• No results found

How to Plan, Design & Implement A Bad Schedule Lessons Learned: The Scheduler as Generalist

N/A
N/A
Protected

Academic year: 2021

Share "How to Plan, Design & Implement A Bad Schedule Lessons Learned: The Scheduler as Generalist"

Copied!
27
0
0

Loading.... (view fulltext now)

Full text

(1)

How to Plan, Design & Implement

A Bad Schedule

Lessons Learned: The Scheduler as Generalist

North Florida Section Meeting

Canaveral Council of Technical Societies

Cocoa Beach, FL

20 March 2014

John Orr, PSP

URS Corporation

(2)

Author Biography:  John P. Orr, PSP

Degrees / Certifications:BS Chemical EngineeringBA BiologyPSP, Planning & Scheduling Professional,  AACE InternationalUniversity:

Bucknell University “Ray, Bucknell …”

Years of Experience:29+ years, beginning in the golden days of yore, when scheduling was still  performed with IBM punch cards.  Worked for James J. O’Brien, O’Brien‐Kreitzberg & AssociatesProfessional Field & AffiliationsConstruction Management, including scheduling, cost control, value engineering,  project administration and claims analysis.North Florida Section President, AACE International.  Technical Board member.Something you do not know about me:

(3)

INTRODUCTION:

(4)

INTRODUCTION ‐ Purposes for the Schedule

In the Beginning, there was the CPM Network …

… and afterwards came the CPM Cost Estimate,

which did not appear until Chapter 14, page 163.

©McGraw‐Hill, 1971

Primary Purpose:  Planning Tool

• To plan and schedule the project work  sequence, • To support project management  during the construction phase, • To provide a “road map” for and  projections of Project Completion.

The focus is on the time element.

(5)

INTRODUCTION ‐ Purposes for the Schedule

Enhancements to the Planning Tool:

• Long‐lead Procurement activities to schedule delivery dates • Major equipment resources (cranes, hoists) scheduled based  on the construction activities they support • Work Breakdown by subcontract to allow the efficient staging  of subcontractors as work areas become available • Cost loading the contract value and projecting (planned)  expenditures over time • Resource loading of manpower, equipment, trades and  persons to report (and level) resource curves and peaks • Record‐keeping/Project Documentation for actual dates, log  records, and costs over time • Productivity calculations developed from resources over time

(6)

INTRODUCTION ‐ Purposes for the Schedule

Additional Competing Purposes

To Measure and Manage:

Time Coordination Cost Work Organization Earned Value Forecasting Resources Financial Planning Risk Record‐Keeping Information/Communication Dispute Resolution

Each individual purpose is well‐intended

Each technique or methodology places new 

requirements on the Schedule database

Stakeholders provide different input and usually 

expect different output and results

(7)

INTRODUCTION ‐ Purposes for the Schedule

The Key Role of the Scheduler:

To Facilitate Collaboration between the Stakeholders!

Project Managers Superintendents Cost / Budget Analysts Timekeepers Earned Value Specialists Financial Planners Risk Analysts VP for Equipment Designers Material Suppliers Subcontractors Cost Estimators Claims / Dispute Resolution Specialists Resources / Productivity Evaluation / Future Estimating

Takeaway:  The most common thread of failed 

projects and slipped schedules is inadequate 

collaborative planning

(8)

SCHEDULE DEVELOPMENT: 

P

ART

I ‐ T

HE

P

LANNING

P

ROCESS

or:

All Prior Planning Should Be 

Done in Advance

(9)

SCHEDULE DEVELOPMENT:  Planning

• What Can Go Wrong During the Planning Process?

– Stakeholder interests vary: • Some Use Schedules To Plan • Some Use Schedules To Control • Some Use Schedules To Monitor • Some Use Schedules To Generate Progress Payments • Some Use Schedules To Prepare Delay Claims (Is the schedule badly flawed or deliberately deceptive … you decide!) • Some Use Schedules To Defend Against Claims One Schedule Cannot Achieve All Ends With Equal Effectiveness! Some Stakeholder Goals and Interests Will Compete or Conflict!

The Scheduler Must Control Schedule Development

– Anything that detracts from the primary purpose, a tool to measure time, is  going to distort the time aspects and invalidate the completion projections

(10)

SCHEDULE DEVELOPMENT:  Planning

• The Cost Estimate/WBS and the Planning Process

The WBS Approach to Planning can be detrimental – The Cost Estimate and WBS presuppose that every work item is a deliverable • The Coordination of work items is the key effort in planning • The Schedule is the tool that models how the elements go together A Focus on Cost Management can be detrimental – Budget, work authorizations, tracking logs, delivery tickets/receiving reports,  inventory cost coding, schedule of values, earned value management,  accounting system and timekeeping input/output strain the schedule

• The Primary Interest of the Scheduler should be in the 

Project achieving its Time Objectives

– Are you a Planner? – Are you a Scheduler? – Are you a Project Controls Professional?

(11)

SCHEDULE DEVELOPMENT:  Planning

• A Bad Schedule Development Scenario:

Your business card says that are a Scheduler, 28 years old with a  Master’s degree in Construction Management – You are given the Cost Estimate (the winning cost estimate) and the WBS • Transfer the estimate and WBS into the scheduling software; • Create new activities floor‐by‐floor, or zone‐by‐zone and distribute the hours  from the cost estimate and add logic relationships; • Establish original durations using default crew sizes (or a template from a prior  project).  Run the first schedule calculation pass, then use the software’s  resource leveling functions to adjust the crew sizes until you get a smooth  resource usage curve that completes within the contract performance period. • Add in the front end mobilization activities (a fragnet from a previous project); • Add in the back end commissioning and closeout activities; • Add procurement of long lead items and link to the initial installation activities • Add constraints to make the bars appear where they belong What is wrong with this scenario?  The bar chart looks great!

(12)

SCHEDULE DEVELOPMENT:  Planning

• What are we missing?

Workflow!  Means and Methods!  What schedulers should do best! – We spent very little time on the core execution schedule elements (scope,  duration, relationship) – We have not focused on the transition points from one trade to another

Disturbing Observations:

1. The majority of large commercial and industrial projects finish  between 5‐10% longer than their planned project length. 2. A study of large infrastructure projects showed an average of  17% time overruns.  (Carson/Palmer Construction CPM Conference Session THU16)

3. Upwards of 90% of all actual durations are within +/– 5% of the  original durations.

(13)

SCHEDULE DEVELOPMENT: 

P

ART

B ‐ T

HE

P

LANNING

P

ROCESS

or:

(14)

SCHEDULE DEVELOPMENT:  

M

IND THE

G

AP

!

• Where do projects lose time?

– Process of elimination; if the activity durations are not the culprit … – What is the nature of the transition points (relationships) from one  activity to another?

Two activities: The Predecessor activity has a 20 

day duration, and subcontractor wants it at least 

25% complete before he starts his follow‐on:

Relationship link:  SS/+5

There is no clear scope associated with this relationship or 

the duration of the lag factor.

There is no reasonableness test we can use to check.

(15)

SCHEDULE DEVELOPMENT:  

M

IND THE

G

AP

!

A Start‐to‐Start/+5 link from Activity A to Activity B:

Activity B cannot start until some amount of productive 

work has been performed on Activity A.

This is the Productive Time Gap

Activity A [Wash Dishes] may have administrative predecessors: Access to dirty dishes Scrub pad Dish rack to drain dishes Dish soap Someone to wash the dishes  Water Activity B [Dry Dishes] may have administrative predecessors: Access to wet dishes Someone to dry the dishes Dishtowel Somewhere to put clean dishes

This is the basis of the Administrative Time Gap

(16)

SCHEDULE DEVELOPMENT:  

M

IND THE

G

AP

!

Failure to perform any of the administrative actions can 

easily preclude or delay either activity from starting or 

continuing to completion

The Administrative Time Gap in Construction

Construction activity administrative predecessors: – People to perform the work of the activity – Tools, equipment and materials – A place for the work to occur – Vital information

Example Administrative Time Gap / Delay

Activity A – Erect Hollow Metal Studs Activity B – Hang Drywall

(17)

SCHEDULE DEVELOPMENT:  

M

IND THE

G

AP

!

• What does this mean to a scheduler?

The daily work of the Project Manager and the Superintendents is  often quite independent of the project schedule.  They are  frequently focusing on Administrative Gap type items.

The daily priorities of the project management team do 

not appear to correlate to the priorities reflected in the 

schedule (indicated by the total float values).

• What value can the scheduler add?

Carson/Palmer Worst Scheduling Practice #9 –

Inconsistent Level of Detail Between the Trades

Orr Addendum: Evaluate the handoffs between the Trades

(18)

Bad Scheduling Practices

or:

What We Learned 

at the

(19)

Bad Scheduling Practices:  Dick Faris’ Eight Steps Backwards

Slipping Backwards – The Devolution of Scheduling:

1. Drag and Drop Gantt Charts; 2. Misuse of Constraints; 3. Lack of Logic Relationships; 4. Start‐to‐Start Ladders; 5. Bad Durations; 6. Improper Use of Lags (and no, he doesn’t know what SF is used for); 7. Lack of Training;

… And the worst problem?

8. L

ACK OF OWNERSHIP BY THE PROJECT PARTICIPANTS

(20)

Bad Scheduling Practices: Chris Carson/Glen Palmer

The Ten Worst Scheduling Practices Used Today:

10. Incomplete Scope & Logic – High Float Value activities 9. Inconsistent Level of Detail Between Trades 8. Misuse of Lag Factors 7. Failure to Update Periodically w/in Small Windows 6. Failure to Perform Time Impact Analysis of Delays 5. Lack of Schedule Risk Management 4. Poor Critical Path Analysis / Management 3. Lack of Resource Planning 2. Adjustments to Logic & Durations to Stay on Schedule 1. Failure to Perform Constructability Reviews

(21)

Bad Scheduling Practices:  Chris Carson/Glen Palmer

The Worst Schedule Development Failures:

10. Incomplete Scope & Logic – High Float Value activities 9. Inconsistent Level of Detail Between Trades 8. Misuse of Lag Factors 7. Failure to Update Periodically w/in Small Windows 6. Failure to Perform Time Impact Analysis of Delays 5. Lack of Schedule Risk Management 4. Poor Critical Path Analysis / Management 3. Lack of Resource Planning 2. Adjustments to Logic & Durations to Stay on Schedule 1. Failure to Perform Constructability Reviews

(22)

CONCLUSIONS

FOR

S

CHEDULE

D

EVELOPMENT

OR

:

W

HAT

D

OES THE

Y

OUNG

S

CHEDULER

T

AKE

H

OME FROM THE

C

ONSTRUCTION

CPM C

ONFERENCE

?

(23)

Conclusions and Guidance for Schedule Development

• But First, a Warning:  The Fallacy of Greater Detail

– The law of diminishing returns – One day duration activities are not good scheduling practice

• The Best Advice to a young Lieutenant

– Connect with your Sergeants (and Chiefs) – Goal: Prepare schedules that the Superintendents will use – Plan the Work, Work the Plan, Monitor and Revise the Plan – If the PM and Superintendent aren’t using it, Fix it!

• The Schedule is a Model of a Plan

– Make sure you understand the plan

• Don’t blame government specifications

– Make sure the schedule is the working schedule

(24)

Conclusions and Guidance for Schedule Development

• Fight for Prior Planning, Done in Advance

– Constructability Reviews – Schedule Risk Workshops  – If you can’t obtain them formally, prepare as if you were: • Add Risk Drivers/impact points to your schedule • Anything that can stop the project should be included

• Understand the Role of the Scheduler as Generalist

– Modeling the Plan means modeling the workflow, the  transitions between trades, collaboration of suppliers, trades,  commissioning agents – Workflow is the heart of the schedule – The schedule models the entire project scope, including third  party impact points and potential drivers that were not 

(25)

Conclusions and Guidance for Schedule Development

• Avail Yourself of the Resources & Experience of Others

– Construction CPM Conference  – AACE International Recommended Practices • Read them • Attend local Section meetings; discuss them • Help write and revise  them

• Remember that the Schedule is Irreplaceable

– The external inputs, outputs all require the establishment,  monitoring and adjusting of the time element of the project – None of them work without an accurate schedule

• Facilitating the collaboration and compilation of the 

inputs and experience of the project team is the 

(26)

Upcoming Annual Meetings 

Come to our 2014 AACE International annual meeting 

at the Sheraton New Orleans!

Industry focus at the next two annual meetings: 

• June 15‐18,  2014 – Energy/Oil & Gas – New Orleans

(27)

References

Related documents

Ade- más, los huesos humanos con mayor número de restos con identificación anatómica incompleta (vértebras, costillas o falanges) pueden sesgar este resultado, al no haberse

7.2.1 The notched bar impact properties of the material shall be determined by testing a set of three Charpy V-notch impact specimens for each heat at one of the standard

A rather different representation of the sacred tree and its goddess, also dating from the Nineteenth Dynasty, occurs on a limestone stela in the Cairo Museum.36 Here

Mechanics Phys 201 Phys — Electromagnetism Phys 202 Phys — Wave and Optics Phys 203 Phys — Experimental Physics I Phys 211 Phys — Experimental Physics II Phys 212 Phys —

• For failed migrations, the Migration Status Report provides a link to the Lifecycle Management e engine log file. The product Oracle Hyperion Enterprise Performance

SEE Tubbs' Sikorsky beyond Switek + Zito as it swoops from a higher altitude right past the Miami-Dade chopper, banks and dives for the

beyond initial acquisition to expand revenue by enabling adoption, consumption, retention— technical expertise must be part of the process More than anything else, success in the

“I believe,” said the Abbe, “that Miss Cunegonde has a great deal of wit, and that she writes charming letters?”.. “I have never received any from her,” said Candide,