• No results found

Exercise Objectives

In document TSCM42 (Page 37-43)

After completing this exercise, you will be able to:

• Create planned independent requirements.

Business Example

You create planned independent requirements for a material and display the result in the stock/requirements list.

Task:

You create planned independent requirements for the material T-SCM372-PP-##

and display them in the stock/requirements list.

1. Choose transaction MD61

(SAP menu: Logistics → Production → Production Planning → Demand Management → Planned Independent Requirements → Create) to create the following planned independent requirements:

Material: T-SCM372-PP-##

Plant: 1000

Define in the Planning Table quantities of 10 PC for the next month and the month after the next.

Save your planned independent requirements.

2. Choose transaction MD04

(SAP menu: Logistics → Production → Production Planning → Demand Management → Environment → Stock/Requirements List) to display the stock/requirements list for:

Material: T-SCM372-PP-##

Plant: 1000

The list contains the planned independent requirements for material T-SCM372-PP-## together with the requirement quantities and requirement dates.

It also provides information on the quantities that are available today and on the requirements dates.

Solution 1: Demand Planning

Task:

You create planned independent requirements for the material T-SCM372-PP-##

and display them in the stock/requirements list.

1. Choose transaction MD61

(SAP menu: Logistics → Production → Production Planning → Demand Management → Planned Independent Requirements → Create) to create the following planned independent requirements:

Material: T-SCM372-PP-##

Plant: 1000

Define in the Planning Table quantities of 10 PC for the next month and the month after the next.

Save your planned independent requirements.

a)

-2. Choose transaction MD04

(SAP menu: Logistics → Production → Production Planning → Demand Management → Environment → Stock/Requirements List) to display the stock/requirements list for:

Material: T-SCM372-PP-##

Plant: 1000

The list contains the planned independent requirements for material T-SCM372-PP-## together with the requirement quantities and requirement dates.

It also provides information on the quantities that are available today and on the requirements dates.

a)

-Exercise 2: Material Requirements Planning

Exercise Objectives

After completing this exercise, you will be able to:

• Perform a planning run.

• Evaluate the planning result.

Business Example

You will run material requirements planning for your material and display the resulting planned orders in the stock/requirements list.

Task:

You carry out a multilevel single-item planning for your material T-SCM372-PP-##

and display the resulting planned orders in the stock/requirements list.

1. Choose transaction MD02

(SAP menu: Logistics → Production → MRP → Planning → Multilevel Single-Item Planning) to carry out a multilevel single-item planning run for:

Material: T-SCM372-PP-##

Plant: 1000

You don’t have to set or change any planning parameters. Press Enter twice to start the planning run.

2. Choose transaction MD04

(SAP menu: Logistics → Production → MRP → Evaluations → Stock/Requirements List) to display the stock/requirements list for:

Material: T-SCM372-PP-##

Plant: 1000

As a result of the MRP run, the system created planned orders to cover the planned independent requirements.

Solution 2: Material Requirements Planning

Task:

You carry out a multilevel single-item planning for your material T-SCM372-PP-##

and display the resulting planned orders in the stock/requirements list.

1. Choose transaction MD02

(SAP menu: Logistics → Production → MRP → Planning → Multilevel Single-Item Planning) to carry out a multilevel single-item planning run for:

Material: T-SCM372-PP-##

Plant: 1000

You don’t have to set or change any planning parameters. Press Enter twice to start the planning run.

a)

-2. Choose transaction MD04

(SAP menu: Logistics → Production → MRP → Evaluations → Stock/Requirements List) to display the stock/requirements list for:

Material: T-SCM372-PP-##

Plant: 1000

As a result of the MRP run, the system created planned orders to cover the planned independent requirements.

a)

-Exercise 3: Production Order Creation

Exercise Objectives

After completing this exercise, you will be able to:

• Perform a planned order conversion.

Business Example

You will convert one of your planned orders to a production order.

Task:

You convert one of your planned orders to a production order in the stock/requirements list.

1. Choose transaction MD04

(SAP menu: Logistics → Production → Shop Floor Control → Control → Stock/Requirements List) to display the stock/requirements list for:

Material: T-SCM372-PP-##

Plant: 1000

2. Double-click the MRP element PlOrd for the first planned order.

Choose button → Prod.Ord. in the dialog box Additional Data for MRP Element.

The planned order will be converted to a production order. Save your production order.

After saving, the stock/requirements list appears again. Choose the Refresh icon.

The new production order is displayed as a new MRP element. The order number is displayed in the data on the MRP element. The original planned order was deleted after the conversion.

Solution 3: Production Order Creation

Task:

You convert one of your planned orders to a production order in the stock/requirements list.

1. Choose transaction MD04

(SAP menu: Logistics → Production → Shop Floor Control → Control → Stock/Requirements List) to display the stock/requirements list for:

Material: T-SCM372-PP-##

Plant: 1000

a)

-2. Double-click the MRP element PlOrd for the first planned order.

Choose button → Prod.Ord. in the dialog box Additional Data for MRP Element.

The planned order will be converted to a production order. Save your production order.

After saving, the stock/requirements list appears again. Choose the Refresh icon.

The new production order is displayed as a new MRP element. The order number is displayed in the data on the MRP element. The original planned order was deleted after the conversion.

a)

In document TSCM42 (Page 37-43)

Related documents