• No results found

Resource Piling Large Load Tests using a Reaction System

N/A
N/A
Protected

Academic year: 2021

Share "Resource Piling Large Load Tests using a Reaction System"

Copied!
38
0
0

Loading.... (view fulltext now)

Full text

(1)

Resource Piling

Large Load Tests using a

Reaction System

(2)

RESOURCE PILING’S

BACKGROUND

(3)

3

RESOURCE

PILING

Bored Piles

Secant

Piles

Kentledge

Load Test

Ancillary

Services

Contiguous

Bored Pile

Wall

Reaction

System

Load Test

Core businesses

(4)

Achievements

• Over 30 years of Piling (since 1981)

• >489 piling projects completed

• Grade L6 (unlimited piling contracts value)

• Largest & deepest piles:

Ø2.5m & 92m

• Largest Kentledge in Singapore:

5,700 ton

• Largest Reaction test in Singapore:

7,652 ton

Recent major projects: Sengkang Hospital, Marina Coastal Expressway,

Garden by the Bay, Marina Barrage, Singapore Deep Tunnel Sewerage

System, Business and Financial Centre, Tuas-A Power Station,

(5)
(6)

Singapore is land scarce (~700 km2). However it has an ever growing population

(latest figures are above 5.3 million people). This dense population results in a change in infrastructure design. Hence a need for taller buildings and

(7)

The Sail @ Marina Bay BFC @ Marina South

(8)

MCE – C483 @ Marina Coastal Expressway

(9)

5700 ton Kentledge Test, Jun 10. Biggest in Singapore

Therefore larger & taller load tests

These taller buildings and deep underground

infrastructures (tunnels,

basements, etc.) require larger and deeper piles. To ensure that these piles have sufficient capacity they are tested using load tests.

A kentledge using concrete blocks is one of the most common method of doing a load test in Singapore.

(10)

If it is not properly carried out, the outcome can be catastrophic. Such an

example is seen at the Gilstead road incident on 16 Jan 2011. A Kentledge

load test failed and blocks landed onto a public road causing:

• Road closure & traffic congestion

• Gas pipe disrupted / leakage

• Church evacuated & Kindergarten temporary stop

• Negative public perception

• Deploy SCDF, SP Power Grid, Police, etc.

(11)

Reaction from authorities

• WSH Council’s alert

• GEOSS committee

– Guidelines on good

practices

– Resource Piling (Mr. Foo

Hee Kang) invited

(12)
(13)

The team

Project Team

Name - Designation

Chairman

Foo Hee Kang – MD

Technical

Advisor

Tan Hock Seng - GM

Leader

Benjamin Lee - PM

Facilitators

Calvin Ng –

Coordinator

Mitram Gopal –

HSE Executive

(Keller)

Members

Donald Choo – Plant Mngr

Kumaresan – Site Mngr

Prabakar – Site Engineer

A team of management staff, operational staff, and safety personnel was gathered to work on a better solution to the Kentledge using

concrete blocks for high capacity load test.

(14)
(15)

Oasis Hotel

•Schedule was

developed to plan and monitor progress of the progress

•Corrective actions were taken when

deadlines were not met •Overall progress was in line with plan

Schedule of project

Implementation Review Root cause analysis Team formation Design solution Gilstead rd collapse

Project planning

(16)
(17)

Root cause analysis

The Ishikawa model along with the 5 Why model were

used to postulate the cause of the accident at Gilstead

road.

The main conclusions were:

– Height of Kentledge leading to large toppling zone

– Inadequacy of design

(18)
(19)

Alternative solutions

Description

Test time

Safety improvment

Statnamic

10 days

No dead weight but explosive

O-cell

8 days

All inside the pile. Good safety

improvement.

Kentledge (steel plates)

35 days

Reduced

1. height,

2. toppling zone

Reaction system

15 days

Reduced:

1. height,

2. lift,

3. Toppling zone,

4. Vehicular movement

4 alternative solutions to the Kentledge using concrete blocks were considered: Statnamic test, O-cell, Kentledge using steel plates, and Reaction system (using reaction from piles). The table above shows the test times and safety

(20)

Statnamic

O-cell

Steel plates

Reaction

system

$7.8 million

$0.78 million

Statnamic is an

explosive test. There are inherent risks with the handling explosive material especially with increase of test loads.

2 main difficulties with O-cells are in terms of the design (accurate

placement of the O-cell in the pile) and quality of construction (especially with the concrete just below the O-cell).

Estimated cost of steel plates for a 7,068 ton Kentledge test is S$7.8 million. This is a huge investment.

Estimated cost for a 7,068 ton Reaction load test is S$0.78. Hence this is the preferred option

Explosive

(21)

Current Capacity Limitations

However, reactions systems capacities have so far been in the range of 1,500

tons to 2,000 tons. Hence the Reaction System load test would need to be

re-designed to allow test of more than 4,000 tons.

Addition factors considered during the re-designing process were

-

Ease of transport,

-

Assembly technique,

-

New safety risks (if any),

-

Time of fabrication,

-

Detailed cost calculations

-

etc.

(22)
(23)

Reaction system

Reaction

Piles

(24)
(25)

Height reduction

-2 1 ,1 4 5 m m 3750 5250 7500 2176 838 912 338 381 1400 5400 3350 3350 5400 1300 2000 Pile Head 835 760 15000 16 ,500

21.2m

6.4m

A 7,068 ton Kentledge using concrete blocks (left) would require employees to work at a maximum height of 21.2 m

whereas a Reaction load test of the same capacity would

require employees to work at a much reduced 6.4 m.

(26)

Toppling zone

21,145mm 3750 5250 7500 2176 838 912 338 381 1400 5400 3350 3350 5400 1300 2000 PileHead 835 760 15000 16,500

Area = 900m²

78.6m

Area = 5,300 m²

78.6m

Height: 21.2m Height: 6.4m

A 7,068 ton Kentledge using concrete blocks (left) has a toppling area of

5,300 m2 whereas a Reaction load test

of the same capacity has a toppling area of 900 m2

(27)

Height

Toppling

Zone

Lifts

Traffic

Cost

Reaction

System

15 m

(70%)

Reduced

4,400 m

2

(83%)

Reduced

3,900

(97%)

Reduced

425

(94%)

Reduced

S$ 182,000

(15%)

annual

savings

Figures are based on 7,068 ton tests

Figures compares a Reaction System load test to a Kentledge load test using concrete blocks

Savings calculations are based on annualized costs and includes estimates of life cycles of materials such

as concrete, steel, jacks, etc.

(28)
(29)

Design & Standardization

The solution is standardized through the

following methods:

– Engineering design

– Method Statement

– Risk Assessments

(30)
(31)

Communication

To ensure successful implementation of the solution, the work procedures, risks and

hazards need to be communicated to the supervisors, and workers. The following are

the main methods used to communicate the solution:

• Discuss with execution team

• Brief RA & SWP

• Brief lifting plan

• Pre-start talks

(32)

Execution

Having communicated the solution, the work is executed on site. Execution is monitored

at several points to ensure that work being carried out complies to safe work

(33)

Execution

An example of the completed setup (a 7,652 ton) load test using the Reaction System at Ophir road, Singapore.

(34)
(35)

Projects completed

Project

Test Load

Done on

Oasis Hotel @ Peck

Seah St.

5380t

2012 Aug.

M+S Project @ Ophir

Road

7652t

2012 Nov.

7652t

2012 Nov.

6240t

2013 Feb.

5046t

2013 Apr.

6240t

2013 Mar.

7532t

2013 May

TRX(Tun Razak

Exchange @

Malaysia)

7500t

2013 Oct

7500t

2013 Oct

Tampines Town Hub

@ Tampines Ave.4

(36)
(37)

Results

Tangible results

o

Height of load test

= Reduced

o

Work-at-Height exposure height & hours

= Reduced

o

Number of lifts using cranes

= Reduced

o

Toppling zone

= Reduced

o

Vehicular movement on the road

= Reduced

o

Productivity

= Increased

Intangible results

o

Workers morale

= Improved

o

Safety awareness

= Improved

(38)

References

Related documents

dba_part_col_statistics Provides column statistics and histogram information for partitions of all tables in the database.. dba_part_histograms Provides histogram data (endpoints

study, five statistical algorithms were imple- mented to form the functionality of the model maintenance system: data preprocessing, se- lective data restriction, model

The work attempts to elucidate the idea of religious pluralism of two very im- portant figures in the traditions of Judaism and Islam: Abraham Joshua Heschel (1907-1972)

Membership of the Board consists of individuals who are involved in or concerned with the education and/or provision of services to Indian children with disabilities, Indian

Actions, Ground properties, Characteristic values of geotechnical parameters, Cautious estimate, Partial factors of safety, Design values, Design effects of actions,

While earlier attempts were only focused on representing the mean degree of loss for different process magnitudes observed, our approach allows risk man- agers to model future losses

Appliances- Large Appliances- Small Books Clothing Computer Equipment Electr Other Food Fur Household Items Mattr Box Spring Medical Equipment Toys Other Pick Up Tax

This dissertation seeks to explore the use of personal therapy among trainees and the extent to which use of personal therapy is supported by training programs, perceptions