• No results found

Shortcomings of the current design and product modelling systems:

3   Problems with the Production Management Systems: Understanding the problem and the context

3.4   Information and Communication System Problems in Construction

3.4.1   Shortcomings of the current design and product modelling systems:

Construction   drawings   (2D)   have   been   traditionally   considered   to   be   a   language   with  which  professionals  within  construction  industry  communicate.  In  the  1760s,   a   precise   standardised   method   for   representing   three   dimensional   objects   called   descriptive   geometry   in   two   dimensions   was   developed   by   the   Frenchman  

Gaspard  Monge  (Koskela  et  al.,  2010).  The  method  was  deemed  so  powerful  that  it   was  kept  in  secrecy  for  many  years,  and  Monge  published  the  details  only  in  1799   (Kant,  1799).  Since  then,  descriptive  geometry  has  been  the  basis  for  construction   design   drawings.   Together   with   written   description,   such   as   bills   of   materials,   drawings  have  been  used  to  represent  the  object  to  be  built,  both  for  contractual   purposes  and  for  site  execution  (Koskela  et  al.,  2010).  

A   number   of   Computer   Aided   Design   (CAD)   software   have   been   developed   over   the  years,  which  facilitate  generation  and  distribution  of  drawings.  However,  due   to  the  fragmentation  prevalent  in  the  construction  industry,  the  ability  to  interpret   these  drawings  on  a  project  varies  from  one  subcontractor  to  the  other.  Also,  due   to  increasing  complexity  of  building  systems,  drawings  have  become  much  difficult   to  interpret  even  for  the  technically  competent.  Computer  Aided  Design  does  not   intrinsically   support   generation   of   intelligent   design,   whereas   the   objects   contained   within   the   drawings   demonstrate   behavioural   patterns   and   where   design  objects  can  be  controlled  in  a  parametric  way.    

Current   practice   in   using   2D   CAD   is   that   the   designers   and   engineers   develop   solutions   independent   of   each   other.   However,   there   is   no   potential   solution   to   automatically   check   the   design   for   consistency,   and   due   to   complexity   of   design,   manual  checking  is  quite  difficult.  This  leads  to  design  errors  and  inconsistencies,   which   are   then   identified   on   site   and   are   costly   to   fix.   Also,   it   is   not   possible   to   automate  tasks  such  as  fabrication  using  CNC  systems  using  CAD  drawings,  or  to   check   the   design   for   potential   clashes   between   various   components   such   as   building   structure   and   facilities.   It   is   also   not   possible   to   build   fail-­‐safe   rules   (design  templates  to  ensure  standard  conformance)  using  2D  CAD  systems.  

On  the  contrary,  object  oriented  design  development,  which  is  offered  by  Building   Information   Modelling   software,   is   capable   of   representing   intelligent   behaviour   and  can  integrate  a  multitude  of  information  from  various  sources.  (Eastman  et  al.   2008).  

The   problems   with   the   traditional   2D   CAD   technologies   during   the   construction   project   lifecycle   are   discussed   below.   The   stages   described   below   could   be   different   in   sequence   depending   on   the   type   of   the   contractual   agreement,   for  

example   Design-­‐Bid-­‐Build   or   Design-­‐Build.   In   Design-­‐Build   and   partnership   projects,  some  of  the  inefficiencies  of  the  traditional  process  described  below  are   taken  care  of,  however,  the  critical  inefficiencies  related  to  the  production  phase   most  likely  remain.    

3.4.1.1  Problems  during  Pre-­‐Construction    

The   key   goal   of   the   conceptual   design   stage   is   to   capture   the   functional   and   aesthetic  requirements  from  the  client  and  translate  that  into  design  intent.  This   makes   design   a   highly   iterative   process,   where   initially   a   significant   amount   of   refinement  is  taking  place  and  client  input  is  being  taken  into  account.  The  current   paper  based  process  leads  to  significant  inefficiencies,  as  it  is  not  easy  to  interpret   and   communicate   the   design   intent   about   a   three   dimensional   space   in   a   two-­‐ dimensional  drawing  (potentially  for  an  untrained  eye  of  the  client).  Also,  through   the  paper-­‐based  process,  critical  project  based  information  such  as  cost  estimates   and   performance   evaluation   (such   as   energy,   acoustics,   structural,   thermal,   etc.)   has   to   be   carried   out   post   design   and   manually.   Often,   when   inefficiencies   are   found   with   the   design,   it   is   too   late   to   make   a   change,   which   then   leads   to   compromises  with  client’s  original  intentions.    

3.4.1.2  Problems  during  Tendering  and  Bid  Process    

Traditional  contracts  based  on  the  lowest  bid,  involve  a  strenuous  bidding  process,   where  contractors  spend  at  least  1%  of  the  estimated  project  costs  on  compiling   bids   (Eastman   et   al.,   2011).   These   bids   are   developed   using   paper   based   or   electronic  2D  drawings,  where  manual  extraction  of  quantities  and  interpretation   of  design  is  required.  As  a  result,  significant  amount  of  time  and  effort  is  required   in  preparing  the  bid.  If  we  consider  a  contractor’s  hit  rate  as  20%  (i.e.  they  win  1   job  for  every  5  bids),  the  1%  of  bid  development  cost  gets  added  to  the  overheads.   Also,   due   to   major   inconsistencies   in   design,   a   significant   amount   of   RFIs   are   generated  even  during  the  bid  stages  as  the  main  contractor  has  to  take  input  from   their  supply  chain  to  arrive  at  a  final  cost.  

3.4.1.3  Problems  during  Design  and  Detail    

Developing  a  detailed  design  is  a  highly  collaborative  and  iterative  process,  where   a   number   of   design   consultants   contribute   towards   the   final   design.   The   current   2D   CAD   and   design   processes   do   not   lend   themselves   for   collaborative   design   development.  Most  commonly  an  over-­‐the-­‐wall  approach  is  taken  towards  design   where  each  consultant  (Architect,  Structural,  MEP,  etc.)  develops  their  respective   design  and  passes  it  to  the  next  as  an  input.  This  makes  the  process  a  very  lengthy   and  costly.  Also,  due  to  the  fragmented  nature  of  design  development,  many  issues   related   to   physical   clashes   between   different   design   elements   (i.e.   architectural   and   structural   or   structural   and   MEP   etc.)   remain   undetected   until   the   construction   stage   of   the   project.   This   leads   to   either   rework   or   lengthy   delays   during  the  construction  process.  

A   study   carried   out   by   Freire   and   Alarcón   (2002)   diagnosed   and   evaluated   the   traditional   design   process   for   three   projects   of   a   design   consultant.   The   authors   used  lean  principles  to  identify  wastes  present  within  the  process  and  found  the   main  wastes  occurring  within  the  process  to  be:  

1. Ignorance  of  client  requirements;   2. Bureaucracy  and  paper  work;   3. Interdisciplinary  coordination;   4. Information  not  available;  and   5. Rework.  

Freire   and   Alarcón   (2002)   also   identified   time   distribution   in   traditional   design   process  as  shown  in  Table  3  below:  

Table  3.  Distribution  of  time  in  design  tasks  (Freire  and  Alarcón,  2002).  

Category Duration (%) Designing 50.2 Verifying information 8.2 Collecting information 28.1 Correcting information 12.2 Issuing 1.4

The  results  from  table  above  clearly  show  that  the  value  adding  activity  of  actual   design  work  contributes  to  only  50.2%  time  spent  on  this  overall  process,  where   the  rest  constitute  wasteful  tasks.  

3.4.1.4  Problems  during  Construction  Phase    

It  is  during  the  construction  stage  that  the  inefficiencies  of  the  traditional  design   cause  the  biggest  problems  (Eastman  et  al.,  2011,  Kymmell,  2008).    

Rework  due  to  inaccuracies  or  lack  of  detail:  As  the  design  is  not  normally   checked   for   constructability   and   refined   for   execution,   a   thorough   review   takes  place  early  in  the  project  to  identify  errors  and  omissions.    

Lack   of   support   for   Prefabrication:   Also,   the   lack   of   automation   and   parametric   abilities   of   the   2D   design   makes   is   difficult   to   support   a   prefabrication   strategy;   hence   most   of   the   components   have   to   be   constructed  on  site,  leading  to  inefficiencies.    

Clashes   leading   to   rework:   Two   types   of   clashes   could   occur,   physical   clashes;  i.e.  construction  elements  clashing  with  each  other  as  design  hasn’t   been   refined   or   process   clashes;   where   the   work   sequence   hasn’t   been   properly  planned  due  to  lack  of  visualisation.  This  causes  either  a  delay  in   work  or  complete  rework  of  construction  elements.  

Drawing   Management:   Drawing   or   design   issue   management   becomes   highly  complex  and  inefficient  in  a  2D  CAD/  paper  based  process.  This  leads   to   not   only   inefficiencies   on   construction   projects,   but   also   causes   safety   issues   as   probability   of   subcontractors   working   with   a   wrong   revision   of   drawings  increases.  On  a  case  study  A  a  major  accident  happened  where  a   subcontractor  used  an  old  revision  of  drawing  to  construct  a  concrete  slab.   This   led   to   the   failure   of   the   slab   and   injury   of   two   personnel.   The   subcontractor   claimed   that   they   had   not   received   the   latest   copy   of   the   drawing.  Also,  on  an  average  it  was  found  for  company  A  that  the  expenses   for   postage   and   scanning   of   paper   drawings   were   in   the   region   of   £200-­‐ £300  (excluding  personnel  costs).  

Visualisation   of   design   during   planning:   It   is   highly   important   that   the   production   teams   and   project   managers   are   familiar   with   the   design   and  

complexity   of   tasks   while   planning   and   scheduling   production   tasks.   However,  with  2D  drawings  it  becomes  quite  difficult  to  visualise  3D  spaces   and   how   the   production   will   happen   over   a   timeline,   especially   if   it   is   a   complex   structure.   Also,   quite   often   it   is   realised   during   the   project   that   required  information  from  drawings  and  specifications  is  either  missing  or   not   clear.   This   leads   to   significant   number   of   Requests   for   Information   (RFIs)  being  sent  to  and  from  the  project.  It  is  widely  documented  that  RFIs   lead  to  major  inefficiencies  during  a  construction  project.  

3.4.1.5  Problems  with  Handover  and  Post  Construction     There  are  two  important  issues  the  project  has  to  address:  

• Handing  over  an  accurate  record  and  information  about  the  facility  to  the   owner  

• Ensuring   the   information   handed   over   supports   effective   operation   and   maintenance  of  the  facility  

Normally  at  the  end  of  a  project,  all  the  as-­‐built  information  is  sorted  and  archived   in  boxes,  which  are  then  handed  over  to  the  client.  However,  as  the  information  is   mostly  recorded  on  paper,  this  resource  is  hardly  ever  used  or  synchronized  with  a   client’s   facilities   management   system   as   demonstrated   in   the   Maryland   General   Hospital  case  study,  which  was  documented  by  the  author  (Eastman  et  al.,  2011).   The  following  observations  were  made  in  the  case  study:  

• The   lifecycle   of   the   equipment   was   not   optimized,   i.e.   the   facitilities   management   system   did   not   take   into   consideration   issues   such   as   maintenance  intervals,  servicing,  etc.    

• Warranty  and  other  product-­‐related  information  were  not  easily  accessible.   • No  ready  inventory  of  equipment  was  available.  

The  resulting  processes  are  quite  informal  and  dependent  on  knowledge  gathered   by  experienced  staff  members  about  the  facilities  operations  over  the  years.  As  a   result,   the   hospital   ends   up   spending   considerable   resources   on   Facilities   Management   but   does   not   get   the   results   it   needs.   The   BIM-­‐enabled   process   for   recording  and  delivering  as-­‐built  information  offered  an  opportunity  to  record  and  

provide  accurate  as-­‐built  information,  in  a  form,  which  helps  maintain  and  manage   the  facilities  in  an  efficient  way  and  increase  the  lifecycle  of  the  building.