March 2013

Los Angeles County Office of Education (LACOE) Business Services, Controller’s Office

Facilities and Construction

(2)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

LOS ANGELES COUNTY HIGH SCHOOL FOR THE ARTS

(LACHSA)

STAFF ORIENTATION

March 2013

Los Angeles County Office of Education (LACOE) Business Services, Controller’s Office

Facilities and Construction

WELCOME

to your new LACOE Los Angeles County High School for the Arts! This Staff Orientation Packet is prepared to give you an understanding of the process behind the funding and building of the LACHSA project as well as an orientation to what the new building provides for LACHSA students and staff. Please let us know if there is any other information we can provide to help with your transition into this new facility.

(3)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

TABLE OF CONTENTS

Page

Welcome………..…………...…....1

Project Overview………...…...……3

New Building Orientation Building Areas………...…...………….5 Building Systems………...…...………….8 Building Support……….…...…...…………10 Training………..………...…...………….11 Safety………...…....……….12 Plans………...…...…………14 Quick-Reference Contacts………..…...…...…………19

(4)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

PROJECT OVERVIEW Project Description

 Location: 5151 State University Drive, Los Angeles, CA, on the campus of California

State University Los Angeles (CSULA) – (same address as CSULA)

 Building is comprised of three stories, with a total of 46,275 gross square feet on 1.35 acres of land, in the north east corner of the campus adjacent to Parking Lot 5

 40 year land lease with CSULA as required by the State of California School Facilities Program (SFP)

 Facility includes:

o 20 classrooms on ground and second level

o Film Classroom / Studio and Editing Room on second level

o Black Box Theater/PE/Dance Studio Classroom on third level with associated scene

shop and dressing areas

o Administrative areas, toilet rooms, and utility spaces

o Outdoor performance area on ground level at south side of building

o Green roof areas

 Architects – HMC Architects

Construction

 Utilized multi-prime construction with 21 trade bid packages which were contracted

directly to LACOE and managed by a Construction Management (CM) firm and LACOE Construction Management

 CM Firm – Bernards

Project Funding

 Funded through the SFP by Propositions 55, 47 and 1D

 Total SFP financial hardship grant: $34.5 million (includes soft and hard costs and grant for Career Technical Education)

o Current project costs include soft costs (architect, CM, inspectors, testing labs, labor compliance program, project accounting system, photo documentation, etc.), hard costs (construction costs) and furniture, fixture and equipment (FFE) costs

o SFP financial hardship status requires any balance not utilized on eligible

expenditures be returned to the SFP; unused balance may not be used for any other project or use

Design Narrative

 The building solution facilitates the unique program requirements of LACHSA.

 The minimalist design allows each class the flexibility to create a sense of community by incorporating specific themes or concepts into their décor.

 The classroom interiors have a utilitarian aesthetic appeal, more like an artist’s loft.  With the variety of art that will be studied, produced, and performed at LACHSA, the

(5)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

Project Green Innovations

 Green planted areas with installation of native plants where possible  Green roof with drip irrigation and native plants

 Abundant natural light including skylights

 Waterless urinals, dual flush water closets and automatic faucets  Occupancy sensor controls on lighting

 Energy management system

 Recycling stations

 Building materials such as concrete with fly ash and rapidly renewable materials such as bamboo flooring

 Wood without urea-formaldehyde

Leadership in Energy and Environmental Design (LEED) Certification

 LACOE is applying for LEED certification in process with an initial level goal of

becoming LEED Certified

 The Green Building Certification Institute (GBCI) assumes administration of LEED

certification for all commercial and institutional projects registered under any LEED Rating System.

 LEED credits are awarded on a 100-point scale, in 5 Performance Areas, and credits are weighted to reflect their potential environmental impacts. Additionally, 10 bonus credits are available, 4 of which address regionally specific environmental issues.

 A project must satisfy all prerequisites and earn a minimum number of points to be

certified. Certification levels based on points achieved are: o Certified – 40+ points

o Silver – 50+ points

o Gold – 60+ points

o Platinum – 80+ points

 LEED performance areas include:

o Sustainable Sites

o Water Efficiency

o Energy & Atmosphere o Materials & Resources

o Indoor Environmental Quality

o Innovation in Design (bonus points) o Regional Priority (bonus points) Project Phases

 SFP application, submitted in 2005

 Bidding & Award of Contracts – December 2010  Preliminary site preparation: started December 2010  Construction: started February 2011

 Occupancy: March 2013

(6)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

NEW BUILDING ORIENTATION Building Areas:

 Administration Area at first floor – includes: o visitor waiting area

o open office area with five (5) workstations o four (4) offices

o conference room

o accounting office o storage / file room o carpet flooring o skylights o health office

o data network room

o two (2) staff restrooms o custodial room

 Staff Support Areas at second floor – includes:

o work area/staff lounge with storage, LACOE copy machine

o kitchenette with sink, refrigerator and microwaves o six (6) tables and thirty (30) chairs

o five (5) offices adjacent to classrooms  Typical Classroom (20 total) - includes:

o desks and chairs for thirty-six (36) students o concrete or wood flooring

o exposed structure and ductwork at ceilings o skylights in some second floor classrooms o tackable acoustic wall treatment

o Audio Visual (AV) and network connections throughout building o local wireless access points in each room

o built-in storage cabinets

o whiteboards including two (2) moveable boards o mobile teacher station

o teacher data connection and phone at front of classroom o teacher desk and chair

o window shades

o equipment including projector, projection screen and speakers o one (1) 21.5” iMac and document camera on mobile teacher station o shared mobile carts with 35 MacBook Pro laptop computers

o shared mobile carts with 35 iPad tablet computers o shared mobile printer stations

(7)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)  Specialized Classroom Resources - include:

o two sinks in each visual arts classroom o single sink in science classrooms o risers in music classrooms

o mirror walls, video screens in dance and drama classrooms o dressing rooms adjacent to dance, drama and Black Box Theater

 Music Technology Computer Lab – includes:

o thirty (30) 21.5” iMac/Quad computer stations o fifteen (15) iPad tablets

o one (1) HP LaserJet printer

o pull down projector screen and projector

o iMac 27 and document camera at mobile teacher station o teacher desk and chair

o specialized student computer desks, chairs and stools  Film Studies – includes:

o chairs for thirty-six (36) students

o full studio with lighting grid and “in use” signs

o portable hanging Chroma key green screen

o editing room with TV viewing monitors and ten (10) editing stations o pull down projector screen and projector

o local wireless access point

o mobile teacher station with document camera and Blu-ray player o teacher desk and chair

o window shades

 Black Box Theater/PE/Dance Studio – includes: o reconfigurable seating platform system

o seating capacity for 260 with stackable chairs & carts o reconfigurable stage platform system

o black wood floor

o black acoustical wall treatment

o ceiling grid and theatrical lighting with exposed structure and HVAC above o full production curtains, theatrical lighting and sound system control

o floor and wall AV, power and data connections for stage and technician support o AV connections to editing, dance and drama classrooms and dressing rooms

o AV catwalk and control station

o local wireless access points

o mobile teacher station with document camera and Blue-ray player o large scale projector and motorized screen

o men’s and women’s public restrooms

o girls and boys dressing rooms

o adjacent storage for platforms and seating o rolling mirrors for PE use

o adjacent scene shop with restroom and storage, shop equipment, access to exterior

space and Black Box Theater o lobby with elevator from first floor

(8)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

 Restroom Facilities – includes:

o men’s and women’s staff restrooms on first floor o men’s and women’s public restrooms on third floor

o boy’s and girl’s restrooms, one each, on first and second floors

 Front lobby with entrance from CSULA parking lot/drop off area; interior stairway to

second floor and elevator to second and third floors

 Exterior performance area on ground floor at rear (south side) of building with special enlarged opening to classroom

 Pedestrian access to:

o 2nd floor classrooms via east and west stairs from ground floor level

o 3rd floor Black Box Theatre Lobby from Circle Drive on third floor and via west

stairway from ground floor level

(9)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

NEW BUILDING ORIENTATION - continued Building Systems:

 Audio Visual Systems building wide - includes:

o campus wide AV paging system with bell schedule, pre-programmed announcements

and emergency contacts

o designed to allow for programmable room access

o can be accessed at LACHSA administration and at LACOE Education Center

o zoned for individual room or group area for announcements

o audio from Black Box Theatre can be redistributed to other locations for event

overflow or event prep rooms (green rooms)

o classroom audio muting during announcements or emergency notifications

 Audio Visual Systems per typical classroom - includes:

o classroom control station on teacher AV podium

o AV podium contains computer, document camera, DVD player, laptop connection

o Ceiling speakers

o Wireless microphone for voice support

o classroom projector

 Network Systems – includes:

o Wired and wireless network service through CSULA and will require authentication. o Wired network service will include internet filters through LACOE.

o Wireless Access Points (WAP) – 19 total serving two wireless SSIDs, one encrypted, one unencrypted, both requiring authentication. Available to faculty, staff and students.

 Telephone Systems – includes:

o service provided by the CSULA Telecommunications Department

o some basic features are:

 Voicemail with Message Waiting Indicator

 Call Forward  Call Transfer  Conference  Ring Again *  Speakerphone *  Redial *  Volume control

o More information can be found at http://www.calstatela.edu/its/services/telecomm/ o * some features are only available on multiline phones.

(10)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)  Security Camera System – includes:

o camera and recording system by ICU Video Security – same system in use at all

LACOE Education Center locations and various LACOE school sites

o cameras throughout exterior of building, at all exterior doors, at entrances to

specialized spaces and in administration space; recording 24/7 on DVD located in secured cabinet

o will be monitored 24/7 by LACOE security at LACOE Education Center West

o can be monitored by Administration and CSULA Police

o LACOE support: Operations and Administrative Services, Facilities and

Construction, Controller’s Office, (562) 803-8447  Elevators

o two (2) located at east and west end of building, key operated

 Emergency Phone – includes:

o one (1) CSULA emergency “Blue Phone” at front of building next to main entrance

and off CSULA parking lot

(11)

Staff Orientation Los Angeles County High School for the Arts (LACHSA) NEW BUILDING ORIENTATION - continued

Building Support:

 LED screen

o programmable screen located in the administration front lobby

o use for in building announcements, calendars, special events and directions

 Drinking fountains

o located on first and second floor student restroom entrances

 Recycling program

o participation in the CSULA comingled recycling program will satisfy the requirements for LEED certification

o materials to be recycled must include at a minimum paper, corrugated cardboard, glass, plastics and metals

o one blue wastebasket container in every classroom and office area

o one large blue container in staff work area and Black Box Theatre

o one recycle trash bin provided by CSULA LACOE Support:

 Janitorial and Maintenance Services

o to be provided by LACOE vendor

o LACOE contact: Building Services, Facilities and Construction, Controller’s Office, (562) 803-8280

 Building Services

o special requests to be provided by LACOE, examples - installation of existing furniture or equipment, moving assistance

o LACOE contact: Building Services, Facilities and Construction, Controller’s Office, (562) 803-8280

 Facilities Planning Services

o special requests to be provided by LACOE, examples - space planning, furniture procurement, special signage

o LACOE contact: Facilities Planning, Facilities and Construction, Controller’s Office, (562) 803-8282

 Construction Management

o responsible for the oversight of the construction of LACHSA

o LACOE contact: Construction Management, Facilities and Construction, Controller’s Office, (562) 922-8950

 Construction and Facilities

o responsible for the oversight of LACOE Building Services, Facilities Planning Services and Construction Management

o LACOE contact: Jema Estrella, Assistant Director, Facilities and Construction, Controller’s Office, (562) 922-8981

(12)

Staff Orientation Los Angeles County High School for the Arts (LACHSA) TRAINING

Training on building systems and the Audio Visual (AV) systems will be scheduled at various times during February and March 2013. LACHSA CM firm, Bernards, will record all training sessions and provide LACOE with DVDs. LACOE and LACHSA will be able to post these recordings so that they can be made available for training new staff or to serve as refreshers when needed.

The AV contractors will provide a review sheet for your use of equipment specifically in the classrooms. This will include the overhead projector, document camera and the classroom network system. Below is a list of training items for LACHSA administration and staff.

TRAINING SYSTEM TRADE CONTRACTOR TRAINING AGENDA Electrical System

RDM Electric

Lighting Controls - Classrooms, Administration & Specialty areas RDM/Apple Valley Intrusion Alarm System

RDM/Apple Valley Fire Alarm System

HVAC System West Tech Controls for HVAC

Elevator USS Cal Builders Elevator Controls Specialties Aragon Overhead Coiling Doors

AV/Theater Lighting

Western AV Audio Visual building wide, Film & Black Box Theatre Troxell Network Audio System building wide, Film & Black Box Theatre Polaris Lighting Lighting in Film & Black Box Theatre

(13)

Staff Orientation Los Angeles County High School for the Arts (LACHSA) SAFETY

The LACOE “Safety Handbook” begins with this statement:

“LACOE is dedicated to providing a safe and healthful environment for all employees – it is a primary responsibility and one that we cannot delegate. As such, the Office requires the work that we do as LACOE employees be performed in a safe and sound manner. To this end, LACOE requests your wholehearted cooperation and support.”

It will take some time for every staff member and student to become familiar with the new LACHSA facility. Your LACHSA administration will provide information, updates and reminders to every staff member and student to follow safe practices. We would like to take this opportunity to point out several building features and areas, new to the LACHSA environment, which should be treated carefully and with safety in mind at all times:

 Elevators – These are located at the east and west end of the building. The elevators are key operated only and can be opened for operation by LACHSA administration. Please follow posted instructions and allowances for the number of occupants.

 Stairs – There are three (3) sets of stairs to provide access to the second floor classrooms and facilities. The main set of stairs is located at the front lobby of the building. There are two other sets of stairs, one at each end (east and west) of the building.

Use handrails at all times. Do not attempt to carry heavy or bulky objects up or down stairs without assistance. Do not sit on handrails or the support walls of any stair case. Keep stairs clear of items, trash or debris to eliminate tripping hazards.

Student access to the third floor via the west stairs should be strictly limited to special events and in the case of emergencies only.

 Balconies – The main set of stairs in the front lobby has a balcony overlooking the lobby from the second floor. The other stairs have balconies at intermediate landings and at the top of the stair landing. Do not sit or place objects on the balcony walls or railings at any time. Do not lean on railings.

 Storage – Each classroom has built in storage cabinets that extend up to the soffit. Follow safety instructions for the use of all storage areas. Never stand on chairs or desks to access overhead storage.

 Fire extinguishers are located:

o in each classroom

o in Administration offices

o in the corridors on both the first and second floors

o in the staff lounge Room 205

o in the Black Box Theatre

o in the Scene Shop

(14)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

 Fire Sprinklers – Fire sprinklers are installed throughout the building, in each classroom and administrative space, in the corridors and throughout the support spaces. These are directly connected to the fire alarm system and will automatically be activated in the event of a fire.

Be careful not to hit any fire sprinkler head when moving tall objects in and out of rooms. Do not hang anything or attach anything to fire extinguisher heads.

(15)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

PLANS

The following pages include orientation plans for the new LACHSA building, including a Site Plan, First Floor Plan, Second Floor Plan and Third Floor Plan.

Site Plan shows:  site location

 footprint of the building

 CSULA parking lot in the North side of the building  exterior performance area on the South side of the building First Floor Plan shows:

 lobby / main entrance  administration / office area  girl’s and boy’s restrooms  staff restrooms

 twelve (12) classrooms (which include music technology computer lab Room #126)

 stairs and elevators Second Floor Plan shows

 staff lounge (Room #205)  girl’s and boy’s restrooms  eight (8) classrooms  two (2) dressing rooms  film studio & editing room  offices

Third Floor Plan shows

 Black Box Theatre & lobby  public restrooms

 scene shop

 dressing rooms

(16)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

(17)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

(18)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

(19)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

(20)

Staff Orientation Los Angeles County High School for the Arts (LACHSA)

QUICK REFERENCE CONTACTS Services:

 Network Systems – CSULA

 Telephone Systems – CSULA

 Security Camera System – LACOE contact: Matthew Jaffke, Administrative Analyst,

Facilities and Construction, Controller’s Office (562) 803-8447

 Building Services including Janitorial and Maintenance Services - LACOE contact:

Building Services, Facilities and Construction, Controller’s Office (562) 803-8280  Facilities Planning Services - LACOE contact: David Albright, AIA, Facilities Planning

Officer, Facilities & Construction, Controller’s Office (562) 803-8282 LACHSA Construction:

 Construction Management - LACOE contact: Vinceena Kelly, AIA, Construction

Management Officer, Facilities & Construction, Controller’s Office (562) 922-8950

 Construction and Facilities - LACOE contact: Jema Estrella, Assistant Director,

References

Related documents

Changes in organisation of instep kicking as a function of wearing compression and 3 textured materials 4 5 Abstract 6.. This study investigated effects of

Data was extracted for both high risk (HR) and low-risk (LR) HPV genotypes [ 50 ]. Studies reporting multiple infections with any HPV genotype were also extracted. Specimens

Using Aberdeen’s PACE framework, the overall survey group is driven to deploy ESBs and SOA technology to reduce IT complexity — and the costs of complexity — and the need to speed

NOTICE IS HEREBY GIVEN that an Application was made to the Department of State of the Commonwealth of Pennsylvania, at Harrisburg, PA, on May 8, 2013, by Construction and

This includes, but is not limited to, the recording of the attendance, the reconciliation of the attendance, daily interactions with teachers, security, and other school level staff

Yeas: Councillors Harris, Haywood, Kushner, Phillips, Siscoe, Sorrento, Stevens, Williamson, Bellows, Britton, Elliott, Garcia, and Mayor

The Contractors/ Vendors for the Fiber Infrastructure System, Security Camera System, Wireless Network System and the Data Network System shall coordinate and set up all System

NexCamera is a new surveillance, security camera system which can connect 100 IP NexCamera is a new surveillance, security camera system which can connect 100 IP NexCamera is a