. How much cost, in total, would be allocated to the Other  activity cost pool? Answer: All three parts can be answered using a first­stage allocation of costs.       Working On    Business        Engagements   Development    Other     Total  Wages and salaries  P270,000      P108,000   P162,000   540,000  Travel expenses ..   P60,000       P30,000    P10,000  P100,000  Other expenses ...   P49,000       P35,000    P56,000  P140,000    Total ...  P379,000      P173,000   P228,000  P780,000 a. P379,000 b. P173,000 c. P228,000 86. Hard Huish Awnings makes custom awnings for homes and businesses.  The company uses an activity­based costing system for its  overhead costs. The company has provided the following data  concerning its annual overhead costs and its activity cost  pools: Overhead costs:   Production overhead ..  P150,000   Office expense ...  P100,000     Total ...  P250,000 Distribution of resource consumption:         Activity Cost Pools             Making       Job       Awnings    Support   Other     Total   Production overhead ..   45%         40%      15%       100%   Office expense ...    8%         65%      27%       100%     The "Other" activity cost pool consists of the costs of  idle capacity and organization­sustaining costs.     The amount of activity for the year is as follows:       Activity Cost Pool      Annual Activity       Making awnings ...    5,000 yards       Job support ...      200 jobs       Other ...    Not applicable

(30)

Required: a. Prepare the first­stage allocation of overhead costs to the  activity cost pools by filling in the table below:        Making      Job        Awnings    Support    Other     Total    Production overhead ..    Office expense ...      Total ... b. Compute the activity rates (i.e., cost per unit of activity) for the Making Awnings and Job Support activity cost pools  by filling in the table below:        Making      Job        Awnings    Support    Production overhead ..    Office expense ...      Total ... c. Prepare an action analysis report in good form of a job that involves making 80 yards of awnings and has direct materials and direct labor cost of P3,000. The sales revenue from this job is P4,000. For purposes of this action analysis report, direct  materials and direct labor should be classified as a Green  cost; production overhead as a Red cost; and office expense  as a Yellow cost. Answer: a. First­stage allocation        Making      Job        Awnings    Support    Other      Total    Production overhead.. P67,500    P60,000   P22,500   P150,000    Office expense... P 8,000    P65,000   P27,000   P100,000      Total... P75,500   P125,000   P49,500   P250,000    Activity ...  5,000      200       yards      jobs b. Activity rates (costs divided by activity)    Production overhead .  P13.50    P300.00    Office expense ...  P 1.60    P325.00      Total ...  P15.10    P625.00

(31)

c.    Overhead cost of the job.        Making      Job        Awnings    Support       Total    Activity ...    80      1    Production overhead .. P1,080.00     P300.00     P1,380.00    Office expense ... P  128.00     P325.00     P  453.00      Total ... P1,208.00     P625.00     P1,833.00    Revenue ...  P4,000.00    Green costs:       Direct materials and labor ...  P3,000.00    Green margin ...  P1,000.00    Yellow costs:       Office expense ...  P  453.00    Yellow margin ...  P  547.00    Red costs:       Production overhead ...  P1,380.00    Red margin ...  P( 833.00) 87. Hard Phoenix Company makes custom covers for air conditioning units  for homes and businesses. The company uses an activity­based  costing system for its overhead costs. The company has provided the following data concerning its annual overhead costs and its activity cost pools: Overhead costs:   Production overhead ..  P100,000   Office expense ...  P 50,000     Total ...  P150,000 Distribution of resource consumption:        Activity Cost Pools            Making       Job       Covers     Support   Other     Total   Production overhead ..   40%         42%      18%       100%   Office expense ...   12%         60%      28%       100%     The "Other" activity cost pool consists of the costs of  idle capacity and organization­sustaining costs.     The amount of activity for the year is as follows:       Activity Cost Pool      Annual Activity       Making covers ...    2,500 yards       Job support ...      200 jobs       Other ...    Not applicable

(32)

Required: a. Prepare the first­stage allocation of overhead costs to the  activity cost pools by filling in the table below:        Making      Job        Covers     Support   Other    Total    Production overhead ..    Office expense ...      Total ... b. Compute the activity rates (i.e., cost per unit of activity) for the Making Covers and Job Support activity cost pools by filling in the table below:        Making        Job        Covers      Support    Production overhead ..    Office expense ...      Total ... c. Prepare an action analysis report in good form of a job that involves making 50 yards of covers and has direct materials  and direct labor cost of P1,500. The sales revenue from this job is P2,500. For purposes of this action analysis report, direct  materials and direct labor should be classified as a Green  cost; production overhead as a Red cost; and office expense  as a Yellow cost. Answer: a. First­stage allocation        Making      Job        Covers    Support    Other     Total    Production overhead .. P40,000    P42,000   P18,000   P100,000    Office expense ... P 6,000    P30,000   P14,000   P 50,000      Total ... P46,000    P72,000   P32,000   P150,000    Activity ...   2,500        200       yards       jobs b. Activity rates (costs divided by activity)    Production overhead ..  P16.00     P210.00    Office expense ...  P 2.40     P150.00      Total ...  P18.40     P360.00

(33)

c.    Overhead cost of the job.       Making        Job       Covers       Support       Total     Activity ...    50      1     Production overhead .. P  800.00     P210.00     P1,010.00     Office expense ... P  120.00     P150.00     P  270.00       Total ... P  920.00     P360.00     P1,280.00     Revenue ...  P2,500.00     Green costs:        Direct materials and labor ...  P1,500.00     Green margin ...  P1,000.00     Yellow costs:        Office expense ...  P  270.00     Yellow margin ...  P  730.00     Red costs:        Production overhead ...  P1,010.00     Red margin ... (P  280.00) 88. Medium Jackson Painting paints the interiors and exteriors of homes  and commercial buildings. The company uses an activity­based  costing system for its overhead costs. The company has provided the following data concerning its activity­based costing  system.  Activity Cost Pool      Activity Measure    Annual Activity  Painting overhead ...   Square meters       10,000 square meters  Job support ...   Jobs      320 jobs  Other ...   None      Not applicable The "Other" activity cost pool consists of the costs of idle  capacity and organization­sustaining costs.     The company has already finished the first stage of the  allocation process in which costs were allocated to the  activity cost centers. The results are listed below:        Job       Painting    Support    Other     Total   Painting overhead ..  P54,000     P42,000   P24,000   P120,000   Office expense ...  P16,000     P96,000   P48,000   P160,000     Total ...  P70,000    P138,000   P72,000   P280,000

(34)

Required: a. Compute the activity rates (i.e., cost per unit of activity) for the Painting and Job Support activity cost pools by  filling in the table below. Round off all calculations to  the nearest whole cent.        Job        Painting    Support    Painting overhead ....    Office expense ...      Total ... b. Prepare an action analysis report in good form of a job that involves painting 63 square meters and has direct materials  and direct labor cost of P2,070. The sales revenue from this job is P2,500. For purposes of this action analysis report, direct  materials and direct labor should be classified as a Green  cost; painting overhead as a Red cost; and office expense as a Yellow cost. Answer: a. Activity rates (costs divided by activity)        Job       Painting    Support    Painting overhead ....     P5.40     P131.25    Office expense ...     P1.60     P300.00      Total ...     P7.00     P431.25 b.    Overhead cost of the job.       Job        Painting    Support     Total    Activity ...    63       1    Painting overhead ....  P340.20     P131.25    P471.45    Office expense ...  P100.80     P300.00    P400.80      Total ...  P441.00     P431.25    P872.25    Sales ...     P2,500.00      Green costs:         Direct materials and labor ...     P2,070.00      Green margin ...       P430.00      Yellow costs:         Office expense ...       P400.80      Yellow margin ...        P29.20      Red costs:         Painting overhead ...       P471.45      Red margin ...      (P442.25)

(35)

89. Hard Cabanos Company manufactures two products, Product C and  Product D. The company estimated it would incur P160,790 in  manufacturing overhead costs during the current period.  Overhead currently is applied to the products on the basis of  direct labor hours. Data concerning the current period’s  operations appear below:       Product C      Product D   Estimated volume       3,400 units    4,800 units   Direct labor hours per unit         1.40 hour      1.90 hours   Direct materials cost per unit    P 7.40         P12.70   Direct labor cost per unit        P14.00         P19.00 Required: a. Compute the predetermined overhead rate under the current  method, and determine the unit product cost of each product  for the current year. b. The company is considering using an activity­based costing  system to compute unit product costs for external financial  reports instead of its traditional system based on direct  labor hours. The activity­based costing system would use  three activity cost pools. Data relating to these activities for the current period are given below:       Estimated       Activity       Overhead        Expected Activity             Cost Pool      Costs     Product C  Product D   Total    Machine setups        P12,190       80         150       230    Purchase orders        79,200      730         920     1,650    General factory        69,400    4,760       9,120    13,880       P160,790    Determine the unit product cost of each product for the    current period using the activity­based costing approach. Answer: a. The expected total direct labor hours during the period are  computed as follows:     Product C: 3,400 units x 1.4 hr.    4,760 hours     Product D: 4,800 units x 1.9 hrs.   9,120 hours        Total direct labor hours        13,880 hours    Using these hours as a base, the predetermined overhead    using direct labor hours would be:      Estimated overhead cost, P160,790       ÷ Estimated direct labor hours, 13,880 = P11.58/DLH

(36)

   Using this overhead rate, the unit product costs are:       Product C     Product D    Direct materials       P 7.40        P12.70    Direct labor      14.00         19.00    Manufacturing overhead      16.22         22.01      Total unit product cost      P37.62        P53.71 b. The overhead rates for each activity center are as follows:        Estimated        Overhead    Expected     Overhead        Costs     Activity       Rate     Machine setups    P12,190       230        P53.00     Purchase orders   P79,200     1,650        P48.00     General factory   P69,400    13,880        P 5.00    The overhead cost charged to each product is:          Product C      Product D               Activity   Amount     Activity     Amount     Machine setups      80    P 4,240        150      P 7,950     Purchase orders        730     35,040        920       44,160     General factory      4,760     23,800      9,120       45,600       Total overhead cost         P63,080       P97,710     Overhead cost per unit:       Product C: P63,080 ÷ 3,400 units = P18.55 per unit.       Product D: P97,710 ÷ 4,800 units = P20.36 per unit.    Using activity based costing, the unit product cost of each    product would be:       Product C     Product D    Direct materials       P 7.40        P12.70    Direct labor      14.00         19.00    Manufacturing overhead      18.55         20.36      Total unit product cost      P39.95        P52.06

(37)

90. Hard Lionel Corporation manufactures two products, Product B and  Product H. Product H is of fairly recent origin, having been  developed as an attempt to enter a market closely related to  that of Product B. Product H is the more complex of the two  products, requiring two hours of direct labor time per unit to  manufacture compared to one hour of direct labor time for  Product B. Product H is produced on an automated production  line. Overhead is currently assigned to the products on the basis of  direct­labor hours. The company estimated it would incur  P450,000 in manufacturing overhead costs and produce 7,500  units of Product H and 30,000 units of Product B during the  current year. Unit costs for materials and direct labor are:        Product B   Product H     Direct material ...   P12         P25     Direct labor ...   P10         P20 Required: 1. Compute the predetermined overhead rate under the current  method of allocation and determine the unit product cost of  each product for the current year. 2. The company's overhead costs can be attributed to four major  activities. These activities and the amount of overhead cost  attributable to each for the current year are given below:       Estimated     Expected Activity              Overhead    Product  Product      Activity Cost Pools       Costs        B        H     Total Machine setups required ...  P180,000       600     1,200   1,800 Purchase orders issued ....    38,382       500       100     600 Machine­hours required ....    92,650     6,800    10,200  17,000 Maintenance requests issued   138,968       693       907   1,600        P450,000 Using the data above and an activity­based costing approach,  determine the unit product cost of each product for the current  year. Answer: 1. The company expects to work 45,000 direct labor­hours during the current year, computed as follows:      Product B:  30,000 units x 1 hr. ...  30,000 hours      Product H:   7,500 units x 2 hrs. ....  15,000 hours      Total direct labor­hours ...  45,000 hours

References

Related documents

Attachments are contained within a division of Company A called Division 1 Company A is assigned an NJUNS member code of COMPA.. The attachments would be

> Direct Deposit Transfer Letter > Automatic Payment Transfer Letter > Account Closure Request Letter... We’re dedicated to ensuring that your transition is a

A Financial Planner will work together with a Portfolio Manager and Tax Specialist, as necessary, to generate a solution that is tailored to your individual needs and

your death benefit for up to 25 months for home healthcare, assisted living, nursing home care and adult day care?. Payments reduce the

Percentage of Compliance Service Deliver - Financial Management Of IT Services.. S# Concerns Compliance 1 Does a formal/informal Availability Management. process exist for

Autophagy activation clears ELAVL1/HuR-mediated accumulation of SQSTM1/p62 during proteasomal inhibition in human retinal pigment epithelial cells. P62/Sequestosome 1 As a

In order to evaluate ‗ex vivo’ SMOi efficacy and to identify new potential clinical biomarkers of responsiveness, we separated, before and after 28 days start of treatment,