5 Designing and Developing VisiLean: A Production Management System
5.1 Designing the framework
5.1.1 Gathering Feedback from Practitioners
In addition to feedback received during workshops and demonstrations, feedback was also gathered during a pilot project, which was carried out on a Highway Automation project (where traffic management infrastructure were being installed) in the UK.
Although the workshops and meetings did not follow a structured questionnaire approach and were mostly open-‐ended discussions, where possible following questions were asked while gathering feedback.
• What challenges are being faced (technical and process related) while
implementing the production management system
• What BIM solutions are being used to support the production
management system
• Are you using Lean Production Management techniques on your
project(s)?
o If so, do you think they are adequately supported through existing Information Systems?
• Do you use BIM on your projects?
o If so, are you using BIM for production management and to support lean processes?
The following paragraphs outline the main feedback received during the initial feedback sessions.
5.1.1.1 Production management systems mostly rely on manual information retrieval
Even after almost two decades following the launch of International Group for Lean Construction and numerous construction organisations around the world having adopted lean practices, hardly any software systems exist that specifically support the lean production process. Collaborative planning sessions, namely reverse phase scheduling, look-‐ahead planning and weekly/commitment planning rely mostly on manual processes where stakeholders use Post It™ notes or similar devices to plan and sequence construction activities. Following from
the planning sessions, the information is mostly managed using paper based plans or at most Excel spread sheets or similar systems.
Observed by the author, on two UK based projects where collaborative planning was implemented, besides following the Post It™ method, five separate spread sheets were being maintained, along with three paper based registers to collect and manage information from the planning meetings. This was in addition of the project planning and scheduling system Primavera Project Planner, and Enterprise Information Management system. None of these systems were integrated with each other causing a significant amount of data re-‐entry. Use of such a system is inefficient as it cannot easily integrate information from other management systems and is not standardised across projects.
Another key issue that was highlighted by the practitioners was that little auditing is possible with the current systems, i.e. when key decisions are made regarding (re) scheduling tasks, reallocating resources, etc., it is currently not possible to record such decisions. Hence, it is not possible to track the performance of the project and link back to these decisions and learn from it (i.e. whether it impacted positively or negatively). Similarly, reports such as the PPC (Percentage Plan Complete) and Reasons for Non Completion are created manually either by the site manager or by the site planner. The data is collected manually and such reports are prepared in Excel. Such tasks are very time consuming and as a result costly.
5.1.1.2 Use of BIM is still limited to Clash Detection and 4D
It was observed through all interviews and workshops that the participants felt that the availability of BIM model provides them a significant opportunity to use it throughout the construction project. Although use of BIM is increasing on the construction site, it is still limited to basic 4D simulation where a master plan is attached to the model and the project schedule can be simulated in 3D at a macro level. There are some systems, which enable detailed resource management and 5D planning, however these systems are highly complicated and rely on dedicated system operatives who have been trained to use these systems. Due to this high level of training and skill required and relatively high cost of
implementation, it is not possible to yet implement these systems across the whole supply chain so that they can be used throughout the construction process. As a result, these are mostly used during the initial stages of the project to develop detailed schedules, but not during the production management operations.
It emerged from the interviews that two organisations were already using BIM during their collaborative planning sessions. However, this was achieved by having a dedicated BIM manager who helped with the navigation of the BIM model while the tasks are being discussed during the collaborative planning session. When these BIM managers were interviewed, it was mentioned that due to the lack of direct connection between the planning tasks and BIM system, the navigation becomes a difficult activity and sometimes results in longer than usual time taken to carry out these meetings.
5.1.1.3 Field BIM is now increasingly becoming accessible due to advanced hardware and maturing/new software
Use of BIM technology on construction sites is increasing due to the advantages that it provides such as physical and process clash detection as well as clarity on the design intent. Some case studies such as Castro Valley project (Khemlani, 2009) and Maryland General Hospital (Eastman et al., 2011) are such examples where BIM has been utilised quite successfully along with other tools and techniques such as lean construction. In two case studies the author observed, one in Chicago, US and other in Bristol, UK, it was found that a workstation (high end computer) was made available to construction teams to access BIM models during execution. This enabled the workers to gain a better understanding of what is to be constructed (i.e. task at hand) and reduced the need for supervisory communication. However, as the BIM models are only the partial representation of the project (i.e. only the product model), the process side was not available in the same interface.
It was also found that construction companies were looking for innovative solutions to take BIM to the worksite using mobile technologies, however were restricted by the options available to them. There are currently only a couple of
software platforms such as Vela systems (now acquired by Autodesk) and Artra (in the UK) that offer field management of construction using mobile devices and also partial integration with BIM model.
5.1.1.4 Summary of feedback
Although the popularity of BIM is increasing on construction projects, from the user workshops and interviews, it was found that not many software systems exist that go beyond macro level 4D planning. Hence, construction personnel are left to devise their individual solutions on their own. In case of some organisations, they hire a trained BIM technician or architect to personally facilitate use of BIM during daily construction activities and other planning sessions, however, this is yet to become an industry wide practice, and one that is not yet supported by commercially (or otherwise) available systems.