Basic
Legend
Name of assessor
1
Dr. Günter Löhnert
For these cells enter text or
data
Email of assessor
2
[email protected]
Select appropriate value
from drop-down values
Date of completion of
assessment
3
September 5, 2014
Cells containing calculated
results
Project Name
4
Paul-Wunderlich-Haus
Year of start of construction 18
2005
Climate zone 27
5A, 5B and 5C Cool-Humid
(5A),Dry (5B), Marine (5C)
City and Country location
5 Eberswalde, Brandenburg, Germany
Year that building was
occupied
19
2007
Typical Heating-degree days
for location (oC)
28
3300
Address
6 Am Markt 1, 16225 Eberswalde
Number of years operation
with full occupancy
20
7
Typical Cooling degree-days
for location (oC)
29
480
Owner(s)
7
Office: Barnim County Administration /
Retail: Individual owner of retail stores
Developer(s)
8
Barnim County Administration and
Barnim Local Savings Bank under
public-law
New or renovation
21
Newbuild
Number of floors above grade,
including ground floor
30
4
Contract type
9 general planner
Energy simulation and
analysis tool(s) used
22
thermal: TRNSYS;
daylight: ADELINE
Number of floors below grade 31
0
Architect of record
10
GAP Gesellschaft für Architektur und
Projektmanagement mbH
Green assessment or rating
tool(s), if used
23
BNB / DGNB
Site area [m²] 32
12666
Prime contractor
11
GAP Gesellschaft für Architektur und
Projektmanagement mbH
2D or 3D models available? 24
Net conditioned (heated or
cooled) floor area in m² for all
occupancies
33
17131
Structural engineer 12
Marzahn & Rentzsch Ingenieurbüro für
Baustatik und Baukonstruktion
Net unconditioned floor area
m² for all occupancies
34
2267
HVAC designer /
Mechanical engineer
13 teamgmi Ingenieurbüro GmbH
Total net floor area for all
occupancies (33 + 34)
35
19398
Electrical engineer
14 Licht- und Elektroplanung Hecht
Primary occupancy type 25
Office
for p
T
Tota
s
otal net floor area
rimary occupancy
36
17131
Cost consultant / quantity
surveyor
15 Architekturbüro Manfred Schasler
Secondary occupancy type 26
Other occupancy
l net floor area for
econd occupancy
37
2267
Energy modeler / energy
engineer
16 teamgmi Ingenieurbüro GmbH
Other consultant 17
Dr. Günter Löhnert; sol·id·ar
planungswerkstatt
Timeline
Project Area
Note: any numbers
shown in yellow cells
are only examples to
show how the system
works, and should be
Occupancy Type
Project Type
Climate
Basic
General notes
The unconditioned floor area (#34) is the parking house. There´s no direct relation to the occupancies.
As an EnOB-project the Paul-Wunderlich-Haus was under intense surveillance. Due to that it was planned, built
and monitored profounder than the other German projects, what led to smaller deviations.
E F G H I J
No.
Performance Indicator
Reference
standard
Calculated
performance at
Design stage
Actual
operational
performance
Difference between Actual & Reference Difference between Actual & CalculatedUnits
Researcher comments
Regulatory requirements or standards (Ashrae, CEN, ISO…) Predicted by simulations, calculations, or construction data Measured over a minimum of 2 years operation % Difference between Reference
[E] & Actual [G] performance
% Difference between Calculated
[F] and Actual [G] performance Year of design data First year of ops data
2006 2010
S: Site
Optional
S1
Percent of area with protected or restored habitat0%
0%
0%
%
The site was waste land in the city center since World War II. During the GDR plants and trees covered the area, but were not cultivated in high quality. After 1990 a pavillon was erected but the site was still merely unused. Thus there was nothing to protect or to restore within the meaning of the indicator. OptionalS2
Percent of area of site or building roof(s) with measures to reduce heat
Island effect
100%
62%
-38%
%
The design stage value is 100%, as there were plants and trees. Nowadays there is still 62% of the area planted (most on the flat roofs of the building).
Optional
S3
Percent by volume stormwater sent off site70%
70%
0%
%
70% (estimated figure) as there is no rainwater collection and utilization, except water retention by the green roofs and small planted areas in the courtyard.E: Energy and Emissions (annual basis except where noted)
Required
E1
Total delivered electricity56
84
50%
kWh/m²a
The difference between the design stage and the Actual Operational Performance is substantiated in both the increased number of events that actually take place in the building (10 events per year were planned, in fact there are more than 400) and a higher default indoor temperature in winter compared with design. In addition decentral heaters are used in a few offices.Required
E2
Total delivered fossil fuel energy0
0
0%
kWh/m²a
Required
E3
Total delivered other energy0
0
0%
kWh/m²a
Required
E4
On-site renewable electricity generated (If available)4,1
4,3
3%
kWh/m²a
Electricity generated by photovoltaic plants on the roof and the south-facing wall of the multi-storey car park with a total area of 1.755 m² and 108 kWpRequired
E5
Other on-site renewable energy collected (If available)22,9
21,6
-6%
kWh/m²a
Collected energy from 530 energy piles (out of 850 piles for the foundation). The difference between the design stage and the Actual Operational Performance represents an adequate range.Required
E6
Total energy exported off-site (if applicable)4,1
4,3
3%
kWh/m²a
The on-site generated energy is exported completely to the grid.Required
E7
operating uses (E1+E2+E3+E4+E5 - E6) Building energy use intensity for all140
79
106
-25%
34%
kWh/m²a
The reference standard refers to buildings that are heated only. Source: German assessment system BNB Use & Operation; Criteria 1.2.1 - Heating and Energy Consumption.The difference between the design stage and the Actual Operational Performance is smaller than the difference in E1, because E4 and E5 have no significant difference between their stages. RequiredE8
Net delivered energy use intensity for all operating end uses (E1+E2+E3)-
52
80
0%
54%
kWh/m²a
A reference standard for this purpose does not exist in Germany.Required
E9
Greenhouse gas from delivered energy for all operating end uses.51,7
2,1
3,2
-94%
54%
Kg GHG/m² *
yr.
The reference standard refers to buildings that are heated only. Source: German assessment system BNB Use & Operation; Criteria 1.1.1 - GHG Emissions due to Heating and Electric Energy Consumption.Calculated with factors from the German Federal Environment Agency (UBA). (Factor = 0.04 kg CO2/kWh for green energy) uba.klima-aktiv.de/ The difference between design stage and Actual Operational Performance reflects the difference in E8 with changes of the factors for GHG.Optional
E10
Energy consumption for Heating, Ventilation and Air Conditioning21
26,3
25%
kWh/m²a
As already mentioned in E1, the default indoor temperature had to be levelled up in winter. OptionalE11
Energy consumption for Lighting10
9,5
-5%
kWh/m²a
The difference between the actual and calculated value corresponds to the typical standard deviation.Optional
E12
Energy Consumption for Domestic Hot Water (DHW)1
kWh/m²a
Through the arrangement of meters the DHW is not metered separately in the Actual Operational Performance. There is no reason why it should be significantly higher, because the amount of water (W1) did not change that much.Optional
E13
Energy consumption for Plugloads23,5
kWh/m²a
There is no separate evaluation of this value. The value is calculated by subtraction of the sum of E10; E11; E12 and E14 from E1. The difference is caused mainly on the forty-fold increase of events. The energy for event technology is included within this value. Approx. 1 kWh/m²a can be subtracted for DHW.
Optional
E14
Energy consumption for external uses (outside lighting, etc)0,5
0,7
40%
kWh/m²a
The higher Actual Operational Performance is also explainable with the higher amount of events that take place in the building.M: Materials and waste
Optional
M1
Total percentage of construction waste diverted from landfill (%)-
-
0%
Weight (kg), volume (m3) or
cost of total materials
Optional
M2
Amount of re-used / recycled materials in project.-
-
0%
Weight (kg), volume (m3) or
cost of total materials
W: Water
Required
W1
Potable water delivered to the building-
4.117
4.587
0%
11%
m³ water delivered per
year.
Analogously to the increased electricity demand, the demand of water ascended according to the higher number of events and the associated use of the toilets, which was not considered during the desgin stage.
Required
W2
Recycled or captured water used in the project (If available)0
0
0%
m³ per year. There is no water recycled or captured in this project.Required
W3
Gross water use intensity per occupant5,800
6,805
7,235
25%
6%
m³ gross water use per occupant per
Required
W4
Gross water use intensity per m2 of conditioned area.0,310
0,240
0,268
-14%
11%
m³ gross water use per m2 per
year. Optional
W5
Water required for building occupants (bathrooms, kitchens, etc)-
-
-
0%
0%
m³ water per occupant peryear. Optional
W6
equipment per m2 of conditioned area. Water required for building technical-
-
-
0%
0%
m³ water per m2 of conditionedarea per year.
Optional
W7
Irrigation water use-
-
-
0%
0%
m³ water per m2 oflandscaped site
Q: Indoor environmental quality
Note that values for Q1, Q2, Q3, Q6 and Q7 may be a range of numbers rather than single numbers.
Optional
Q1
Daylight factor in a typical room or space at lowest typical floor.≥ 1,5 - <10
>2 (- <10)
2,2 - 9,6
+47% / -4%
+10% / -4%
Percent daylight factorThe reference value and the value at design stage refer to German assessment system BNB criteria 3.1.5. (visual comfort).
At the design stage a high-peak was not explicitly defined, but 10% should not be exceeded to avoid overheating. One of the goals of the project was to reach a high daylight factor, therefore the interval has been set with an increased bottom limit. This goal was reached easily, as one can see in the Actual Operational Performance .
Required
Q2
Ambient illumination level in a typical room or space.500
500
500
0%
0%
Calculated or measured Lux levesl
According to the Arbeitsstättenrichtlinie (ASR - Guideline for Workplaces) the level of illuminace at workplaces has to be 500 Lux. If the amount of daylight is not sufficient, electric light will be switched on automatically to compensate.
Required
Q3
Temperature range in a typical occupancy20 - 26
20 - 26
20 - 27
0% / +4%
0% / +4%
Temperature in deg C presented as a
range
The reference standard, given by the Arbeitsstättenrichtlinie (ASR - Guideline for Workplaces), is congruent with the calculated performance. The Actual Operational Performance differs slightly at the upper area.
Optional
Q4
Thermal comfort in a typical occupancy (temperature, RH, dry and wet bulb temps)-
-
-
-
-
TBA Values for this indicator are not available. It would have been too much effort to measure or calculate them.Required
Q5
Acoustic quality within a typical occupancy-
-
-
-
-
A-weightedambient DBA Values for this indicator are not available. It would have been too much effort to measure or calculate them.
Required
Q6
IAQ: CO2 concentration in a typical occupancy.≤ 1,000
< 1,500
771
30%
-49%
ppm The reference value, based on the German assessment system BNB, describes an hourly average concentration of 1,000 ppm, which allows peaks up to 1,500 ppm. The calculated value represents a maximum level of 1,500 ppm that never shall be exceeded according to DIN EN 1946. The Actual Operational Performance value shows the excellent Indoor Air Quality (IAQ) of the building.Optional
Q7
Concentration of particulates in a typical occupancy.-
-
-
-
-
ppm of <2.5 ug Not metered.$: Economic factors
Required
$1
Construction cost1.255
1.262
1%
€/m²NFA The reference value refers to the German Building Cost Information Service (BKI 2013 - High Standard divided by factors for the region (Barnim) and the year 2008 and changed from GFA to NFA). The client of this project limited the bulding costs from the very beginning.Required
$2
Commissioning cost-
-
0%
Cost per m2 of net floor area(specify
Calculations for commissioning costs are neither implemented nor considered in Germany.
Required
$3
Annual operating water cost1,74
1,18
1,36
-22%
15%
€/m² NFA The reference value refers to OSCAR 2012 - service charge analysis. The buildings used in this study have an average age of 21 years. The study criteria were adapted to the the Paul-Wunderlich-Haus (e.g. GFA, location, ...).The difference between the design stage and the Actual Operational Performance goes along with the increased water demand, one can see in W1. Required$4
Annual operating energy cost12,48
9,30
14,46
16%
55%
€/m² NFA The reference value refers to OSCAR 2012 - service charge analysis. The buildings used in this study have an average age of 21 years. The study criteria were adapted to the the Paul-Wunderlich-Haus (e.g. GFA, location, ...).The difference between the design stage and the Actual Operational Performance is based on the higher energy demand (E1 and others), a provider change every two years, raising taxes and the share in costs and grid fees.OF: Occupancy factors
Required
OF1
Typical number of occupants per day during normal operating conditions.605
634
0%
5%
of occupants per Typical number dayThe value of the design stage is an average value, a certain amount of occupants work as field personnel and can not be counted as a full occupant. The numbers also include visitors in the offices.
Required
OF2
Typical person-hours of occupancy per year1.832
1.832
0%
0%
Number of hours per year
spent in the building by a
Average full time job with 8 h/d at 229 d/a (24 vacation days / 8 holidays)
Required
OF3
Annual occupancy intensity during typical operating conditions.1,11
1,16
0%
5%
No. occupants x typical person-hrs occupancy per year divided
As there´s no change of typical person-hours (OF2) the difference is the same as in OF1.
Required
OF4
Typical weekly operating hours of building.55
55
0%
0%
hours per week Number ofbuilding is open
Monday - Friday; 7:00 am - 6:00 pm (flexitime for office use / retail not considered)
Required
OF5
Number of days per year that building systems are operating253
253
0%
0%
Number of days per year building is open to users.
365 d - 52 weekends (104 d) - 8 holidays except the weekends in Brandenburg (e.g. Easter Sunday not counted) = 253
47,5
The reference value refers to the German VDI 3807, a nonbinding guideline on energy and water demand for buildings. The values in the guideline are from 1993, thus the difference between the reference value and the Actual Operational Performance (AOP) is not very significant.
Within this project the indicators of Materials and Waste are not collected.
The building runs with electricity solely and geothermal heating and cooling (free cooling mostly) via heat pumps. Except electricity (E1), no other energy is delivered.
see footnote 2 on Building_Info for net floor area definition The two dates shown are examples only. You should enter data for both
years
There are no separate meters for these data, thus W1 can not be divided any further. The data have not been calculated during the design stage.
94%
Elapsed years
4
To increase or decrease detail shown vertically or
horizontally, click on buttons at far top left (1 & 2).
Basic
Legend
Name of assessor
1
Steffen Ammon
For these cells enter text or
data
Email of assessor
2
[email protected]
Select appropriate value
from drop-down values
Date of completion of
assessment
3
September 5, 2014
Cells containing calculated
results
Project Name
4
Hauptzollamt Hamburg-Stadt
Year of start of construction 18
2009
Climate zone 27
5A, 5B and 5C Cool-Humid
(5A),Dry (5B), Marine (5C)
City and Country location
5 Hamburg, Hamburg, Germany
Year that building was
occupied
19
2011
Typical Heating-degree days
for location (oC)
28
3309
Address
6 Koreastraße 4, 20457 Hamburg
Number of years operation
with full occupancy
20
3
Typical Cooling degree-days
for location (oC)
29
166
Owner(s)
7 Bundesanstalt für Immobilienaufgaben
Developer(s)
8 Bundesbauabteilung Hamburg
New or renovation
21
Newbuild
Number of floors above grade,
including ground floor
30
7
Contract type
9 General Planner (AoR)
Energy simulation and
analysis tool(s) used
22
ennovatis Planning (U13)
Number of floors below grade 31
1
Architect of record
10 Winking Froh Architekten BDA
Green assessment or rating
tool(s), if used
23
BNB
Site area [m²] 32
1738
Prime contractor
11 Winking Froh Architekten BDA
2D or 3D models available? 24
Net conditioned (heated or
cooled) floor area in m² for all
occupancies
33
8293
Structural engineer 12 SFB Saradshow Fischediek
Net unconditioned floor area
m² for all occupancies
34
865
HVAC designer /
Mechanical engineer
13 HKP Ingenieure
Total net floor area for all
occupancies (33 + 34)
35
9158
Electrical engineer
14 HKP Ingenieure
Primary occupancy type 25
Office
Total net floor area
for
Tot
primary occupancy
36
9158
Cost consultant / quantity
surveyor
15 Bundesbauabteilung Hamburg
Secondary occupancy type 26
al net floor area for
second occupancy
37
Energy modeler / energy
engineer
16 BS Plan
Other consultant 17 S. Ammon (Auditor)
Note: any numbers
shown in yellow cells
are only examples to
show how the system
works, and should be
Occupancy Type
Project Type
Climate
Basic
General notes
The project was assessed after completion (post-assessment). Comparing calculated and actual performance,
it should be taken into account, that the estimation of the values at design stage was made more roughly in
comparison to the other German projects, what leads to large deviations.
Timeline
E F G H I
No.
Performance Indicator
Reference
standard
Calculated
performance at
Design stage
Actual
operational
performance
Difference
between Actual
& Reference
Difference
between Actual
& Calculated
Units
Researcher comments (please include sources of data and observations that help qualify the datapoints)Regulatory requirements or standards (Ashrae, CEN, ISO…) Predicted by simulations, calculations, or construction data Measured over a minimum of 2 years operation % Difference between Reference
[E] & Actual [G] performance
% Difference between Calculated
[F] and Actual [G] performance Year of design data First year of ops data
2008 2012
.
S: Site
Optional
S1
Percent of area with protected or restored habitat0%
0%
0%
%
The site was waste land used as a car park in Hamburg Hafen City. In terms of the assessment it is an improvement considering brownfield redevelopment. OptionalS2
Percent of area of site or building roof(s) with measures to reduce heat
Island effect
-
-
#WERT!
%
. Optional
S3
Percent by volume stormwater sent off site-
-
#WERT!
%
E: Energy and Emissions (annual basis except where noted)
Required
E1
Total delivered electricity71,8
42,15
-41%
kWh/m²a
The project was assessed after completion (post-assessment). Comparing calculated and actual performance, it should be taken into account, that the estimation of the values at design stage was made more roughly in comparison to the other German projects, what leads to large deviations.Required
E2
Total delivered fossil fuel energy0
0
0%
kWh/m²a
The building does not need any fossil fuel energy. Heat is provided by district heating.Required
E3
Total delivered other energy65,6
47,21
-28%
kWh/m²a
The project was assessed after completion (post-assessment). Comparing calculated and actual performance, it should be taken into account, that the estimation of the values at design stage was made more roughly in comparison to the other German projects, what leads to large deviations.Required
E4
On-site renewable electricity generated (If available)0
0
0%
kWh/m²a
Required
E5
Other on-site renewable energy collected (If available)0
0
0%
kWh/m²a
Required
E6
Total energy exported off-site (if applicable)0
0
0%
kWh/m²a
Required
E7
Building energy use intensity for all operating uses (E1+E2+E3+E4+E5 -
E6)
140
137
89
-36%
-35%
kWh/m²a
The reference standard refers to buildings that are heated only. Source: German assessment system BNB Use & Operation; Criteria 1.2.1 - Heating and Energy Consumption. The project was assessed after completion (post-assessment). Comparing calculated and actual performance, it should be taken into account, that the estimation of the values at design stage was made more roughly in comparison to the other German projects, what leads to large deviations.
Required
E8
all operating end uses (E1+E2+E3 - E6) Net delivered energy use intensity for-
137
89
0%
-35%
kWh/m²a
The project was assessed after completion (post-assessment). Comparing calculated and actual performance, it should be taken into account, that the estimation of the values at design stage was made more roughly in comparison to the other German projects, what leads to large deviations. RequiredE9
Greenhouse gas from delivered energy for all operating end uses.51,7
19,2
13,4
-74%
-30%
Kg GHG/m² * yr.
The reference standard refers to buildings that are heated only. Source: German assessment system BNB Use & Operation; Criteria 1.1.1 - GHG Emissions due to Heating and Electric Energy Consumption.
Calculated with factors from the German Federal Environment Agency (UBA). (uba.klima-aktiv.de/)
Differences between the design stage and the Actual Operational Performance reflect the difference in E8 with slight changes of the factors for GHG.
Optional
E10
Energy consumption for Heating, Ventilation and Air Conditioning70,9
-
-
kWh/m²a
aus EnEV-NachweisOptional
E11
Energy consumption for Lighting6,2
-
-
kWh/m²a
aus EnEV-NachweisOptional
E12
Energy Consumption for Domestic Hot Water (DHW)0,4
-
-
kWh/m²a
aus EnEV-NachweisOptional
E13
Energy consumption for Plugloads-
-
-
kWh/m²a
Optional
E14
Energy consumption for external uses (outside lighting, etc)-
-
-
kWh/m²a
.
M: Materials and waste
. Optional
M1
Total percentage of construction waste diverted from landfill (%)-
-
0%
Weight (kg), volume (m3) or cost of total materials (specify
which is used)
. Optional
M2
Amount of re-used / recycled materials in project.-
-
0%
Weight (kg), volume (m3) or cost of total materials (specify
which is used)
W: Water
Required
W1
Potable water delivered to the building-
3.300
1.820
0%
-45%
m³ water delivered per year. The project was assessed after completion (post-assessment). Comparing calculated and actual performance, it should be taken into account, that the estimation of the values at design stage was made more roughly in comparison to the other German projects, what leads to large deviations. RequiredW2
Recycled or captured water used in the project (If available)0
0
0%
m³ per year. There is no use or recycling of rainwater within this project.Required
W3
Gross water use intensity per occupant5,800
8,397
4,550
-22%
-46%
m³ gross water use per occupant peryear.
Required
W4
Gross water use intensity per m2 of conditioned area.0,310
0,398
0,219
-29%
-45%
m³ gross water use per m2 per year.Optional
W5
Water required for building occupants (bathrooms, kitchens, etc)-
-
-
0%
0%
m³ water peroccupant per year.
Optional
W6
equipment per m2 of conditioned area. Water required for building technical-
-
-
0%
0%
conditioned area per m³ water per m2 of year.Optional
W7
Irrigation water use-
-
-
0%
0%
landscaped site per m³ water per m2 ofyear.
Q: Indoor environmental quality
Note that values for Q1, Q2, Q3, Q6 and Q7 may be a range of numbers rather than single numbers.
. OptionalQ1
Daylight factor in a typical room or space at lowest typical floor.≥ 1,5 - <10
≥ 2 - <10
1 - 9
-33% / -10%
-50% / -10%
Percent daylightfactor
The reference value and the value at design stage refer to German assessment system BNB criteria 3.1.5. (visual comfort).
In terms of the assessment criteria the reference value stands for the quality level "good", as the design stage value is classified in the next better level (very good). The Actual Operational Performance was metered in June 2014.
. Required
Q2
Ambient illumination level in a typical room or space.500
500
500
0%
0%
Calculated ormeasured Lux levesl
According to the Arbeitsstättenrichtlinie (ASR - German Guideline for Workplaces) the level of illuminace at workplaces has to be 500 Lux. If the amount of daylight is not sufficient, electric light will be switched on automatically to compensate.
Required
Q3
Temperature range in a typical occupancy20 - 26
21 - 24
23,8 - 24
+19% / -8%
+13% / 0%
Temperature in deg C presented as a rangeThe reference standard is given by the Arbeitsstättenrichtlinie (ASR - German Guideline for Workplaces). The design stage calculation refers to DIN V 18599 that calls for indoor temperature heating/cooling 21 - 24°C.
The Actual Operational Performance was metered in June 2014 under worst case conditions. The result touching the higher level was expected. Optional
Q4
Thermal comfort in a typical occupancy (temperature, RH, dry and wet bulbtemps)
-
-
-
-
-
TBA Values for this indicator are not available. It would have been too much effort to measure or calculate them.Required
Q5
Acoustic quality within a typical occupancy-
-
-
-
-
A-weighted ambientDBA Values for this indicator are not available. It would have been too much effort to measure or calculate them.
Required
Q6
IAQ: CO2 concentration in a typical occupancy.≤ 1,000
-
795 - 1,091
-21% / 9%
-
ppmThe reference value, refering to the German assessment system BNB describes an hourly average concentration of 1000ppm which allows peaks up to 1500ppm. There was no value calculated at the design stage.
The Actual Operational Performance value was metered in June 2014.
Optional
Q7
Concentration of particulates in a typical occupancy.-
-
-
-
-
ppm of <2.5 ug Values for this indicator are not available. It would have been too much effort to measure or calculate them.$: Economic factors
Required
$1
Construction cost1.718
1.547
-10%
€/m²NFA The reference value refers to the German Building Cost Information Service (BKI 2013 - High Standard divided by factors for the Hamburg area and the year 2013 and changed from GFA to NFA)Required
$2
Commissioning cost-
-
0%
Cost per m2 of net floor area (specifycurrency)
Calculations for commissioning costs are neither implemented nor considered in Germany.
Required
$3
Annual operating water cost1,73
1,42
0,82
-53%
-42%
€/m²a The reference value refers to the OSCAR 2012 service charge analysis. The buildings used in this study have an average age of 21 years. The study criteria were adapted to the Main Custom Office (e.g. ground floor area, location, ...).Required
$4
Annual operating energy cost13,35
11,92
13,02
-2%
9%
€/m²aThe reference value is based on the OSCAR 2012 - service charge analysis. The buildings used in this study have an average age of 21 years. Criteria from the study were adjusted to the Main Custom Office (e.g. GFA, location, ...).
The differences can be neglected.
OF: Occupancy factors
Required
OF1
Typical number of occupants per day during normal operating conditions.393
400
0%
2%
Typical number ofoccupants per day The higher value in the Actual Operational Performance is within a normal range.
Required
OF2
Typical person-hours of occupancy per year1.840
1.840
0%
0%
Number of hours per year spent in the building by a typical
occupant
Full time job with 8 h/d at 230 d/a (24 vacation days / 7 holidays).
Required
OF3
Annual occupancy intensity during typical operating conditions.0,72
0,74
0%
2%
No. occupants x typical person-hrs occupancy per year,
divided by 1 million
The difference reflects the difference from OF1.
Required
OF4
Typical weekly operating hours of building.65
70
0%
8%
week building is open Number of hours perto users.
Design stage value based on the hours of operation according to the German DIN V 18599 (13 h/d) In reality the building is now open to users from 6:00 am until 8:00 pm (14h/d; flexitime) Required
OF5
Number of days per year that building systems are operating254
254
0%
0%
year building is open Number of days perto users.
365 d - 52 weekends (104 d) - 7 holidays except weekends in Hamburg (e.g. Easter Sunday not counted) = 254. Elapsed years
4
To increase or decrease detail shown vertically or
horizontally, click on buttons at far top left (1 & 2).
Any numbers shown in yellow cells are only examples to show how the system works, and should be removed for your project
There is no energy that is generated on-site by now, but arrangements for an installation of photovoltaics at a later stage have been made.
The energy consumption for plugloads and external use is not measured separately.
Within this project the indicators of Materials and Waste are not collected.
see footnote 2 on Building_Info for net floor area definition
The two dates shown are examples only. You should enter data for both years
Values for these indicators are not available. It would have been too much effort to measure or calculate them.
There are no separate meters for these data, thus W1 can not be divided any further. The values have not been calculated at the design stage.
The reference value refers to the VDI 3807, a nonbinding German guideline on energy and water demand for buildings. The values in the guideline are from 1993, thus the difference between the reference value and the Actual Operational Performance (AOP) does not have a high significance. The differences between the design stage and AOP is a consequential figure caused by W1.
Basic
Legend
Name of assessor
1
Julia Müller
For these cells enter text or
data
Email of assessor
2
julia.müller@
Select appropriate value
from drop-down values
Date of completion of
assessment
3
September 5, 2014
Cells containing calculated
results
Project Name
4
Bundesministerium für Umwelt
und Bau (BMUB)
Year of start of construction 18
2007
Climate zone 27
5A, 5B and 5C Cool-Humid
(5A),Dry (5B), Marine (5C)
City and Country location
5 Berlin, Berlin, Germany
Year that building was
occupied
19
2011
Typical Heating-degree days
for location (oC)
28
3193
Address
6 Stresemannstraße 128-130
Number of years operation
with full occupancy
20
3
Typical Cooling degree-days
for location (oC)
29
292
Owner(s)
7 Bundesanstalt für Immobilienaufgaben
Developer(s)
8 Projektsteuerung: Arcadis Deutschland
New or renovation
21
New & Renovation
Number of floors above grade,
including ground floor
30
6
Contract type
9 Standard Building Contract (SBC)
Energy simulation and
analysis tool(s) used
22
-
Number of floors below grade 31
2
Architect of record
10
Architekturbüro Geier Maass Pleuser,
Berlin
Green assessment or rating
tool(s), if used
23 Passive House Certificate (ZEBAU)
Site area [m²] 32
6171
Prime contractor
11 none
2D or 3D models available? 24
-Net conditioned (heated or
cooled) floor area in m² for all
occupancies
33
16928
Structural engineer 12 Wetzel von Seht
Net unconditioned floor area
m² for all occupancies
34
626
HVAC designer /
Mechanical engineer
13 Acerplan / GT-Plan
Total net floor area for all
occupancies (33 + 34)
35
17554
Electrical engineer
14 Acerplan / GT-Plan
Primary occupancy type 25
Office
To
for pri
Total
se
ficiency and sustainability t
tal net floor area
mary occupancy
36
17554
Cost consultant / quantity
surveyor
15 Arcadis Deutschland
Secondary occupancy type 26
net floor area for
cond occupancy
37
Energy modeler / energy
engineer
16 Müller BBM
Other consultant 17 Müller BBM (Brandschutz)
Note: any numbers
shown in yellow cells
are only examples to
show how the system
works, and should be
Occupancy Type
Project Type
Climate
Basic
General notes
An intense consulting regarding energy ef
ook place during the planning phase of the BMUB.
The project is still in it´s monitoring phase, that requires a fine-tuning phase in order to optimise the interaction of services.
The data of 2012 and 2013 analysed within SB Challenge 2014 derive from this fine-tuning-phase.
The proper evaluation of the consumption for the monitoring is possible since 2013 and will be finished in 2015.
Only with the differentiated consumption analysis it will be possible to make a statement about the deviance and as a result to take
corresponding measures to optimise the operation process.
Timeline
E F G H I
No.
Performance Indicator
Reference
standard
Calculated
performance at
Design stage
Actual
operational
performance
Difference between Actual & Reference Difference between Actual & CalculatedUnits
Researcher comments(please include sources of data and observations that help qualify the datapoints)
Regulatory requirements or standards (Ashrae, CEN, ISO…) Predicted by simulations, calculations, or construction data Measured over a minimum of 2 years operation % Difference between Reference
[E] & Actual [G] performance
% Difference between Calculated
[F] and Actual [G] performance Year of design data First year of ops data
2004 (2008)
2012
The values at design stage for E (Energy and Emissions) and W (Water) are calculated in 2008. .S: Site
Optional
S1
Percent of area with protected or restored habitat21%
-
-
%
The Actual Operational Performance value can not be elevated accurately caused by changes of the site border. OptionalS2
Percent of area of site or building roof(s) with measures to reduce heat Island effect
0%
0%
0%
%
The areas measure less than 1%.. Optional
S3
Percent by volume stormwater sent off site100%
100%
0%
%
E: Energy and Emissions (annual basis except where noted)
Required
E1
Total delivered electricity41,2
45,70
11%
kWh/m²a
Required
E2
Total delivered fossil fuel energy-
1,18
-
kWh/m²a
The Actual Operational Performance value stands for the delivered fuel cell gas and gas for cooking in the restaurant, which was not planned at the design stage. The fuel cell is a pilot project used for hot water in the kitchen. The value for the fuel cell only is 0,62kWh/m²a. RequiredE3
Total delivered other energy39,1
60,9
56%
kWh/m²a
District heating has increased. One reason is that the passive house needs heating support because the waste water heat pump works less efficient than planned (see E5). Actually the district heating was dimensioned and calculated for the existing building only. RequiredE4
On-site renewable electricity generated (If available)-
0,30
-
kWh/m²a
There is no value excisting for the design stage. The value in Actual Operational Performance relates to the gain from photovoltaics.Required
E5
Other on-site renewable energy collected (If available)2,5
1,62
-34%
kWh/m²a
The waste water heat pump did not perform as intended. Due to a reduced system operation, partial breakdown / stagnation of the heat pump, in the first year of operation there was approximately 20 MWh less heat generated than planned. This underperformance was compensated by the district heating.Required
E6
Total energy exported off-site (if applicable)0
0
0%
kWh/m²a
The on-site generated energy is used on-site exclusively. No energy is exported.Required
E7
operating uses (E1+E2+E3+E4+E5 - E6) Building energy use intensity for all156
83
110
-30%
33%
kWh/m²a
The reference value is calculated in proportion of the areas that are heated only (12.107m²) and the areas that are heated and ventilated (4.821m²). Source: German assessment system BNB Use & Operation; Criteria 1.2.1 - Heating and Energy Consumption.
One reason for the difference between Actual Operational Performance and Calculated can be seen in E3. Required
E8
Net delivered energy use intensity for all operating end uses (E1+E2+E3 - E6)-
80
108
-
34%
kWh/m²a
A reference standard for this purpose does not exist in Germany.Required
E9
Greenhouse gas from delivered energy for all operating end uses.84,1
11,4
17,3
-79%
52%
Kg GHG/m² * yr.
The reference value is calculated in proportion of the areas that are heated only (12.107m²) and the areas that are heated and ventilated (4.821m²). Source: German assessment system BNB Use & Operation; Criteria 1.1.1 - GHG Emissions due to Heating and Electric Energy Consumption.
Calculated with factors from the German Federal Environment Agency (UBA). (uba.klima-aktiv.de/)
Differences between the design stage and the Actual Operational Performance reflect the difference in E8 with changes of the factors for GHG.
Optional
E10
Energy consumption for Heating, Ventilation and Air Conditioning-
-
-
kWh/m²a
Optional
E11
Energy consumption for Lighting-
-
-
kWh/m²a
Optional
E12
Energy Consumption for Domestic Hot Water (DHW)-
-
-
kWh/m²a
Optional
E13
Energy consumption for Plugloads-
-
-
kWh/m²a
Optional
E14
Energy consumption for external uses (outside lighting, etc)-
-
-
kWh/m²a
.
M: Materials and waste
. Optional
M1
Total percentage of construction waste diverted from landfill (%)-
-
0%
Weight (kg), volume (m3) or cost of total materials
(specify which is used) . Optional
M2
Amount of re-used / recycled materials in project.-
-
0%
Weight (kg), volume (m3) or cost of total materials(specify which is used)
W: Water
Required
W1
Potable water delivered to the building-
1.839
2.883
0%
57%
m³ water delivered peryear. The values include water for the kitchen of the restaurant. The increased amount is not explainable by now (see comment concerning the Monitoring E10-E14).
Required
W2
Recycled or captured water used in the project (If available)0
0
0%
m³ per year. There was no recycled or captured water used in this project.Required
W3
Gross water use intensity per occupant5,800
6,110
9,452
63%
55%
m³ gross water use peroccupant per year. Required
W4
Gross water use intensity per m2 of conditioned area.0,310
0,109
0,170
-45%
57%
m³ gross water use per m2per year.
Optional
W5
Water required for building occupants (bathrooms, kitchens, etc)-
4,440
6,250
0%
41%
m³ water per occupant per year. Within this indicator the kitchen of the restaurant is not considered. The increased amount is not explainable by now (see comment concerning the Monitoring E10-E14).Design stage: Occupants: 1335 m³/a / Restaurant kitchen: 284 m³/a AOP: Occupants: 2061 m³/a / Restaurant kitchen: 719 m³/aOptional
W6
equipment per m2 of conditioned area. Water required for building technical-
0,013
0,006
0%
-54%
conditioned area per year. m³ water per m2 of The difference between the design stage and Actual Operation Performance correlates with the difference mentioned in W1.Design stage: 220 m³/a Actual: 103 m³/aOptional
W7
Irrigation water use-
-
0
0%
-
m³ water per m2 oflandscaped site per year. Water for irrigation is provided by a water well and is not metered.
Q: Indoor environmental quality
Note that values for Q1, Q2, Q3, Q6 and Q7 may be a range of numbers rather than single numbers.
. Optional
Q1
Daylight factor in a typical room or space at lowest typical floor.≥ 1,5 - <10
-
2 - 8
+ 25% / -20%
-
Percent daylight factorThe reference value and the value at design stage refer to German assessment system BNB criteria 3.1.5. (visual comfort).
There was no calculation in the design stage. The Actual Operational Performance shows that the daylightfactors stays within the interval, given by the reference standard. The values were metered in July 2014.
. Required
Q2
Ambient illumination level in a typical room or space.500
500
500
0%
0%
Calculated or measuredLux levesl
According to the Arbeitsstättenrichtlinie (ASR - German Guideline for Workplaces) the level of illuminace at workplaces has to be 500 Lux. If the amount of daylight is not sufficient, artificial light will be switched on to compensate.
Required
Q3
Temperature range in a typical occupancy20 - 26
20 - 26
22 - 26
+ 10% / 0%
+ 10% / 0%
Temperature in deg C presented as a range The reference standard is given by the Arbeitsstättenrichtlinie (ASR - German Guideline for Workplaces). OptionalQ4
Thermal comfort in a typical occupancy (temperature, RH, dry and wet bulb
temps)
-
-
-
-
TBA Values for this indicator are not available. It would have been too much effort to measure or calculate.
Required
Q5
Acoustic quality within a typical occupancy-
-
-
-
-
A-weighted ambient DBA Values for this indicator are not available. It would have been too much effort to measure or calculate.Required
Q6
IAQ: CO2 concentration in a typical occupancy.≤ 1,000
-
418 - 1,063
-58% / 6%
-
ppmThe reference value, refering to the German assessment system BNB, describes an hourly average concentration of 1000ppm, which allows peaks up to 1500ppm. There was no value calculated at the design stage.
The Actual Operational Performance value was metered in July 2014.
Optional
Q7
Concentration of particulates in a typical occupancy.-
-
-
-
-
ppm of <2.5 ug Values for this indicator are not available. It would have been too much effort to measure or calculate them.$: Economic factors
Required
$1
Construction cost2.164
3.464
60%
€/m²NFAThe reference value refers to the German Building Cost Information Service (BKI 2013 - High Standard divided by factors for the region (Berlin) and the year 2012 and changed from GFA to NFA). The increase of construction cost has different reasons. Main reasons are the passive house standard, the refurbishment of the existing building and the fact that ministry buildings have higher security standards. Other reasons are for example a complete exchange of screed, difficulties with plaster in the existing building or difficult soil conditions and a dugout from World War II, that caused an
Required
$2
Commissioning cost-
-
0%
€/m²a Calculations for commissioning costs are neither implemented nor considered in Germany.Required
$3
Annual operating water cost1,87
0,50
0,90
-52%
80%
€/m²a The reference value referes to OSCAR 2012 - service charge analysis. The buildings used in this study have an average age of 21 years. The study criteria were adapted to the BMUB.One reason for the difference between the design stage and Actual Operation Performance is the increased amount (see also W1). Required$4
Annual operating energy cost13,49
6,05
15,08
12%
149%
€/m²a The reference value referes to OSCAR 2012 - service charge analysis. The buildings used in this study have an average age of 21 years. The study criteria were adapted to the BMUB.The difference between the design stage and the Actual Operational Performance refers to the changing energy demand (E1-E5).OF: Occupancy factors
Required
OF1
Typical number of occupants per day during normal operating conditions.301
305
0%
1%
Typical number of occupants per dayRequired
OF2
Typical person-hours of occupancy per year1.840
1.840
0%
0%
Number of hours per year spent in the building by a typical occupant.Average full time job with 8.2 h/d at 223 d/a (30 vacation days / 7 holidays)
Required
OF3
Annual occupancy intensity during typical operating conditions.0,55
0,56
0%
1%
No. occupants x typical person-hrs occupancy per
year, divided by 1 million
Required
OF4
Typical weekly operating hours of building.75
75
0%
0%
Number of hours per weekbuilding is open to users. Monday - Friday; 6:00 am - 9:00 pm (flexitime)
Required
OF5
Number of days per year that building systems are operating254
254
0%
0%
Number of days per yearbuilding is open to users. 365 d - 52 weekends (104 d) - 7 holidays except the weekends in Berlin (e.g. Easter Sunday is not counted) = 254
The reference value relates to the VDI 3807, a nonbinding guideline on energy and water demand for buildings. The values in the guideline are from 1993, thus the difference between the reference value and the Actual Operational Performance does not have a high significance. The difference between the design stage and Actual Operational Performance correlates with the difference mentioned in W1.
Any numbers shown in yellow cells are only examples to show how the system works, and should be removed for your project
The monitoring itself requires a fine-tuning phase in order to optimise the interaction of services. The data of 2012 and 2013 analysed within SB Challenge 2014 derive from this fine-tuning-phase. The proper evaluation of the consumption for the monitoring is possible since 2013 and will be finished in 2015.
Within this project the indicators of Materials and Waste are not collected.
see footnote 2 on Building_Info for net floor area definition The two dates shown are examples only. You should enter data for both
years
Elapsed years